Northern line extension to Battersea

From Wikipedia, the free encyclopedia

Northern line extension to Battersea
London Underground Northern line extension map.svg
Route of extension
Overview
StatusUnder construction
LocaleLondon Borough of Wandsworth
TerminiKennington
Battersea Power Station
Stations2
Service
TypeRapid transit
SystemLondon Underground
Operator(s)Transport for London
History
Planned opening20 September 2021
Technical
Line length2 mi (3.22 km)[1]
Track gauge1,435 mm (4 ft 8+12 in)
Operating speed45mph

The Northern line extension to Battersea is an extension of the London Underground Northern line currently under construction from Kennington to Battersea in South West London, terminating at the redeveloped Battersea Power Station. The extension will form a continuation of the Charing Cross branch of the line.

Two new underground stations have been built: Nine Elms and terminus Battersea Power Station. Both stations will be in Travelcard Zone 1.[2][3] Provision has been made for a future extension to Clapham Junction.[4]

The cost of the extension was £1.1bn, under budget by £160m. It was funded by the private sector including the developers of Battersea Power Station with contributions from other developments across the Vauxhall Nine Elms Battersea area.[5][6] Construction began in 2015, and the extension will open on 20 September 2021.[7][8][9] The extension is the first major expansion of the Underground since the Jubilee Line Extension opened in 1999.[10]

Background[]

Battersea Power Station[]

Battersea Power Station

Battersea Power Station was a coal-fired power station located on the south bank of the River Thames in Nine Elms, Battersea. Built in two stages as a single building in the 1930s and 1950s, the power station closed in 1983. It is a Grade II* listed building, owing to its size, Art Deco interior fittings & decor, and design by architect Giles Gilbert Scott.[11]

The first major proposal to develop the site in the mid 1980s was an indoor theme park by the owners of Alton Towers.[12] The theme park proposal included the 'Battersea Bullet', a dedicated British Rail shuttle train from London Victoria station to the theme park.[12][13] Owing to the early 1990s recession, the project was cancelled.[14] Various other proposals including offices, shopping centre and a football stadium were suggested as the site passed through several different owners. However, the site remained undeveloped for over 30 years. The building was added to the Heritage at Risk Register in 1991, and the World Monuments Fund watch list in 2004.[14][15]

Northern line[]

The Northern line was last extended into South London in 1926, as part of an extension to Morden station. In the 1980s, a southern extension of the Northern line to Peckham was proposed, as part of a review of potential extensions of Underground lines. The proposal was not proceeded with.[16]

Throughout the 2000s, no plans were considered for extending the Northern line, as the Public Private Partnership (PPP) to upgrade the Underground did not include provision for line extensions within the PPP contracts.[17][18] Instead, the Northern line was to be upgraded with new signalling, and was proposed to be split into two separate lines by the mid 2020s following the completion of expansion work at Camden Town tube station.[19] Extensions of the Underground were being considered elsewhere in London, including a proposed extension of the Bakerloo line into south east London.[20]

History[]

Planning and Development[]

Mid 2000s[]

View over the Vauxhall Nine Elms Battersea regeneration area, looking towards Battersea Power Station

In 2006, Irish property developers Real Estates Opportunities (REO) and Treasury Holdings purchased the Battersea Power Station site from Hong Kong property developer Parkview International for €532 million (£400 million).[21] In 2007, they abandoned the previously approved proposal for redeveloping the site, and appointed Rafael Viñoly to design a new masterplan for the site.[22] Transport consultants assessed what improvements to public transport were required to allow the site to be viably developed. Replacing the previously proposed plan to upgrade Battersea Park station at a cost of £26m,[23] a privately funded extension of the Northern line was proposed to serve the Battersea Power Station site.[24][25]

In June 2008, REO and Treasury Holdings announced their plans for the site, with their masterplan proposing refurbishing the power station with office and retail space, 3,200 new homes and a Biomass power station. They announced that they were in discussions with Transport for London (TfL) regarding an extension of the Northern line to serve the site.[26][27] The developer noted that Vauxhall is the closest Underground station to the site, and claimed that the station and the Victoria line was already at capacity.[28] In October 2008, the United States ambassador to the United Kingdom announced that the Embassy of the United States would move to a new site at Nine Elms, vacating its Mayfair location at Grosvenor Square.[29] Plans for the Embassy were approved in 2009, with infrastructure contributions towards an extension of the Northern line.[30]

In 2009, as part of the development of the Vauxhall Nine Elms Battersea Opportunity Area Planning Framework by the Greater London Authority (GLA), TfL considered the transport options for different amounts of development in the area. Options assessed by TfL included upgrading nearby stations, extending London Underground lines to the site, as well as improving local bus routes.[31] The report concluded that a high level of development in the area would require an extension of the Northern line to Battersea.[25] In July 2009, TfL made clear that there was no funding available in its Business Plan for an extension, and that it would have to be privately funded.[32]

2010s[]

In 2010, Mayor of London, Boris Johnson published the Mayor's Transport Strategy (MTS), which outlined the Mayor's plans for public transport in the capital.[33] The MTS specifically supported a privately funded extension of the Northern line to Battersea, to assist with regeneration of the Vauxhall, Nine Elms and Battersea areas.[34]

Initial route consultation (2010)[]

In May 2010, REO and Treasury Holdings launched a consultation into the extension of the Northern line to Battersea.[35] As well as increasing the accessibility of their site, the developers noted that the extension would relieve Vauxhall station and serve redevelopment sites in the area including the new US Embassy and New Covent Garden Market.[36] The consultation noted construction could be completed by 2016.[35] Four options were included in the consultation, all extensions of the Northern line from Kennington to Battersea:[35]

The first route option proposed no intermediate stations. This would provide the fastest journey time to Battersea with the lowest cost. However, the route would not serve Nine Elms or other areas. The second route option proposed a station in south Nine Elms, south of the South West Main Line. This would serve major development sites and existing residential areas. The third route option proposed an interchange station at Vauxhall. This would have the highest cost due to complex engineering. Despite the benefit of connecting to the Victoria line and National Rail services at Vauxhall station, the route may "exacerbate crowding issues" on the Victoria line and at Vauxhall station. The fourth route option proposed a station in north Nine Elms, north of the South West Main Line. Although located close to Vauxhall station and the new US Embassy, the route would not serve existing residential areas.[35]

In November 2010, planning permission for the Battersea Power Station project was granted by Wandsworth Council, with £203m pledged by the developers towards a future extension of the Northern line.[37][38] In December 2010, the scheme was approved by the Mayor of London.[39]

Noting the difficult economic state of the UK due to the financial crisis, the GLA advised landowners, developers and local council leaders in November 2010 that the extension would be mostly privately funded via developers' contributions, costing the extension at £560 million.[40][41] Options for funding the extension included direct developer contributions (such as from the Battersea Power Station developers), redirection of the Crossrail Mayoral Community Infrastructure Levy in the local area to the project, and Tax increment financing.[42]

