HVDC BorWin1
This article needs additional citations for verification. (October 2009) |
HVDC BorWin1 | |
---|---|
Location | |
Country | Germany |
Coordinates | 54°21′15″N 6°01′30″E / 54.35417°N 6.02500°E 53°7′31″N 7°18′33″E / 53.12528°N 7.30917°E |
General direction | north–south |
From | Platform BorWin Alpha |
Passes through | North Sea |
To | Diele substation |
Ownership information | |
Operator | TenneT |
Construction information | |
Manufacturer of conductor/cable | ABB |
Manufacturer of substations | ABB |
Construction started | 2007 |
Commissioned | 2009 |
Technical information | |
Type | submarine cable, subsoil cable |
Type of current | HVDC |
Total length | 200 km (120 mi) |
Power rating | 400 MW |
AC voltage | 170 kV (Platform BorWin Alpha), 380 kV (Diele) |
DC voltage | ±150 kV |
No. of circuits | 1 |
HVDC BorWin1 is the first HVDC facility in the world to be built for importing power from an offshore wind park to shore, and the first to use voltage source converters (VSC) in Germany. It connects the offshore wind park BARD Offshore 1 and other offshore wind farms in Germany near Borkum to the European power grid. The facility was built by ABB and has a capacity of 400 MW at a bipolar voltage of ±150 kV. HVDC BorWin1, which leads from BorWin Alpha Offshore Platform to Diele substation, consists of a 75 kilometres (47 mi) of underground and 125 kilometres (78 mi) of submarine cable.
Unlike the later (and more powerful) HVDC connections that have been built for transmitting wind power to shore in Germany, Borwin 1 uses two-level converters in which several hundred IGBTs are connected directly in series in each valve. Pulse-width modulation (PWM) is used to improve the level of harmonics but filtering is still needed. One converter is provided at each end of the link, in the symmetrical monopole configuration.
Borwin 1 is operated by the German Transmission System Operator TenneT (formerly Transpower Stromübertragungs GmbH).[1][2] and construction and commissioning were completed in 2009, although the project has had many technical difficulties since that date. In March 2014 a fire on the platform caused the scheme to be shut down for several months. [3]
Sites[]
Site | Coordinates |
---|---|
Diele Static Inverter Plant | 53°7′31″N 7°18′33″E / 53.12528°N 7.30917°E |
Borkum 2 platform | 54°21′15″N 6°01′30″E / 54.35417°N 6.02500°E |
BorWin Alpha[]
BorWin Alpha is the first HVDC converter station in the world to be installed on an offshore platform. It is located in the wind power farms of the German Bight in the North Sea.
BorWin Alpha converts the power generated in offshore wind park BARD 1 into direct current at a voltage of 150 kV for HVDC-transmission to Diele. Operating as static inverter valves, the station BorWin alpha uses not thyristors, but IGBT elements.
BorWin alpha was built in a shipyard in Vlissingen, Netherlands with electrical equipment from ABB. The equipment was dragged with the SSCV Thialf to the place of assembly and installed at the end of May and the beginning of June 2009. The overall height of BorWin alpha is 84 metres, from which 62 metres come from the carrying construction, the so-called Jacket. The weight of the entire platform is 5000 tons. Of this 1800 tons come from the Jacket.
References[]
- ^ "BorWin1". ABB. Retrieved 2011-08-08.
- ^ Constantijn Steinhusen (2009-11-01). "North Sea Wind Power Comes Ashore". Transmission & Distribution World. Penton Media, Inc. Retrieved 2010-03-01.
- ^ 'Dirty electricity' probe at BorWin1 Archived 2014-10-15 at the Wayback Machine, RE News, 11 June 2014.
External links[]
- Grid connection BorWin1 (transpower)
- BorWin 1 HVDC system, CIGRÉ Compendium of all HVDC Projects.
- Entry on structurae.net
- Entry on 4coffshore
- Electric power transmission systems in Germany
- Energy infrastructure completed in 2009
- HVDC transmission lines
- Electrical interconnectors in the North Sea
- 2009 establishments in Germany