Nant de Drance Hydropower Plant

From Wikipedia, the free encyclopedia
Nant de Drance
Lac Emosson Picswiss.jpg
Lac d'Emosson forms the lower reservoir
CountrySwitzerland
LocationFinhaut, Saint-Maurice, Valais
Coordinates46°3′49.18″N 6°54′39.73″E / 46.0636611°N 6.9110361°E / 46.0636611; 6.9110361Coordinates: 46°3′49.18″N 6°54′39.73″E / 46.0636611°N 6.9110361°E / 46.0636611; 6.9110361
StatusUnder construction
Construction beganSeptember 2008
Opening date2021
Construction costUS$2.1 billion (CHF 1.9 billion, 1.5 billion)
Owner(s)Nant de Drance SA
Upper reservoir
CreatesLac du Vieux Emosson
Total capacity25,000,000 m3 (20,000 acre⋅ft)
Lower reservoir
CreatesLac d'Emosson
Total capacity227,000,000 m3 (184,000 acre⋅ft)
Power Station
Hydraulic head425 m (1,394 ft)
Pump-generators6 x 150 MW reversible Francis-type
Installed capacity900 MW
Annual generation2,500 GWh (est.)

The Nant de Drance Hydropower Plant is a pumped-storage power station currently being constructed in the canton of Valais in Switzerland. It is within the municipality of Finhaut, district of Saint-Maurice and about 14 km (8.7 mi) southwest of Martigny. Construction on the power plant began in 2008 and it should begin operations in 2020, for a completion in mid-2021.[1] It is owned by Nant de Drance SA, a consortium of Alpiq (39%), SBB (36%), Industrielle Werke Basel (IWB) (15%) and Forces Motrices Valaisannes (FMV) (10%). When complete, the US$1.9 billion plant will have an installed capacity of 900 MW.[2][3]

Background[]

Lac du Vieux Emosson will be raised and form the upper reservoir

On 25 August 2008, the Swiss Federal Department of Environment, Transport, Energy and Communications granted a building permit to Nate de Drance SA for the construction of the plant with a 600 MW design. Preliminary construction began in September 2008 but a concession was granted in April 2011 which allowed for a larger 900 MW plant. Excavation of the tunnels began in 2009 and the caverns commenced in 2010.[4] Raising of the upper Vieux Emosson Dam began in Spring 2013 and should be done by the end of 2015. The underground power house excavation was complete in April 2014.[5] The first generators should be tested in 2017 with all six commissioned between 2018 and 2021.[4]

In December 2014, at the International Tunnelling & Underground Space Awards, the project was awarded the Major Tunnelling Project of the Year award in the category of projects over US$500 million.[6]

Design[]

The plant will be located between the upper and lower reservoirs

The power plant will use two existing reservoirs to operate. The lower reservoir, Lac d'Emosson, is formed by the 180 m (590 ft) tall, 555 m (1,821 ft) long Émosson Dam, an arch dam which was completed in 1974. It withholds a reservoir with a storage capacity of 227,000,000 m3 (184,000 acre⋅ft) and surface area of 327 ha (810 acres). The lower reservoir is 4 km (2.5 mi) long and when full, lies 1,930 m (6,330 ft) above sea level. The upper reservoir for the plant, Lac du Vieux Emosson, is formed by a 45 m (148 ft) tall and 170 m (560 ft) long arch dam originally completed in 1955. The dam is undergoing a raising and will be 65 m (213 ft) tall when done. When raised, Lac du Vieux Emosson's storage capacity will be doubled and it will withhold 25,000,000 m3 (20,000 acre⋅ft) and have a surface area of 55 ha (140 acres). When full, the upper reservoir will lie 2,225 m (7,300 ft) above sea level.[7]

The power plant will lie in-between both reservoirs and use the pumped-storage hydroelectric method. To accomplish this, when energy demand is high, water will be released from the upper reservoir, down a series of 425 m (1,394 ft) penstocks to the six 150 MW reversible Francis turbine-generators in the power plant.[7] The large underground power house measures 194 m (636 ft) long, 52 m (171 ft) high and 32 m (105 ft) wide.[5] After generating power, water from the power plant will be discharged to the lower reservoir. When power demand is low, such as at night, the turbines will reverse and water can be pumped back up to the upper reservoir for use during high demand periods. As such, it will serve a peaking power plant[7] with 80% effeciency.[8]

Under the guidance of AF-Consult Switzerland Ltd as general planner, the civil engineering works were carried out by GMI (a joint venture of Marti and Implenia) and the electro-mechanical works are being undertaken by GE Hydro.[9]

References[]

  1. ^ "L'eau coulera bientôt dans les veines de Nant de Drance". Le Nouvelliste. 5 November 2019. Retrieved 8 April 2020.
  2. ^ "Projet Initié Par Alpiq, CFF, IWB ET FMV" (in French). Nant de Drance SA. Retrieved 11 January 2015.
  3. ^ De Clercq, Geert (1 September 2014). "RPT-Cavernous Swiss power plant undermined by renewable energy". Reuters. Retrieved 11 January 2015.
  4. ^ Jump up to: a b "A New Pumped Storage Plant" (in French). Nante de Drance SA. Retrieved 11 January 2015.
  5. ^ Jump up to: a b "Nant de Drance". Alpiq. Retrieved 11 January 2015.
  6. ^ "The Nant de Drance project wins at the International Tunnelling & Underground Space Awards 2014". BG Group. 11 December 2014. Retrieved 11 January 2015.
  7. ^ Jump up to: a b c "The Heart of the Mountain" (in French). Nant de Drance SA. Retrieved 11 January 2015.
  8. ^ "Inside Switzerland's giant water battery". SWI swissinfo.ch. 3 September 2021.
  9. ^ "The Nant de Drance Hydropower Scheme – brief overview of the civil works". Engineers' Journal. 20 March 2018. Retrieved 31 October 2018.
Retrieved from ""