Preferred route consultation (2011)[]
Map with the extension shown in white

In May 2011, the preferred route of the extension was announced as part of a second consultation by REO and Treasury Holdings, in collaboration with TfL.[43] This consultation proposed an extension of the Northern line from Kennington to Battersea, using the previously proposed Option 2 via Nine Elms.[44] The Nine Elms station was proposed to be located adjacent to Wandsworth Road and a Sainsbury's supermarket, south of the South West Main Line viaduct. The Battersea station was proposed to be located to the south of the Battersea Power Station development site, adjacent to Battersea Park Road. Ventilation shafts to serve the new tunnels were also proposed at Kennington Park and other locations.[44]

Following criticism during the consultation by local residents that route options were not considered, the consultation was extended until August 2011 so that the public could comment on the previously proposed route options.[45] However, Option 2 remained the preferred option.[45] Following feedback during consultation, the project would ensure that a future extension to Clapham Junction station could be built in the future.[46] The consultation noted that the extension could open by 2017, pending potential delays.[44]

In October 2011, a report commissioned by Wandsworth Borough Council showed that the proposed extension had a positive business case, with the potential of delivering up to £4.5bn in tax receipts across the area.[47] In November 2011, Chancellor George Osborne announced that the UK Government would financially support the extension of the Northern line to Battersea, with the potential creation of an Enterprise Zone in the Vauxhall Nine Elms Battersea area.[48][49]

Power Station developer into administration (2011)[]

In December 2011, Treasury Holdings went into administration, after failing to repay debts of £340m to Lloyds Banking Group and Ireland's National Asset Management Agency (NAMA).[50][51] Due to the financial crisis and the collapse of the Irish property bubble, REO and Treasury Holdings had not been able to find an investor to allow them to proceed with the development. REO had been criticised by investors and potential partners for their high levels of debt, as well as their "overly litigious" approach to business.[50] For the first time in its history, the Power Station site was put up for sale on the open market by Lloyds and NAMA. As part of the sale, the £200m contribution to the Northern line extension remained, as well as the approved planning permission.[52] Despite the sale of the site, Mayor Boris Johnson requested that the planning and development of the extension continue, with responsibility of the project passing to TfL.[25]

In March 2012, the Vauxhall Nine Elms Battersea Opportunity Area Planning Framework was published by the Greater London Authority (GLA), proposing 16,000 new homes, 500,000m² of commercial space and 27,000 new jobs across the Vauxhall, Nine Elms and Battersea area, as well as outlining the infrastructure requirements required to support this level of growth.[53]

Power Station sold, further consultation (2012)[]
Proposed site of Nine Elms station

In June 2012, the Battersea Power Station site was sold to a Malaysian consortium of companies for £400m. The consortium included SP Setia (a property company), Sime Darby (a trading conglomerate) and Employees Provident Fund (Malaysia's largest pension fund).[54][55] The consortium stated that they were in favour of the extension, and confirmed that they would honour the £200m contribution towards the extension.[56][57]

In November 2012, TfL launched a consultation into the preferred route, prior to submission of a Transport and Works Act Order to seek permission for the extension to be built.[58][59] TfL had reassessed the various route options, confirming that Route 2 via Nine Elms was the best option.[60] TfL also reassessed the potential station sites at both Battersea and Nine Elms, as well as confirming the locations of ventilation shafts.[60] Residents were also concerned regarding the potential levels of overcrowding at Kennington station, and TfL were considering if works were required to mitigate this.[61] The proposed station site at Battersea was vacant, and the proposed station site at Nine Elms was being used as a supermarket car park, as well as an office building.[62] This ensured that local opposition to demolition (such as the London Astoria for the Crossrail project) was avoided.[62]

In December 2012, HM Treasury confirmed that it would allow the GLA to borrow up to £1 billion from the Public Works Loan Board, at a preferential rate, to finance the construction of the line. Major development sites across the area - such as at New Covent Garden Market - would pay back the loan over time by developer contributions.[63][49]

As part of consultations into Crossrail 2 in 2014, the developer of the Battersea Power Station site suggested that Battersea could be the location of a station instead of at King's Road Chelsea. This would provide a link between the area and Clapham Junction station.[64]

Public inquiry[]

Kennington station, where the extension will split from the existing Northern line

In April 2013, TfL applied for a Transport and Works Act Order to seek permission to build the extension.[65] TfL also began work to appoint a contractor to build the extension, as well as undertaking ground investigation works to understand the soil and subsoil where the new tunnels are to be built.[66]

In July 2013, Prime Minister David Cameron and Prime Minister of Malaysia Najib Razak broke ground on the £8bn Battersea Power Station development,[67] with Cameron stating that "where once there was little hope of decent public transport links, we have nailed that problem".[68]

On 19 November 2013, the Secretary of State for Transport announced the start of a public inquiry to be conducted by an independent planning inspector, into the proposed construction of the extension.[69][70] During the inquiry, the inspector heard from those in favour of the extension (such as TfL, the promoter of the extension, as well as other supporters), from those objecting to the extension, as well as points raised by concerned third parties (such as from statutory undertakers).[71] Points covered in the inquiry included that the extension would only serve one developer, that other alternatives (such as a route via Vauxhall) were not sufficiently tested, impacts on the Kennington Green Conservation Area & Kennington Park, that an extension to Clapham Junction station should be built, as well as concerns regarding the levels of noise, vibration and dust during construction.[72] The inspector noted that the support of the extension by the three local London boroughs "should not be underestimated", and that there was "strong support from businesses and interests" across the Vauxhall Nine Elms Battersea Opportunity Area and the wider area.[71] TfL's responsiveness was also recognised, acting upon feedback to modifying the scheme to limit concerns, as well as adopting the most "stringent operational noise controls than on any other new underground railway in the UK".[71]

The public inquiry was completed on 20 December 2013.[73] In June 2014, the planning inspector recommended that the scheme proceed along with various recommendations.[73] The extension was given the final approval by Secretary of State for Transport Patrick McLoughlin in November 2014, and was projected to open in 2020 at a cost of around £1bn.[74][75]

In 2014, an agreement was reached between TfL and the developers of Battersea Power Station to name the Battersea station "Battersea Power Station". This name first appeared during the December 2014 TfL Board meeting.[76][77]

Construction and commissioning[]

Tunnels under construction, 2017
Battersea Power Station station under construction, 2017

In August 2014, Mike Brown, managing director of London Underground, announced that a £500 million six-year contract had been awarded to a joint venture[78] of Ferrovial Agroman and Laing O'Rourke to design and build the Northern line extension to Battersea, with Mott MacDonald as design engineer.[79][80] Awaiting the final approval, TfL noted that the project could be completed before the Crossrail project, pending any potential delays.[81]

Preparation works started on the route in 2015, with Mayor Boris Johnson officially starting construction on 23 November 2015 at a ceremony at Battersea Power Station.[82][83] Boring of the tunnels was estimated to begin in 2017, with the extension complete by 2020.[82]

