Eastern Interconnection
This article needs additional citations for verification. (August 2015) |
The Eastern Interconnection is one of the two major alternating-current (AC) electrical grids in the North American power transmission grid. The other major interconnection is the Western Interconnection. The three minor interconnections are the Quebec, Alaska, and Texas interconnections.
All of the electric utilities in the Eastern Interconnection are electrically tied together during normal system conditions and operate at a synchronized frequency at an average of 60 Hz. The Eastern Interconnection reaches from Central Canada eastward to the Atlantic coast (excluding Quebec), south to Florida, and back to the western Great Plains (excluding most of Texas).
Interconnections can be tied to each other via high-voltage direct current power transmission lines (DC ties), or with variable-frequency transformers (VFTs), which permit a controlled flow of energy while also functionally isolating the independent AC frequencies of each side. The Eastern Interconnection is tied to the Western Interconnection with six DC ties, to the Texas Interconnection with two DC ties, and to the Quebec Interconnection with four DC ties and a VFT.
In 2016, National Renewable Energy Laboratory simulated a year with 30% renewable energy (wind and solar power) in 5-minute intervals. Results show a stable grid with some changes in operation.[1][2]
Electricity demand[]
The North American Electric Reliability Corporation (NERC) reported in 2008 the following actual and projected consumption for the regions of the Eastern Interconnection (all figures in gigawatts):[3]
in GW | Summer | Winter | ||||
---|---|---|---|---|---|---|
Region | 2007 | 2017 | Growth | 2007 | 2017 | Growth |
FRCC | 47 | 57 | 21.3% | 42 | 60 | 42.9% |
MRO (US) | 42 | 52 | 23.8% | 35 | 42 | 20.0% |
NPCC (US) | 61 | 69 | 13.1% | 48 | 53 | 10.4% |
RFC | 180 | 209 | 16.1% | 141 | 164 | 16.3% |
SERC | 209 | 243 | 16.3% | 179 | 209 | 16.8% |
SPP | 43 | 51 | 18.6% | 31 | 38 | 22.6% |
US- East Interconnection | 582 | 681 | 17.0% | 476 | 566 | 18.9% |
MRO (CAN) | 6.2 | 6.9 | 11.3% | 7.3 | 8.2 | 12.3% |
NPCC (CAN) | 50.3 | 50.7 | 0.8% | 65.0 | 66.7 | 2.6% |
CAN- East Interconnection | 56.5 | 57.6 | 2.0% | 72.3 | 74.9 | 3.6% |
Eastern Interconnection | 638.5 | 738.6 | 15.7% | 548.3 | 640.9 | 16.9% |
See also[]
References[]
- ^ "Eastern Renewable Generation Integration Study". National Renewable Energy Laboratory. Retrieved 8 September 2016.
- ^ Bloom et al. Eastern Renewable Generation Integration Study page xvii. National Renewable Energy Laboratory, August 2016. Technical Report NREL/TP-6A20-64472-ES. Quote: "integrating up to 30% variable wind and PV generation into the power system is technically feasible at a five-minute interval"
- ^ Load Forecasting Working Group of the Reliability Assessment Subcommittee (August 2008). "2008-2017 Regional and National Peak Demand and Energy Forecasts Bandwidths" (PDF). North American Electric Reliability Corporation: 7–12. Archived from the original (PDF) on 2009-03-27. Retrieved 2008-12-15. Cite journal requires
|journal=
(help)
Further reading[]
- 2008 Long Term Reliability Assessment 2008-2017 (PDF). North American Electric Reliability Corporation. 27 January 2009. Retrieved 2 March 2016.
- 2015 State of Reliability (PDF). North American Electric Reliability Corporation. May 2015. Retrieved 2 March 2016.
- Current projects
- Eastern Interconnection
- Electric power transmission systems in the United States
- Wide area synchronous grids
- Electric grid interconnections in North America