Citicorp Center engineering crisis

From Wikipedia, the free encyclopedia

Citigroup building with sketch of internal framework superimposed on one side. The same design is used on all four sides and transmits wind and gravity loads to the four support stilts.

The Citicorp Center engineering crisis was the discovery, in 1978, of a significant structural flaw in Citicorp Center, then a recently completed skyscraper in New York City, and the subsequent effort to quietly make repairs over the next few months. The building, now known as Citigroup Center, occupied an entire block and was to be the headquarters of Citibank. Its structure, designed by William LeMessurier, had several unusual design features, including a raised base supported by four offset stilts, and diagonal bracing which absorbed wind loads from upper stories.

In the original design, potential wind loads for the building were calculated incorrectly. The flaw was discovered by Diane Hartley, an undergraduate student at Princeton University who was writing a thesis on the building, and was communicated to the firm responsible for the structural design. LeMessurier was subsequently lauded for acknowledging his error and orchestrating a successful repair effort. Estimates at the time suggested that the building could be toppled by a 70-mile-per-hour (110 km/h) wind, with possibly many people killed as a result. The crisis was kept secret until 1995 and Hartley had no knowledge of the significance of her work until after that time.

Background[]

St. Peter's Evangelical Lutheran Church is visible on the left-hand-side, below the skyscraper. The church's location necessitated the unusual placement of columns in the center of each face, instead of at the corners.

The Citigroup Center, originally known as Citicorp Center, is a 59-story skyscraper at 601 Lexington Avenue in the Midtown Manhattan neighborhood of New York City.[1][2][3] It was designed by architect Hugh Stubbins as the headquarters for First National City Bank (later Citibank), along with associate architect Emery Roth & Sons.[4][5][6] LeMessurier Associates and were the structural engineers, and Bethlehem Steel was the steel contractor.[5][7] The building was dedicated on October 12, 1977.[8][9]

As part of Citicorp Center's construction, a new building for St. Peter's Lutheran Church was erected at the northwest corner of the site; by agreement, it was supposed to be separate from the main tower.[10][11] To avoid the church, the tower is supported by four stilts[5][12] positioned underneath the centers of each of the tower's edges.[13] (Early plans called for the supports to be placed under the tower's corners, but the agreement with the church prevented that.[14]) To allow this design to work, Bill LeMessurier specified that load-bearing braces in the form of inverted chevrons be stacked above the stilts inside each face of the building. These braces are designed to distribute tension loads that are created by wind from the upper stories down to the stilts.[15][16]

The long, multi-story diagonal braces had to be fabricated in sections and assembled on site, requiring five joints in each brace. LeMessurier's original design for the chevron load braces used welded joints. To save money, Bethlehem Steel proposed changing the construction plans to use bolted joints, a design modification that was accepted by LeMessurier's office but not known to the engineer himself until later.[13]

For his original design, LeMessurier calculated wind load on the building when wind blew perpendicularly against the side of the building, as these were the only calculations required by New York City building code. Such winds are normally the worst case, and a structural system capable of handling them can easily cope with wind from any other angle. Thus, the engineer did not specifically calculate the effects of diagonally-oriented "quartering winds".[13][17]

Discovery[]

In June 1978, Princeton University engineering student Diane Hartley was writing her senior thesis about Citicorp Center's design at the suggestion of her professor, David Billington.[18][19] As part of that work she analyzed the structural design and calculated stresses from quartering winds, finding them higher than the maximum expected stress values provided to her by LeMessurier’s firm. Billington, in his feedback on Hartley's thesis, also questioned the figures provided by the firm. Hartley asked her contact there about the discrepancy and was assured the building could handle the forces, so she dropped the issue. Hartley’s concerns and the response she received are documented in her thesis.[18] LeMessurier was separately designing a similar building with wind braces in Pittsburgh, and a potential contractor questioned the expense of using welded rather than bolted joints. LeMessurier asked his office how the welds went at the Citicorp construction and was then told bolts had been substituted.[18]

Hartley's inquiry was relayed to LeMessurier, exactly when or how is not known, but on July 24, 1978, LeMessurier went to his office and conducted calculations on Citicorp Center's design.[18][17] He found that, for four of the eight tiers of chevrons, such winds would create a 40 percent increase in wind loads and a 160 percent increase in load at the bolted joints.[13] Citicorp Center's use of bolted joints and the increased loads from quartering winds would not have caused concern if these issues had been isolated from each other. However, the combination of the two findings prompted LeMessurier to run tests on the structural safety.[20] The original welded-joint design could withstand the load from straight-on and quartering winds, but a 70-mile-per-hour (110 km/h) near-hurricane force quartering wind would exceed the strength of the bolted-joint chevrons.[16][18] LeMessurier also discovered that his firm had used New York City's truss safety factor of 1:1 instead of the column safety factor of 1:2.[16]