In mid-February 2017, two large tunnel boring machines were delivered to the Battersea construction site, and lowered to tunnel level by a large crane.[84][85] The boring machines were named Helen and Amy – after the first British astronaut Helen Sharman, and British aviation pioneer Amy Johnson, the first female pilot to fly solo from London to Australia – following a competition amongst local school children.[86] A 300m temporary conveyor belt was constructed to transport an estimated 300,000 tonnes of excavated material from the Battersea construction site to the River Thames, where it would loaded onto barges to be transported to East Tilbury to create new arable farmland.[87][85]

The main tunnelling work started in April 2017[88] and was completed on 8 November 2017, with a breakthrough at Kennington.[89] Tunnelling work to connect the bored tunnels to the existing Kennington loop of the Northern line was dug by hand, due to risk of impacting the existing Northern line.[31][90] Following the completion of tunnelling, work began on the installation of rails, power and communication equipment, as well as the station structures themselves.[89]

In July 2017, Wandsworth Borough Council agreed to a request by the developers of Battersea Power Station to reduce the percentage of affordable housing at the development from 15% to 9%, due to the cost of the £266.4m contribution towards the extension.[91][92] This was criticised by the Mayor of London, Sadiq Khan, who called the request to reduce the affordable housing 'shameful'.[92]

In December 2017, the detailed designs for Battersea station were approved by Wandsworth Council.[93] In January 2018, the first train travelled over the completed 'step plate' junctions at Kennington that will allow access to the extension.[94] In March 2018, the detailed designs for Nine Elms station were approved by Lambeth Council.[95] In May 2018, Mayor of London Sadiq Khan noted that changes to the design of the development above the future Battersea station by the Power Station developer had increased the cost of the station by around £240m, and that TfL was seeking to recoup these costs.[96] Work at Kennington to build additional platform cross passages was completed in September 2018.[97]

Nine Elms station, nearing completion in April 2019

In January 2019, Mayor Sadiq Khan announced a delay to the opening of the project from December 2020 to 2021, due to a variety of construction delays.[98][99][100] In June 2019, it was announced that installation of track had been completed, and that an engineering train travelled the full length of the tunnel from Kennington to Battersea for the first time.[101][102]

By February 2020, construction of the extension was nearly complete, with platforms, escalators and the Tube Roundel installed in the stations.[103] In March 2020, work on the extension was paused due to the COVID-19 pandemic. Work resumed at the end of May 2020 with social distancing and other mitigation measures.[104] In July 2020, the roof of the Battersea station was handed over to the Battersea Power Station developer to allow their construction to begin.[104] In November and December 2020, stations were energised and track traction current turned on.[105] Subsequently, the first 1995 Stock train ran onto the extension over the 2020 Christmas period, marking the start of the signal testing period.[106]

Kennington station was moved from Zone 2 to the Zone 1/2 boundary in May 2021, in preparation for the opening of the extension.[107] In June 2021, it was announced that the extension will have 4G mobile signal, unlike the majority of the tunnelled Underground network in 2021.[108] The 4G network will also support the future Home Office Emergency Services Network, which will replace the current Airwave emergency services communication network.[108] By summer 2021, final testing and commissioning was underway, with regular test trains running from July 2021.[109]

Opening of extension[]

In early September 2021, TfL announced that the extension would open on 20 September 2021.[7] Initial peak-time service on the extension was announced to be six trains per hour, with five trains an hour at off-peak times.[6] Peak and off-peak service will be doubled in late 2022, following completion of the temporary closure of the Bank branch of the Northern line in 2022 for the Bank station upgrade.[110][111]

Route[]

hide
Northern line Battersea extension
Legend
Charing Cross branch
Bank branch
Kennington
to Morden
Battersea extension
Victoria line to Walthamstow
Victoria line to Brixton
Nine Elms
to London Waterloo
London River Services Battersea Power Station
to Peckham Rye
Victoria
Battersea Park National Rail
reserved course
to Willesden Junction
Clapham Junction National Rail London Overground
Main line and commuter
routes to S, SW and W

The extension of the Northern line comprises 3.2 kilometres (2.0 mi) of twin tunnels (3,150 m long northbound and 3,250 m long southbound), with 2 new stations and 2 ventilation shafts.[71] All stations are fully accessible with step-free access from street to train.[9][112] Both of the new stations will be located in Zone 1.[3]

Branching off the Northern line at Kennington, the tunnels connect to the Kennington Loop, a loop of tunnel that allows Northern line trains from the Charing Cross branch of the line to turn around. Although the loop remains, the two tunnels split off the loop to head south. Two shafts located at Kennington Park and Kennington Green provide ventilation and emergency access to the tunnels.[112] Passing underneath Oval tube station and the Victoria line tunnels, the line turns west. Nine Elms station is located adjacent to Wandsworth Road, and is the only intermediate station on the route.[113] A pedestrian route under the Nine Elms to Waterloo Viaduct allows access to the US Embassy and other developments in Nine Elms.[114] The line continues, slowly turning towards the south to be parallel with Battersea Park Road. Battersea Power Station is located at the south of the Battersea Power Station development site, a short walk from Battersea Park station.[115] A crossover junction prior to the station allows trains to terminate in either platform. Overrun tunnels continue past the station for a distance, passing underneath Battersea Dogs & Cats Home.[112]

Station London Borough Coordinates Infrastructure Notes
Kennington Southwark 51°29′17.8″N 0°6′20.4″W / 51.488278°N 0.105667°W / 51.488278; -0.105667 (Kennington tube station) Additional cross passages to existing station to improve interchange and reduce crowding[116] Connection to Charing Cross, Morden and Bank branches of the Northern line
Nine Elms Lambeth 51°28′48″N 0°7′42.6″W / 51.48000°N 0.128500°W / 51.48000; -0.128500 (Nine Elms tube station) New station with deep level platforms[113]
Battersea Power Station Wandsworth 51°28′46.2″N 0°8′31.2″W / 51.479500°N 0.142000°W / 51.479500; -0.142000 (Battersea Power Station tube station) New station with deep level platforms[115] Out of station interchange to Battersea Park station

Named Battersea during planning stages

Design, architecture and art[]

The station buildings at Nine Elms and Battersea Power Station were designed by Grimshaw Architects,[93][117][118] while other structures such as the ventilation head houses in Kennington were designed and built by the contractor, Ferrovial Agroman Laing O'Rourke.[78] Both stations were built using the cut and cover station box method, where all aspects of the station are built in a large concrete box dug out of the ground.[119] The station at Nine Elms was designed to have a future residential development built above the station itself. This development of 400 new homes will be designed by Assael Architecture.[120]

Neither station on the extension will have platform edge doors installed, although provision for future installation has been 'roughed in' in case that platform edge doors are required in future.[121]

