JLOS House Project

From Wikipedia, the free encyclopedia
JLOS Towers
JLOS House Project is located in Kampala
JLOS House Project
Location within Kampala
General information
TypeGovernment Offices
Location98-102 Katalima Road
Naguru, Kampala
Uganda
Coordinates0°20′28″N 32°36′39″E / 0.341114°N 32.610832°E / 0.341114; 32.610832Coordinates: 0°20′28″N 32°36′39″E / 0.341114°N 32.610832°E / 0.341114; 32.610832
Construction started2021 (Expected)
Completed2023 (Expected)
Technical details
Floor area80,000 square metres (861,113 sq ft)
Design and construction
ArchitectFBW Architects

The JLOS House Project, is a proposed three-component government office development project in Uganda's capital city of Kampala, to house the offices of the Justice, Law and Order Sector (JLOS). The three components of the project are:[1][2][3]

  • JLOS Towers, an 80,000 square metres (861,113 sq ft) office complex to house the headquarters of more than a dozen law enforcement and social services government departmental offices.
  • Uganda Police Headquarters, a modern building to house the headquarters of the Uganda Police Force.
  • Renovation, refurbishment and enlargement of existing office buildings that house the Courts of Appeal and headquarters of the Judiciary, to also accommodate the Uganda Supreme Court.

Location[]

The first component of the project is the JLOS Towers to be located at 98-102 Katalima Road, in the Naguru neighborhood, in the Nakawa Division of Kampala, about 6 kilometres (4 mi), northeast of the city's central business district.[4] The coordinates of the JLOS Towers would be 0°20'28.0"N, 32°36'39.0"E (Latitude:0.341114; Longitude:32.610832).[5]

The second component in the project, is the headquarters of the Uganda Police Force, to be constructed immediately south of the JLOS Towers, at 40-96 Katalima Road, Naguru.

The third component is the renovation, refurbishment and enlargement of existing office buildings that house the Courts of Appeal and headquarters of the Judiciary, to accommodate the Uganda Supreme Court, currently housed in a building on Upper Kololo Terrace on Kololo Hill. That location is in the centre of the city, bounded by Lumumba Avenue to the north, Buganda Road to the south, Square One to the west and Square Two to the east. The coordinates of this location are: 0°18'56.0"N, 32°34'46.0"E (Latitude:0.315556; Longitude:32.579438).[6]

Overview[]

JLOS Towers is planned to house the following government departments, currently scattered in different locations across the city:[7]

  1. The headquarters of the Uganda Ministry of Justice and Constitutional Affairs
  2. The Uganda High Court
  3. The Uganda Ministry of Internal Affairs
  4. Offices of Uganda Human Rights Commission
  5. Headquarters of Uganda Prison Services
  6. Headquarters of Uganda Registration Services Bureau
  7. The Justice, Law and Order Sector Secretariat
  8. Offices of Uganda Law Reform Commission
  9. Headquarters and offices of The Directorate of Public Prosecution
  10. Offices of the Judicial Service Commission
  11. Uganda Ministry of Gender, Labor and Social Development
  12. Headquarters of Uganda Tax Appeals Tribunal
  13. Headquarters of the Centre for Arbitration and Dispute Resolution
  14. The Uganda Directorate of Citizenship and Immigration Control.

Construction[]

In August 2015, following open international bidding, a consortium led by TWED Property Development Limited of Uganda and G5 Property Development Limited of South Africa was selected to design, develop, construct and manage the project in a public-private partnership (PPP) arrangement. The other members of the consortium include FBW Architects and ROKO Construction Company. Financing will be provided by Standard Bank of South Africa and Stanbic Bank Uganda.[8] Construction was expected to commence in 2016.[1]

In June 2021, the Daily Monitor reported that construction would start in the second half of calendar year 2021 and last 24 months. The contract price is quoted as USh213 billion (approx. US$60.2 million), at that time.[9]

See also[]

References[]

  1. ^ a b JLOS (18 June 2016). "Special Report on the JLOS House Project". Kampala: JLOS House Project. Archived from the original on 30 June 2016. Retrieved 18 June 2016.
  2. ^ Press Release (12 August 2015). "JLOS House Project preferred bidder named". Kampala: Uganda Law Reform Commission. Retrieved 18 June 2016.
  3. ^ Kashaka, Umaru (3 May 2014). "New Supreme Court Building to Cost Sh303 Billion". New Vision. Kampala. Retrieved 18 June 2016.
  4. ^ Globefeed.com (18 June 2016). "Distance between Post Office Building, Kampala Road, Kampala, Central Region, Uganda and Katalima Bend, Kampala, Central Region, Uganda". Globefeed.com. Retrieved 18 June 2016.
  5. ^ Google (18 June 2016). "Location of Proposed JLOS Towers, Naguru, Kampala, Uganda" (Map). Google Maps. Google. Retrieved 18 June 2016.
  6. ^ Google (18 June 2016). "Location of the Headquarters of the Uganda Judiciary, Kampala" (Map). Google Maps. Google. Retrieved 18 June 2016.
  7. ^ ULRC (9 October 2013). "JLOS House Complex Construction". Kampala: Uganda Law Reform Commission (ULRC). Retrieved 18 June 2016.
  8. ^ Press Release (12 August 2015). "JLOS House Project preferred bidder named". Kampala: Uganda Law Reform Commission. Retrieved 18 June 2016.
  9. ^ Anthony Wesaka (28 June 2021). "Construction of Shs213b Justice house set to start". Daily Monitor. Kampala. Retrieved 30 June 2021.