Electricity (Supply) Act 1935

From Wikipedia, the free encyclopedia
Electricity (Supply) Act 1935
Act of Parliament
Long titleAn Act to authorise the Central Electricity Board to make certain arrangements with authorised undertakers who are the owners of, or control, generating stations which are not selected stations; to authorise the Central Electricity Board to supply electricity directly to railway companies for certain purposes; to amend sections eleven and twelve of the Electricity (Supply) Act, 1926; and for purposes connected with the matters aforesaid.
Citation25 Geo. 5 c. 3
Territorial extentGreat Britain
Dates
Royal assent12 February 1935
Other legislation
AmendsElectricity (Supply) Acts 1882 to 1933
Repealed byElectricity Act 1989
Status: Repealed

The Electricity (Supply) Act 1935 (25 Geo. 5. c. 3)[1] was an Act of the Parliament of the United Kingdom which amended the law on the supply of electricity. This Act was construed as one with the Electricity (Supply) Acts 1882 to 1933, and was cited as the Electricity (Supply) Acts 1882 to 1935. It authorised the Central Electricity Board to make arrangements with owners of generating stations that were not selected stations; it authorised the Central Electricity Board to supply electricity directly to railway companies; and amended Sections 11 and 12 of the Electricity (Supply) Act 1926.[2]

Background[]

The Central Electricity Board had been established by Section 1 of the Electricity (Supply) Act 1926. Its duties (Section 2) included the identification of selected electricity generating stations, generally those that could produce electricity at the lowest cost.[3] There were a number of marginal stations for which the price the Central Electricity Board was able to offer was still not below the working costs.[4] Agreements were reached for these stations to take a supply from the board bringing the station under grid control. These agreements were ultra vires and were retrospectively sanctioned by section 1 of the 1935 Act.[4]

Section 11 of the Electricity (Supply) Act 1919 had prohibited railway companies from building generating stations unless they could demonstrate that electricity undertakers could not provide a supply at an equivalent or lesser cost.[5] Railway companies had to negotiate with multiple undertakings along the route of their tracks. With the construction of the National Grid (1927–33) these arrangements had become wasteful and impracticable. Section 3 of the 1935 Act address this issue and permitted the Central Electricity Board to supply in bulk to railway companies.[5][3]

The Central Electricity Board had, in some cases, offered long term concessions to undertakings to undercut private generation. These arrangements were retrospectively permitted by Section 2 of the 1935 Act.[6]

Provisions of the Act[]

The Electricity (Supply) Act 1935 received royal assent on 12 February 1935. Its long title was ‘An Act to authorise the Central Electricity Board to make certain arrangements with authorised undertakers who are the owners of, or control, generating stations which are not selected stations; to authorise the Central Electricity Board to supply electricity directly to railway companies for certain purposes; to amend sections eleven and twelve of the Electricity (Supply) Act, 1926; and for purposes connected with the matters aforesaid.’

The Act comprised four sections as follows.

Section 1 (1) gave the Central Electricity Board the power to enter into agreements concerning operation with the owners or operators of generating stations that are not selected stations. Such agreements include regulating the manner in which the station is operated and maintained and including supplying electricity to the board and taking a supply from the board.

Section 1 (2) required the Electricity Commissioners to inquire into the working of past arrangements to which Section 1 (1) applies, to ensure that arrangements did not entail a financial loss to the Board.

Section 2 gave the Central Electricity Board the power to supply electricity to authorised undertakers at a price and a tariff specified by Section 11 of the 1926 Act.

Section 3 specified the price to be charged by authorised undertakers for electricity supplied to railway companies. It gave the Electricity Commissioners the power to specify the charges and allowances to be included in the price to be charged.

Section 4 gave the Central Electricity Board the power to supply electricity directly to railway companies.

Section 5 defines the short title, citation, interpretation and extent of the Act. The Act did not extend to Northern Ireland.

Operation of the Act[]

The provisions of the Electricity (Supply) Acts 1882 to 1935 remained un-amended until the nationalisation of the industry under the Electricity Act 1947.

Later Acts[]

The Electricity Act 1947[7] (10 & 11 Geo. 6, c. 54), nationalised the UK electricity supply industry. The Electricity Commissioners, the power companies, and the joint electricity authorities were abolished. The ownership of electricity generation and transmission facilities was vested in the British Electricity Authority.

See also[]

References[]

  1. ^ "Electricity (Supply) Act 1935". legislation.co.uk. 1935. Retrieved 7 August 2020.
  2. ^ "Electricity (Supply) Act 1926". legislation.co.uk. 1926. Retrieved 7 August 2020.
  3. ^ a b Electricity Council (1987). Electricity Supply in the United Kingdom: a Chronology. London: Electricity Council. p. 52. ISBN 085188105X.
  4. ^ a b Hannah, Leslie (1979). Electricity before Nationalisation. London: Macmillan. p. 114. ISBN 0333220862.
  5. ^ a b Hannah, Leslie (1979). Electricity before Nationalisation. London: Macmillan. pp. 162–65. ISBN 0333220862.
  6. ^ Hannah, Leslie (1979). Electricity before Nationalisation. London: Macmillan. pp. 176, 383. ISBN 0333220862.
  7. ^ "Electricity Act 1947". loogislation.gov.uk. 1947. Retrieved 7 August 2020.
Retrieved from ""