Both stations on the extension will have permanent artworks installed by TfL's contemporary art programme, Art on the Underground.[122][123] At Battersea Power Station, artist Alexandre da Cunha installed "Sunrise Sunset Sunrise", a 100-metre-long kinetic sculpture in the ticket hall of the station, using the obsolete technology of the rotating billboard.[124][125] The proposed artwork for Nine Elms was not installed for technical reasons, and a new work will be commissioned in the future.[126]

During the period of construction, Art on the Underground commissioned two artists - Emma Smith and Nina Wakeford - to undertake temporary artworks, engaging with local residents, construction workers as well as TfL staff to create them.[127][128]

Benefits of the extension[]

Battersea Power Station development in December 2020, with the tube station nearing completion

Transport for London (TfL), local councils and developers have outlined a wide range of benefits of the extension.[72][129][130][110]

Lambeth and Wandsworth Councils have estimated that around 20,000 new homes and 25,000 new jobs could be provided, and that the extension will support the regeneration of the Vauxhall Nine Elms Battersea area.[72][129][110] Developers and local councils note that access to major development sites across the area such as Battersea Power Station, Embassy Gardens, New Covent Garden Market and the US Embassy will be improved by the extension,[72][129] especially that the extension will be in Zone 1.[3]

Transport in the local area will be improved, bringing rapid transit to communities currently served only by buses, as well as the more frequent trains than existing National Rail services from Battersea Park station.[129] Furthermore, TfL state that the extension will reduce overcrowding on local bus services and at Vauxhall station, as well as on the Victoria and Northern lines.[130] The extension will also increase the number of accessible, step-free Underground stations.[130]

As with the proposed Bakerloo line extension, TfL proposes to use its property development arm to build residential development above Nine Elms station following the opening of the extension.[120] This would recoup some of the costs of building the extension, as well as providing long term income for TfL.[131]

The Vauxhall Nine Elms Battersea regeneration also improved other transport infrastructure in the area, including cycle lanes, a new Thames Clippers river boat pier and an upgrade of Vauxhall Underground station at a cost of £36m providing step-free access to the Victoria line.[132][133] Other proposed works have included a new bridge across the River Thames to Pimlico and a planned rebuild of Vauxhall bus station.[134][132]

Perspectives[]

Embassy Gardens development adjacent to Nine Elms station

The extension is supported by local boroughs, property developers with redevelopment sites in the area, as well as local people living near the extension.[110][130][135][136] The extension is the first major expansion of the Underground since the Jubilee Line Extension opened in 1999.[10]

However, the extension has been criticised for a variety of reasons. The percentage of affordable housing at the Battersea Power Station development has been criticised - this was reduced in 2017, partially due to the cost of the £266.4m contribution towards the extension.[91][92] Other criticism has been regarding the developments in the area catalysed by the extension, with concerns regarding high amount of foreign ownership and buy to let property investments, rather than local people purchasing properties.[137] During the public inquiry, the planned extension was also criticised for a perception of an "extension for developers" and that money would have been better spent on other transport projects in London.[138][137] The potential of gentrification in the Vauxhall, Nine Elms and Battersea areas due to the extension was also noted.[91][138] The extension has also been criticised for failing to extend to Clapham Junction railway station, one of the busiest stations in the UK.[135][139]

Cost and funding[]

As of September 2021, the extension is estimated to have costed around £1.1bn to construct. This is £160m below budget, despite construction delays.[6] The extension was funded by a £1bn loan to the Greater London Authority from the Public Works Loan Board, and that will be repaid by developer contributions (Section 106 agreements and Community Infrastructure Levy) in the Vauxhall Nine Elms Battersea area, as well as through business rates.[49][140]

Future[]

Extension to Clapham Junction[]

Clapham Junction railway station

Provision has been made for a future extension of the Northern line to Clapham Junction station, with a reserved course underneath Battersea Park.[4][46][141] During the public inquiry into the extension in 2014, the inspector noted that although an extension to Clapham Junction would be desirable, it was unnecessary to meet the needs of the Vauxhall Nine Elms Battersea regeneration area.[139] Additionally, it was noted that an extension to Clapham Junction could overwhelm the extension, due to the high demand.[142] Despite the proposal for the future Crossrail 2 project to serve the station,[143] local residents and politicians have continued to request a future extension of the Northern line to Clapham Junction.[135]

Potential future split of the Northern line[]

Unlike other London Underground lines, the Northern line has two separate branches through Central London, meeting at Camden Town and Kennington.[144] TfL has previously proposed splitting the line into two separate halves to allow for more trains to run on each branch, increasing capacity by around 25%.[19] The extension to Battersea would allow the Charing Cross branch to terminate at Battersea Power Station.[145][146]

However, Camden Town station would be required to be rebuilt for a split of the line to occur[19] - given that the station is already severely overcrowded at weekend peak times, and that a split of the Northern line in two would increase numbers of passengers wishing to change trains at the station.[146][147][148] In 2018, plans to upgrade and rebuild Camden Town station were placed indefinitely on hold, due to TfL's financial situation.[149] As of 2021, there is currently no plan to split the line.

References[]

