Duber Khwar Hydroelectric Plant

From Wikipedia, the free encyclopedia
Duber Khwar Hydropower Plant
Duber Khwar Hydroelectric Plant is located in Pakistan
Duber Khwar Hydroelectric Plant
Location of Duber Khwar Hydropower Plant in Pakistan
Official nameDuber Khwar Hydropower Plant
LocationPattan, Kohistan, KPK, Pakistan
Coordinates35°7′9.82″N 072°55′38.51″E / 35.1193944°N 72.9273639°E / 35.1193944; 72.9273639Coordinates: 35°7′9.82″N 072°55′38.51″E / 35.1193944°N 72.9273639°E / 35.1193944; 72.9273639
StatusOperational
Construction beganJune 2003
Opening dateJune 2013
Owner(s)Water and Power Development Authority (WAPDA)
Dam and spillways
Type of damGravity, roller-compacted concrete
ImpoundsDuber Khwar River
Height40.5 m (133 ft)
Length202 m (663 ft)
Duber Khwar Hydroelectric Plant
Coordinates35°6′17.98″N 72°59′39.02″E / 35.1049944°N 72.9941722°E / 35.1049944; 72.9941722
Operator(s)WAPDA
Commission dateJanuary 2014
Turbines2 x 65 MW Pelton-type
Installed capacity130 MW
Annual generation595GWh

Duber Khwar Hydropower Plant is located near the town of Pattan in Kohistan, Khyber Pakhtunkhwa, Pakistan on the , a right bank tributary of Indus River. It is approximately 300 km NW from Islamabad, the federal capital of Islamic Republic of Pakistan.[1]

The total electricity generation capacity of the Duber Khwar Project is 130 MW.[2] There are two vertical Pelton wheel turbine units of 65 MW each installed at Duber Khwar Hydroelectric Station. These turbines are manufactured by Andritz Hydro Austria.[3] Andritz Hydro Austria has supplied and installed the complete electro-mechanical equipment and services with the focus on its "water to wire" concept. The supplies consisted of two 65 MW Pelton-type turbines with a rated head of 516 m, associated generators and generator auxiliaries and the complete electrical power systems.[4]

Construction of Duber Khwar Hydropower Plant was commenced in June 2003 and the project was completed in June 2013. The plant began commercial operation in January 2014.[5] The total cost of the project is about PKR 16.325 billion. Prime Minister Nawaz Sharif is likely to inaugurate the Duber Khwar hydropower project soon. Environment-friendly Duber Khwar hydropower project will generate 595 million units of low-cost hydel electricity per annum.[6]

Dam[]

Type: Concrete gravity dam
Length: 202 m.
Height: 40.5 m.
Design Discharge: 29 Cusecs
Headrace Tunnel Length: 4.873 km
Design Head: 535 m.[7][8]

See also[]

References[]

Map all coordinates using: OpenStreetMap 
Download coordinates as: KML
  1. ^ "Archived copy". Archived from the original on 2014-07-07. Retrieved 2014-03-22.CS1 maint: archived copy as title (link)
  2. ^ "Archived copy". Archived from the original on 2014-07-07. Retrieved 2014-03-22.CS1 maint: archived copy as title (link)
  3. ^ "Your Dedicated Source of Hydropower News".
  4. ^ "30MW Duber Khwar hydropower project starts test production". 4 January 2014.
  5. ^ "First unit at Pakistan's 130-MW Duber Khwar hydroelectric plant generating power". Hydroworld.com. 6 January 2014.
  6. ^ "Archived copy". Archived from the original on 2014-03-22. Retrieved 2014-03-22.CS1 maint: archived copy as title (link)
  7. ^ http://eng.sinohydro.com/index.php?m=content&c=index&a=show&catid=42&id=105
  8. ^ "Archived copy". Archived from the original on 2014-07-07. Retrieved 2014-03-22.CS1 maint: archived copy as title (link)
Retrieved from ""