On July 26, LeMessurier visited wind-tunnel expert Alan Garnett Davenport at the University of Western Ontario. Davenport's team conducted calculations on the building and found not only that LeMessurier's modeling was correct, but also that, in a real-world situation, member stresses could increase by more than the 40 percent LeMessurier had calculated.[18][21] LeMessurier then went to his Maine summer home on July 28 to analyze the issue.[18][21] With the tuned mass damper active, LeMessurier estimated that a wind capable of toppling the building would occur on average once every 55 years.[22][18] If the tuned mass damper could not function due to a power outage, a wind strong enough to cause the building's collapse would occur once every 16 years on average.[22]

Repairs[]

LeMessurier agonized over how to deal with the problem. If the issues were made known to the public, he risked ruining his professional reputation as well as causing panic in the immediate area surrounding the building, as well as to occupants.[23] LeMessurier considered never bringing the issue up, and he also briefly contemplated killing himself before anyone else found out about the defect.[24][25] LeMessurier ultimately contacted Stubbins's lawyer and his insurance carrier. LeMessurier then contacted Citicorp's lawyers, the latter of which hired Leslie E. Robertson as an expert adviser.[23] Citicorp accepted LeMessurier's proposal to weld steel plates over the bolted joints, and Karl Koch Erecting was hired for the welding process.[26] Very few people were made aware of the issue, besides Citicorp leadership, mayor Ed Koch, acting buildings commissioner Irving E. Minkin, and the head of the welder's union.[16][26]

Construction crews started installing the welded panels at night in August 1978. Officials made no public mention of any possible structural issues, and the city's three major newspapers had gone on strike.[27][26] Officials barely acknowledged the issue, instead describing the work as a routine procedure. Henry DeFord III of Citicorp claimed the Citicorp Center could already withstand a 100-year wind[28] and that there were no "noticeable problems in the building at all".[29] As precautions, emergency generators were installed for the mass damper, strain gauges were placed on critical beams and weather forecasters were engaged.[18] Citicorp and local officials created emergency evacuation plans for the immediate neighborhood.[16][30] However, these evacuation plans were not publicized at the time. This was in spite of the fact that thousands of people could have been killed in a potential collapse.[24] Six weeks into the work, a major storm (Hurricane Ella) was off Cape Hatteras and heading for New York. With New York City hours away from emergency evacuation, the reinforcement was only half-finished. Ella eventually turned eastward and veered out to sea.[16][30]

Repairs were completed in October 1978, before the media resumed publishing. LeMessurier claimed a wind strong enough to topple the repaired building would only occur once every 700 years.[27][31] Stubbins and LeMessurier covered all of the repair costs, which were estimated to be several million dollars.[31]

Publication[]

Since no structural failure occurred, the work was only publicized in a lengthy article in The New Yorker in 1995.[27][32] The 1995 story in The New Yorker described the student as a "young man, whose name has been lost in the swirl of subsequent events" who called LeMessurier saying "that his professor had assigned him to write a paper on the Citicorp tower".[32][17] However, the student apparently never contacted LeMessurier directly.[17][33] According to the website Online Ethics, when one of LeMessurier's colleagues asked whether the student was female, "LeMessurier responded that he didn't know because he had not actually spoken with the student."[33] LeMessurier had died in 2007 without specifying how much of the exchange between the student and the engineer had been brought to his attention.[18]

Hartley identified herself as the engineering student in 2011, years after the New Yorker article was published.[17] Hartley said she had spoken with Joel S. Weinstein at LeMessurier's office.[17]

Ethical questions[]

According to the American Institute of Architecture Trust case study,[18] "many have viewed the actions of LeMessurier as nearly heroic, and many engineering schools and ethics educators now use LeMessurier’s story as an example of how to act ethically." However, others have criticized LeMessurier for his lack of oversight that led to the issues, as well as his lack of honesty toward neighborhood residents, architects, engineers, and other members of the public when the issues were discovered. Architect Eugene Kremer discussed the ethical questions raised in this case.[24] Kremer mentioned six key points:[34]

  1. Analysis of wind loads. In his initial plans, LeMessurier relied only on calculations required by building codes, rather than checking all calculations.[13][24]
  2. Design changes. The builders had made a quick decision to use bolted joints without consulting LeMessurier.[13][24]
  3. Professional responsibility. Before LeMessurier decided to make Citicorp aware of the design defects, he briefly considered concealing the issues instead.[24][25]
  4. Public statements. In press interviews and releases at the time, officials either omitted or lied about details of the defects.[24][35]
  5. Public safety. When Hurricane Ella threatened the city in August and September 1978, evacuation plans for the surrounding area were made in secret.[30]
  6. Advancement of professional knowledge. Concealing this problem for almost 20 years prevented ethical and engineering learning that could have taken place.[24]