  1. ^ Sheppard, Owen (3 November 2016). "Northern line extension from Kennington to Battersea 'halfway there'". Southwark News. Retrieved 12 January 2016.
  2. ^ "Northern line extension to Battersea gets go-ahead" (Press release). Transport for London. 12 November 2014. Retrieved 26 May 2021.
  3. ^ Jump up to: a b c "Zone 1 confirmed for new Battersea and Nine Elms Tube stations" (Press release). Wandsworth Borough Council. 13 May 2021. Retrieved 11 September 2021.
  4. ^ Jump up to: a b Henderson, Jamie (23 June 2013). "Clapham Junction next for Northern Line says London Assembly member". Wandsworth Guardian. Retrieved 12 January 2014. A path running beneath Battersea Park has already been reserved for such a move
  5. ^ "Tunnelling for the Northern Line Extension to begin in March" (Press release). Greater London Authority. 20 January 2017. Retrieved 13 April 2020.
  6. ^ Jump up to: a b c "New Tube map unveiled featuring new Northern line stations to open next week as Tube extends to Battersea Power Station" (Press release). Transport for London. 16 September 2021. Retrieved 16 September 2021.
  7. ^ Jump up to: a b "Northern Line extension to open in two weeks". ITV News. 3 September 2021. Retrieved 3 September 2021.
  8. ^ Lydall, Ross (21 May 2021). "First extension to London Underground this century to open in Sept". Evening Standard. London. Retrieved 26 May 2021.
  9. ^ Jump up to: a b "Northern line extension". Transport for London. Retrieved 26 May 2021.
  10. ^ Jump up to: a b "Battersea boost imminent". Modern Railways. 20 August 2021. Retrieved 11 September 2021. the first major new stretch of tube railway since the Jubilee Line extension (JLE) opened at the turn of the millennium.
  11. ^ "BATTERSEA POWER STATION, Non Civil Parish - 1357620 | Historic England". Historic England. 2007. Retrieved 9 September 2021.
  12. ^ Jump up to: a b Harrad, Tom (7 April 2016). "How Battersea Power Station Almost Became London's Very Own Alton Towers". Vice. Retrieved 9 September 2021.
  13. ^ Marsden, Colin J (June–July 2010). "The All-Time Guide to EMU Classifications" (PDF). Modern Locomotives Illustrated. No. 183. Stamford, Lincs: Key Publishing. Retrieved 10 July 2021.
  14. ^ Jump up to: a b Watts, Peter (2016). Up in smoke: the failed dreams of Battersea Power Station. Richmond: Paradise Road. ISBN 978-0-9935702-0-9. OCLC 948340667.
  15. ^ "Battersea Power Station". World Monuments Fund. February 2019. Retrieved 14 September 2021.
  16. ^ "Strategic Review 1988 - New Lines and Extensions - Northern Line Southern Extension" (PDF). What Do They Know. London Underground. 1988.
  17. ^ "Details of Tube modernisation plans unveiled". Tube Lines. 8 January 2003. Archived from the original on 19 May 2006. Retrieved 8 March 2021.
  18. ^ Shawcross, Valerie; Livingstone, Ken (7 March 2005). "Transport Plan - Southward Extensions". Mayor's Question Time. Retrieved 29 March 2021.
  19. ^ Jump up to: a b c "Transport 2025: Transport vision for a growing world city". Transport for London. November 2006. Retrieved 14 September 2021. A segregation of services would deliver simpler service patterns on the line. This will allow more trains to be run through both the West End and City branches – enabling 30tph services on the central London branches. This will provide roughly 25 per cent extra capacity and crowding relief on these busy sections. With the core infrastructure being capable of supporting these service patterns, the main requirements are some additional trains (and stabling) and station capacity improvements at Camden Town.
  20. ^ "Underground 2025 – South London Corridor Report January 2007" (PDF). What Do They Know. London Underground Limited Strategy and Service Development. January 2007. Retrieved 9 September 2021.
  21. ^ "Iconic landmark is sold for £400m". BBC News. 30 November 2006. Retrieved 9 September 2021.
  22. ^ Westbrook, Andrew (5 April 2007). "Back To Square One For Power Station". Wandsworth Guardian. Archived from the original on 26 May 2008. Retrieved 9 September 2021.
  23. ^ "£26m to be spend [sic] on Battersea Park station". icSouthlondon. Trinity Mirror. 28 February 2006. Archived from the original on 6 March 2006. Retrieved 13 September 2021.
  24. ^ "Battersea Power Station". Battersea Power Station. 2010. Archived from the original on 27 November 2010. Retrieved 9 September 2021.
  25. ^ Jump up to: a b c "London Underground (Northern Line Extension) Order SUPPORTING STATEMENT" (PDF). Transport for London. April 2013. pp. 5–9. Retrieved 9 September 2021.
  26. ^ Booth, Robert (20 June 2008). "Latest plans for Battersea power station revealed". The Guardian. London. Retrieved 9 September 2021.
  27. ^ "Northern Line Extension to Nine Elms & Battersea - Background". Treasury Holdings. 23 August 2011. Retrieved 9 September 2021.
  28. ^ "Battersea Power Station is Reborn" (PDF) (Press release). Battersea Power Station. 20 June 2008. Archived from the original (PDF) on 20 September 2009. Retrieved 9 September 2021.
  29. ^ Castle, Stephen (2 October 2008). "U.S. Embassy to relocate in London". The New York Times. Retrieved 9 September 2021.
  30. ^ "'The Iceberg' cometh". Embassy Network. 18 October 2009. Retrieved 9 September 2021.
  31. ^ Jump up to: a b Thiagarajan, Suresh (16 October 2018). "Northern Line Extension Project". Permanent Way Institution. Retrieved 13 September 2021.
  32. ^ Tracey, Richard; Johnson, Boris (6 July 2009). "Northern Line Extension". Mayor's Question Time. Retrieved 9 September 2021.
  33. ^ "Mayor's Transport Strategy 2010". Greater London Authority. 19 January 2015. Retrieved 31 March 2021.
  34. ^ "Mayor's Transport Strategy - Chapter five - Transport proposals" (PDF). Greater London Authority. May 2010. p. 139.
  35. ^ Jump up to: a b c d "Proposals for a Northern Line extension to Nine Elms and Battersea" (PDF). Real Estate Opportunities and Treasury Holdings. May 2010. Archived from the original (PDF) on 29 August 2017. Retrieved 9 September 2021.
  36. ^ "Battersea Power Station". Battersea Power Station. 2010. Archived from the original on 29 April 2010. Retrieved 9 September 2021.
  37. ^ "Battersea Power Station scheme approved" (Press release). Wandsworth Council. 11 November 2010. Archived from the original on 14 October 2013. Retrieved 9 September 2021. Before work begins Treasury Holdings will sign a legal agreement pledging more than £211m to improving local infrastructure and community services. Around £203m of this would go towards extending the Northern Line.
  38. ^ "Battersea power station revamp gets go-ahead". the Guardian. 12 November 2010. Retrieved 9 September 2021.
  39. ^ "Mayor approves £5.5bn Battersea Power Station revamp". BBC News. 22 December 2010.
  40. ^ "Study shows Nine Elms tube link viable" (Press release). Wandsworth Council. 5 November 2010. Retrieved 9 November 2010.
  41. ^ "Northern Line Extension (NLE) Briefing Note 2 (September 2010)" (PDF). Battersea Power Station. September 2010. Archived from the original (PDF) on 22 February 2011. Retrieved 9 September 2021.
  42. ^ "Boris: Nine Elms developers won't pay Crossrail levy". Architect's Journal. 29 October 2009. Retrieved 5 January 2012.
  43. ^ "Northern Line Extension to Nine Elms & Battersea - Home". Northern Line Extension. 23 August 2011. Archived from the original on 23 August 2011. Retrieved 9 September 2021.
  44. ^ Jump up to: a b c "Extension of the Northern line to Nine Elms and Battersea" (PDF). Northern Line Extension. May 2011. Archived from the original (PDF) on 23 August 2011. Retrieved 9 September 2021.
  45. ^ Jump up to: a b "Proposed Extension of the Northern line to Nine Elms and Battersea Public Consultation May-June 2011 – Update" (PDF). Northern Line Extension. June 2011. Archived from the original (PDF) on 23 August 2011. Retrieved 9 September 2021. Route 2 is currently the preferred option because it offers the most benefits, however, no formal decision on this has yet been taken and your views will be considered
  46. ^ Jump up to: a b "Northern line extension Factsheet 8: Previous consultation on the Northern line extension (NLE) and our response to issues raised" (PDF). Transport for London. 2012. Retrieved 9 September 2021. Consultation responses raised some interest in the possibility of the Northern line being extended beyond Battersea as far as Clapham Junction. The proposals allow for the potential for a future extension beyond Battersea.
  47. ^ Rosewell, Bridget (October 2011). "The Wider Economic Benefits of VNEB Regeneration ‐ Interim Report" (PDF). Volterra. Retrieved 10 September 2021.
  48. ^ "Northern Line: Government backs Tube extension plan". BBC News. 29 November 2011. Retrieved 9 September 2021.
  49. ^ Jump up to: a b c Odell, Mark; Pickford, James (4 December 2012). "Plan to break Battersea transport deadlock". Financial Times. Retrieved 9 September 2021.
  50. ^ Jump up to: a b "Irish property developers' grand vision for Battersea power station left in ruins". The Guardian. London. 20 December 2011. Retrieved 9 September 2021.
  51. ^ "Ireland's 'bad bank' NAMA becomes one of world's biggest property lenders". The Guardian. London. 21 December 2010. Retrieved 9 September 2021.
  52. ^ Prynn, Jonathan; Cecil, Nicholas; Bar-Hillel, Mira (10 April 2012). "New Sale: Battersea power station". Evening Standard. London. Retrieved 9 September 2021.
  53. ^ "Vauxhall Nine Elms Battersea Opportunity Area Planning Framework". Greater London Authority. March 2021. Archived from the original on 16 August 2012. Retrieved 9 September 2021.
  54. ^ "Battersea Power Station: Malaysian company beats Chelsea bid". BBC News. 7 June 2012. Retrieved 7 June 2012.
  55. ^ Hammond, Ed; Grant, Jeremy (5 July 2012). "Malaysians seal £400m Battersea deal". Financial Times. Retrieved 14 September 2021.
  56. ^ Werdigier, Julia (7 June 2012). "New Buyers for Venerable London Power Station". The New York Times. ISSN 0362-4331. Retrieved 9 September 2021.
  57. ^ Kenyon, Peter; McInnes, Ian (July 2012). "Northern Line extension gains momentum". Tunnel Talk. Retrieved 10 September 2021.
  58. ^ "TfL would like to hear your views on plans to extend the Northern line" (Press release). Transport for London. 8 November 2012. Retrieved 9 September 2021.
  59. ^ "Northern Line extension consultation begins". BBC News. 15 November 2012. Retrieved 10 September 2021.
  60. ^ Jump up to: a b "Northern line extension Factsheet 8: Previous consultation on the Northern line extension (NLE) and our response to issues raised" (PDF). Transport for London. 2012. Retrieved 9 September 2021. Some concerns were raised about the first phase of public consultation conducted in summer 2010. ... Following public consultation in summer 2011, TfL undertook a detailed assessment of the various route options. This concluded that route 2 was the best option to take forward.
  61. ^ Johnson, Boris; Shawcross, Valerie (31 May 2012). "Kennington station". Mayor's Question Time. Retrieved 11 September 2021.
  62. ^ Jump up to: a b Dixon, J S (19 June 2014). "Report to the Secretary of State for Transport and the Secretary of State for Communities and Local Government - Transport and Works Act 1992 Town and Country Planning Act 1990 Planning (Listed Buildings and Conservation Areas) Act 1990 and Acquisition of Land Act 1981 - London Underground (Northern Line Extension) Order 201[ ]" (PDF). HM Government. pp. 7–8. Retrieved 13 September 2021.
  63. ^ "Boost for Battersea as Osborne puts power station on the Tube". London Evening Standard. 5 December 2012. Retrieved 19 January 2013.
  64. ^ Beard, Matthew (11 August 2014). "Battersea Power Station owner makes bid for new Crossrail 2 station". Evening Standard. Retrieved 11 September 2021.
  65. ^ "TfL applies for Northern Line extension legal powers". Railway Gazette International. London. 30 April 2013.
  66. ^ Pitt, Vern (3 July 2013). "Four teams in for £600m Battersea Northern Line extension". Building magazine. Retrieved 11 September 2021.
  67. ^ "Battersea Power Station work opened by David Cameron and Malaysian PM". BBC News. 4 July 2013. Retrieved 13 September 2021.
  68. ^ Cameron, David (4 July 2013). "David Cameron: Battersea is a symbol of Britain's renewal". Evening Standard. Retrieved 13 September 2021. Where once there was little hope of decent public transport links, we have nailed that problem with the Northern line extension. This needed a financial guarantee from Government to get going: we provided it, now it’s happening.
  69. ^ "Northern line extension public inquiry starts today" (Press release). Transport for London. 19 November 2013. Retrieved 11 September 2021.
  70. ^ Rucki, Alexandra (19 November 2013). "Public inquiry launches into Northern Line extension to Battersea". Your Local Guardian. Retrieved 11 September 2021.
  71. ^ Jump up to: a b c d Dixon, J S (19 June 2014). "Report to the Secretary of State for Transport and the Secretary of State for Communities and Local Government - Transport and Works Act 1992 Town and Country Planning Act 1990 Planning (Listed Buildings and Conservation Areas) Act 1990 and Acquisition of Land Act 1981 - London Underground (Northern Line Extension) Order 201[ ]" (PDF). HM Government. p. 12-13. Retrieved 11 September 2021.
  72. ^ Jump up to: a b c d Dixon, J S (19 June 2014). "Report to the Secretary of State for Transport and the Secretary of State for Communities and Local Government - Transport and Works Act 1992 Town and Country Planning Act 1990 Planning (Listed Buildings and Conservation Areas) Act 1990 and Acquisition of Land Act 1981 - London Underground (Northern Line Extension) Order 201[ ]" (PDF). HM Government. pp. 3–4. Retrieved 11 September 2021.
  73. ^ Jump up to: a b Dixon, J S (19 June 2014). "Report to the Secretary of State for Transport and the Secretary of State for Communities and Local Government - Transport and Works Act 1992 Town and Country Planning Act 1990 Planning (Listed Buildings and Conservation Areas) Act 1990 and Acquisition of Land Act 1981 - London Underground (Northern Line Extension) Order 201[ ]" (PDF). HM Government. pp. i–ii. Retrieved 11 September 2021.
  74. ^ de Peyer, Robin (12 November 2014). "Northern Line extension to Battersea and Nine Elms gets go ahead". Evening Standard. Retrieved 12 November 2014.