References[]

  1. ^ "Citigroup Center – The Skyscraper Center". Council on Tall Buildings and Urban Habitat. Archived from the original on June 15, 2012.
  2. ^ "601 Lexington Avenue". Emporis. Retrieved January 1, 2021.
  3. ^ Landmarks Preservation Commission 2016, p. 1.
  4. ^ White, Norval; Willensky, Elliot & Leadon, Fran (2010). AIA Guide to New York City (5th ed.). New York: Oxford University Press. p. 320. ISBN 978-0-19538-386-7.
  5. ^ a b c "Manhattan's Fifth Tallest Building Is Designed for Energy Conservation" (PDF). AIA Journal. 60 (4): 11, 61. October 1973.
  6. ^ "Plan for Skyscraper On Lexington Ave. Detailed by Citibank". The New York Times. July 25, 1973. ISSN 0362-4331. Retrieved April 3, 2021.
  7. ^ "Architectural Awards of Excellence" (PDF). American Institute of Steel Construction. 1978. p. 17. Retrieved April 6, 2021.
  8. ^ Landmarks Preservation Commission 2016, p. 7.
  9. ^ Goldberger, Paul (October 12, 1977). "Citicorp's Center Reflects Synthesis of Architecture". The New York Times. ISSN 0362-4331. Retrieved April 5, 2021.
  10. ^ Stern, Mellins & Fishman 1995, p. 490.
  11. ^ Alpern, Andrew; Durst, Seymour (2011). Holdouts! : the buildings that got in the way. Old York Foundation Distributed by David R. Godine, Publisher. p. 116. ISBN 978-1-56792-443-5. OCLC 722452921.
  12. ^ Stern, Mellins & Fishman 1995, p. 492.
  13. ^ a b c d e f Morgenstern 1995, p. 46.
  14. ^ "At New York's Citicorp Center, a structure of masterly invention underlies the urbane face of a skyscraper in the grand manner" (PDF). Architectural Record. 159 (E3): 69. August 1978.
  15. ^ Stern, Mellins & Fishman 1995, p. 493.
  16. ^ a b c d e f Werner, Joel (April 17, 2014). "The Design Flaw That Almost Wiped Out an NYC Skyscraper". Slate. Retrieved April 17, 2014.
  17. ^ a b c d e f McGinn, Robert (2018). The Ethical Engineer: Contemporary Concepts and Cases. Princeton University Press. p. 82. ISBN 978-1-4008-8910-5.
  18. ^ a b c d e f g h i j k Vardaro, Michael. "Case Study: The Citicorp Center Design". AIA Trust. Retrieved November 29, 2020.
  19. ^ Hartley, Diane Lee (1978). "Implications of a Major Urban Office Complex: The Scientific, Social and Symbolic Meanings of en_US Citicorp Center, New York City - V. 1 and 2". Princeton University Senior Theses.
  20. ^ Morgenstern 1995, pp. 46–47.
  21. ^ a b Morgenstern 1995, p. 47.
  22. ^ a b Morgenstern 1995, pp. 47–48.
  23. ^ a b Morgenstern 1995, pp. 48–49.
  24. ^ a b c d e f g h Kremer, Eugene (Fall 2002). "(Re)Examining the Citicorp Case: Ethical Paragon or Chimera". Cross Currents. 52 (3).
  25. ^ a b Morgenstern 1995, p. 48.
  26. ^ a b c Morgenstern 1995, p. 50.
  27. ^ a b c Landmarks Preservation Commission 2016, p. 9.
  28. ^ "Citicorp Bldg. To Get $1M in Wind Bracing". New York Daily News. August 9, 1978. p. 271. Retrieved April 6, 2021 – via newspapers.com.
  29. ^ "Citicorp Tower Gets More Steel Bracing As Added Precaution". The Wall Street Journal. August 9, 1978. p. 15. ISSN 0099-9660. ProQuest 134301488.
  30. ^ a b c Morgenstern 1995, pp. 52–53.
  31. ^ a b Morgenstern 1995, p. 53.
  32. ^ a b Morgenstern 1995, p. 45.
  33. ^ a b "William LeMessurier - The Fifty-Nine-Story Crisis: A Lesson in Professional Behavior". Online Ethics. May 29, 1995. Retrieved July 8, 2021.
  34. ^ Delatte, Norbert J. (January 1, 2009). Beyond Failure: Forensic Case Studies for Civil Engineers. ACSE Press. p. 340. ISBN 978-0-7844-7228-6. Retrieved March 13, 2019.
  35. ^ Morgenstern 1995, p. 51.

Sources[]

Retrieved from ""