  75. ^ "Northern Line extension to Battersea and Nine Elms given go-ahead". BBC News. 12 November 2014. Retrieved 11 September 2021.
  76. ^ Noble, Will (7 December 2018). "Battersea Power Station Station: Weirdest Tube Station Name Ever?". Londonist. Retrieved 11 September 2021.
  77. ^ "TfL Board December 2014 - Item 7 TfL Business Plan 2014" (PDF). Transport for London. December 2014. Retrieved 11 September 2021.
  78. ^ Jump up to: a b "Ferrovial consortium chosen to expand London Underground for 628 million euro Ferrovial". Ferrovial. 9 September 2014. Retrieved 11 September 2021.
  79. ^ "Next Step for Northern Line Extension". London Borough of Wandsworth. 21 August 2014. Retrieved 11 September 2021.
  80. ^ "Northern Line extension contractor selected". Railway Gazette International. 21 August 2014. Retrieved 11 September 2021.
  81. ^ "Northern Line extension could open before Crossrail". Rail UK. 21 May 2014. Retrieved 11 September 2021.
  82. ^ Jump up to: a b "Northern Line extension breaks ground". Railway Gazette International. 25 November 2015. Retrieved 11 September 2021.
  83. ^ Shenouda, Josh (25 November 2015). "Boris Johnson starts work on the Northern line extension to Battersea and Nine Elms". Wandsworth Times. Retrieved 11 September 2021.
  84. ^ "London Underground Northern Line extension tunnelling to start in March". Railway Gazette International. 20 January 2017. Retrieved 11 September 2021.
  85. ^ Jump up to: a b Kitching, Ruby (17 March 2017). "Tunnelling | Northern Line extension". New Civil Engineer. Retrieved 11 September 2021.
  86. ^ Murray, Dick (16 February 2017). "Machines brought in to begin work on £1.2bn Northern line extension". Evening Standard. Retrieved 11 September 2021. They were named, thanks to a vote by local schoolchildren, in honour of astronaut Helen Sharman and aviation pioneer Amy Johnson
  87. ^ "Tilbury set to get new farm land thanks to project to extend London's Underground service". Thurrock Gazette. 20 January 2017. Retrieved 11 September 2021.
  88. ^ "Tunnelling starts to extend the Northern line to Battersea". Transport for London. 11 April 2017. Retrieved 29 March 2020.
  89. ^ Jump up to: a b Collier, Hatty (8 November 2017). "Northern Line extension: Tunnelling work on £1.2bn extension to Battersea completed ahead of 2020 opening". Evening Standard. Retrieved 11 September 2021.
  90. ^ Kitching, Ruby (25 May 2017). "Tunnelling: Northern link". Ground Engineering. Retrieved 13 September 2021.
  91. ^ Jump up to: a b c Wainwright, Oliver (2 February 2021). "Penthouses and poor doors: how Europe's 'biggest regeneration project' fell flat". The Guardian. London. Retrieved 11 September 2021.
  92. ^ Jump up to: a b c Cuffe, Grainne (11 July 2017). "Mayor of London brands Wandsworth Council 'shameful' for decision on affordable homes at Battersea Power Station". Wandsworth Times. Retrieved 11 September 2021.
  93. ^ Jump up to: a b "Historic day for east Battersea as design for new Northern Line tube station is given green light". Wandsworth Borough Council. 21 December 2017. Retrieved 11 September 2021.
  94. ^ Carr, Collin (9 January 2018). "First train travels over new Northern line extension junction". Rail UK. Retrieved 11 September 2021.
  95. ^ "18/00043/DET | Approval of details to discharge Condition 3(a) (i) (Stations and other buildings: detailed design approval of above ground elements) of the deemed planning permission for the London Underground Northern Line Extension (Nine Elms Station) (Ref : TWA 3/1/415) | Nine Elms TFL Construction Site, Pascal Street London SW8". planning.lambeth.gov.uk. March 2018. Retrieved 14 September 2021. Decision Issued Date Mon 05 Mar 2018
  96. ^ Khan, Sadiq; Eshalomi, Florence (4 May 2018). "Developer Funded Transport". Mayor's Question Time. Retrieved 14 September 2021. The additional costs to the Northern line extensions have been caused by significant changes made by the Battersea Power Station developer to the design of the development above the station at Battersea. More ambitious structures than were originally agreed have meant substantial changes are needed for the new Tube station to function properly. This had led to an increase in the overall cost of the project. TfL is in discussions with Battersea Power Station developers to recover these additional costs.
  97. ^ "Finished complex cross passage works at Kennington Station in NLE". Ferrovial. 2 October 2018. Retrieved 11 September 2021.
  98. ^ Khan, Sadiq (3 January 2019). "Oral Update to the Mayor's Report". Mayor's Question Time. Retrieved 11 September 2021.
  99. ^ Plimmer, Gill; Pickard, Jim (21 December 2018). "London's Northern Line extension to Battersea delayed by a year". Financial Times. Retrieved 11 September 2021.
  100. ^ Prynn, Jonathan; Sleigh, Sophia (21 December 2018). "TfL under fire as Battersea Tube extension is delayed by 'miscalculations'". Evening Standard. London. Retrieved 8 May 2020.
  101. ^ "First engineering train travels full Northern Line Extension". Railway PRO. 18 June 2019. Retrieved 11 September 2021.
  102. ^ "Northern Line extension due to open in September 2021 as trackwork completed". Railway Gazette International. 14 June 2019. Retrieved 11 September 2021.
  103. ^ "Battersea Power Station signs unveiled at new Northern Line hub". Evening Standard. 20 February 2020. Retrieved 13 April 2020.
  104. ^ Jump up to: a b Eshalomi, Florence; Khan, Sadiq (7 September 2020). "Update on the Northern Line Extension". Mayor's Question Time. Retrieved 11 September 2021.
  105. ^ "Two new stations on the Northern Line Extension". Nine Elms on the South Bank. Retrieved 11 September 2021.
  106. ^ "First passenger trains complete journeys on new Northern Line Extension". Transport for London (Press release). Retrieved 4 January 2021.
  107. ^ Bennett, Ella (13 May 2021). "Kennington on the Northern Line line is changing zones as lockdown eases". MyLondon. Retrieved 11 September 2021.
  108. ^ Jump up to: a b Lydall, Ross (22 June 2021). "Tube to get full mobile phone coverage by 2024". Evening Standard. Retrieved 11 September 2021.
  109. ^ White, Chloe (11 July 2021). "Transport for London Northern Line Extension project meets a major milestone as trial operations begin". RailAdvent. Retrieved 11 July 2021.
  110. ^ Jump up to: a b c d "Battersea Power Station Underground To Open" (Press release). Battersea Power Station. 3 September 2021. Retrieved 11 September 2021.
  111. ^ Smith, Claire (3 September 2021). "TfL's Northern Line Extension opening date revealed". New Civil Engineer. Retrieved 14 September 2021. At the time, TfL said that introduction of services on the new line is being "realigned" to coincide with the opening of the Bank Station upgrade allowing for additional capacity on the line. Nonetheless, the impact of Covid and other project issues mean that the upgrade will now not be completed until at least mid-2022 with a blockade on the line planned at Bank between January and May 2022.
  112. ^ Jump up to: a b c "Northern Line Extension Proposed route and key sites" (PDF). Transport for London. 2012. Retrieved 10 September 2021.
  113. ^ Jump up to: a b "Factsheet E: New station at Nine Elms" (PDF). Transport for London. September 2013. Retrieved 10 September 2021.
  114. ^ "New connections: Arch 42". Nine Elms on the South Bank. 9 February 2021. Retrieved 10 September 2021.
  115. ^ Jump up to: a b "Factsheet M: New station at Battersea" (PDF). Transport for London. September 2013. Retrieved 10 September 2021.
  116. ^ "Fact sheet G: Impact of the Northern line extension on the Northern line and Kennington station" (PDF). Transport for London. September 2013. Retrieved 10 September 2021.
  117. ^ "Battersea Station receives planning approval" (Press release). Grimshaw Architects. 21 December 2017. Retrieved 11 September 2021.
  118. ^ @GrimshawArch (7 September 2021). "The first new #NorthernLine stations in 80 years are open to the public on 20 September. Our design of #NineElms and #BatterseaPowerStation achieved internal architectural character through the expression of high-quality structural elements. Plan your trip to see the new stations" (Tweet). Retrieved 11 September 2021 – via Twitter.
  119. ^ Lydall, Ross (21 May 2021). "First extension to London Underground this century to open in Sept". Evening Standard. London. Retrieved 12 September 2021.
  120. ^ Jump up to: a b Lowe, Tom (23 April 2021). "Assael clears planning for £144m scheme above Nine Elms tube station". Building Design. London. Retrieved 11 September 2021.
  121. ^ Pidgeon, Caroline (10 June 2019). "Platform edge doors on the Northern Line". Mayor's Question Time. Retrieved 14 September 2021.
  122. ^ Krause, Riley (9 September 2019). "Here are the artworks that will decorate Battersea and Nine Elms Northern Line stations". Wandsworth Times. Retrieved 11 September 2021.
  123. ^ "Artworks announced for Battersea and Nine Elms Northern Line stations" (Press release). Wandsworth Borough Council. 6 September 2019. Archived from the original on 20 September 2020. Retrieved 13 April 2020.
  124. ^ "Sunset, Sunrise, Sunset". Art on the Underground. Retrieved 13 April 2020.
  125. ^ "Artworks announced for Battersea and Nine Elms Northern Line stations". Wandsworth Borough Council. Retrieved 13 April 2020.
  126. ^ Art on the Underground (3 September 2021). "The artwork at Nine Elms as originally conceived by artist Samara Scott will not be able to go ahead for technical reasons. Details of a commission for a permanent artwork at this station will be announced in due course". Twitter. Retrieved 3 September 2021.
  127. ^ Thurloway, Jameela (24 April 2019). "Emma Smith". Contemporary Art Society. Retrieved 14 September 2021. In 2017 Smith produced Televox, the first commission by Art on the Underground’s artist‐led engagement programme, which focuses on communities working and living along the Northern Line Extension (due for completion in 2020).
  128. ^ "Nina Wakeford's Art on the Underground commission celebrates London communities past, present and future". Royal College of Art. 26 November 2019. Retrieved 14 September 2021.
  129. ^ Jump up to: a b c d "Northern Line Extension to Nine Elms & Battersea - Key Benefits". Northern Line Extension. 23 August 2011. Archived from the original on 27 August 2011. Retrieved 9 September 2021.
  130. ^ Jump up to: a b c d "Northern line extension - Benefits of the NLE". Transport for London. Retrieved 11 September 2021.
  131. ^ "Property". Transport for London. Retrieved 2 April 2021.
  132. ^ Jump up to: a b "Vauxhall Tube upgrade begins next year". Nine Elms on the South Bank. 20 May 2013. Retrieved 12 September 2021.
  133. ^ "Battersea Power Station Pier - Uber Boat by Thames Clippers". Thames Clippers. Retrieved 13 September 2021.
  134. ^ Clark, Tim (17 December 2020). "Nine Elms bridge scheme 'paused' after Covid forces council rethink". The Architects' Journal. London. Retrieved 13 September 2021.
  135. ^ Jump up to: a b c Meyer, James (10 September 2021). "Two new tube stations to open (this is what residents think of them)". Wandsworth Times. Retrieved 11 September 2021.
  136. ^ "Northern line extension to open in months to support London's Covid recovery". Metro. London. 24 May 2021. Retrieved 11 September 2021. During the consultation, the vast majority of respondents supported the plans, with 87% agreeing it would benefit the area.
  137. ^ Jump up to: a b Kollewe, Julia (14 February 2015). "Battersea is part of a huge building project – but not for Londoners". the Guardian. Retrieved 13 September 2021.
  138. ^ Jump up to: a b Dixon, J S (19 June 2014). "Report to the Secretary of State for Transport and the Secretary of State for Communities and Local Government - Transport and Works Act 1992 Town and Country Planning Act 1990 Planning (Listed Buildings and Conservation Areas) Act 1990 and Acquisition of Land Act 1981 - London Underground (Northern Line Extension) Order 201[ ]" (PDF). HM Government. p. 180. Retrieved 11 September 2014.
  139. ^ Jump up to: a b Dixon, J S (19 June 2014). "Report to the Secretary of State for Transport and the Secretary of State for Communities and Local Government - Transport and Works Act 1992 Town and Country Planning Act 1990 Planning (Listed Buildings and Conservation Areas) Act 1990 and Acquisition of Land Act 1981 - London Underground (Northern Line Extension) Order 201[ ]" (PDF). HM Government. pp. 186–187. Retrieved 11 September 2021.
  140. ^ Eshalomi, Florence; Khan, Sadiq (10 June 2019). "Northern Line Extension (1)". Mayor's Question Time. Retrieved 11 September 2021.
  141. ^ Johnson, Boris; Darren, Johnson (8 October 2012). "Extension of Northern Line to Clapham Junction". Mayor's Question Time. Retrieved 11 September 2021. There are no current plans to extend further to Clapham Junction; however it is a requirement that the extension be designed so that a further extension would be possible in the future.
  142. ^ Lydall, Ross (21 May 2021). "First extension to London Underground this century to open in Sept". Evening Standard. Retrieved 12 September 2021. Engineers have previously said that extending the Northern line to Clapham Junction could have overwhelmed the new route due.
  143. ^ "Clapham Junction". Crossrail 2. Retrieved 12 September 2021.
  144. ^ Lawrence-Jones, Charlie (21 February 2020). "Why the London Underground's Northern line has two branches". MyLondon. Retrieved 13 September 2021.
  145. ^ "Permanent split for the Northern line". Your Local Guardian. 15 May 2010. Retrieved 13 September 2021.
  146. ^ Jump up to: a b "Plans to split Northern Line in two move forward another step". Rail Technology Magazine. 4 August 2015. Retrieved 13 September 2021.
  147. ^ "Improving capacity at Camden Town station". Transport for London. 2017. Retrieved 20 February 2018. Detailed report, with updated timeline etc.
  148. ^ "We Need To Talk About Camden: The Future of the Northern Line". London Reconnections. 6 May 2013. Retrieved 13 September 2021.
  149. ^ Topham, Gwyn (11 December 2018). "Major tube upgrades shelved as TfL struggles to balance books". The Guardian. ISSN 0261-3077. Retrieved 26 January 2020.