HTR-PM

From Wikipedia, the free encyclopedia

The HTR-PM (球床模块式高温气冷堆核电站) is a small modular nuclear reactor in China. It is the world’s first prototype of a high-temperature gas-cooled (HTGR) pebble-bed generation IV reactor. The reactor unit has a thermal capacity of 250 MW, and two reactors are connected to a single steam turbine to generate 210 MW of electricity.[1]Its role is to replace coal-fired power plants in China's interior, in line with the country's plan to reach carbon neutrality by 2060.[2]

History[]

The HTR-PM is a high-temperature gas-cooled reactor (HTGR) and is partly based on the earlier HTR-10 prototype reactor.[1] The demonstration project for the High-Temperature gas-cooled Reactor Pebble-bed Module (HTR-PM) was launched in 2001.[3] Work on the first demonstration power plant, composed of two reactors driving a single steam turbine, began in December 2012 in Shidao Bay Nuclear Power Plant in Shandong province. The pressure vessels of the two reactors were installed in 2016. The steam generator shell, hot gas duct shell and reactor pressure vessel shell of the first reactor in the HTR-PM demonstration project were successfully paired on 28 April 2020, paving the way for the installation of the main helium fan.[4] [5]

The cold functional tests of the HTR-PM were successfully completed between October and November 2020. The air and helium mixture was pressurized to a maximum of 8.9 MPa in the primary coolant loop.[6] Following the cold functional tests, the hot tests were performed in three stages: vacuum dehumidification, heating and dehumidification and the hot functional tests. The hot tests began in December 2020, and would continue before bringing the reactor online.[7] On 12 September 2021, the first of two reactors achieved criticality.[8][9] On 11 November 2021, reactor two achieved first criticality. [10] On 20 December 2021, reactor one was connected to the state power grid and began producing power.[11]

Concerns[]

Additional safety measures have been recommended for this type of reactor based on experiences with the German AVR reactor.[12]

See also[]

References[]

  1. ^ a b Zhang, Zuoyi; Dong, Yujie; Li, Fu; Zhang, Zhengming; Wang, Haitao; Huang, Xiaojin; Li, Hong; Liu, Bing; Wu, Xinxin; Wang, Hong; Diao, Xingzhong; Zhang, Haiquan; Wang, Jinhua (March 2016). "The Shandong Shidao Bay 200 MW e High-Temperature Gas-Cooled Reactor Pebble-Bed Module (HTR-PM) Demonstration Power Plant: An Engineering and Technological Innovation". Engineering. 2 (1): 112–118. doi:10.1016/J.ENG.2016.01.020.
  2. ^ "China starts up world's first high-temperature gas-cooled reactor". Global Construction Review (in British English). 15 September 2021. Retrieved 28 October 2021.
  3. ^ "HTR-PM: Making dreams come true". Nuclear Engineering International. 26 February 2019.
  4. ^ "Key components of second HTR-PM reactor connected : New Nuclear - World Nuclear News". world-nuclear-news.org. Retrieved 25 May 2020.
  5. ^ "Milestone achieved on China's HTR-PM - Nuclear Engineering International". www.neimagazine.com. Retrieved 25 May 2020.
  6. ^ "Cold testing of HTR-PM reactors completed : New Nuclear - World Nuclear News". www.world-nuclear-news.org. 4 November 2020. Retrieved 25 July 2021.{{cite web}}: CS1 maint: url-status (link)
  7. ^ "Hot functional testing of HTR-PM reactors starts : New Nuclear - World Nuclear News". World Nuclear News. 4 January 2021. Retrieved 25 July 2021.{{cite web}}: CS1 maint: url-status (link)
  8. ^ "China's HTR-PM reactor achieves first criticality : New Nuclear - World Nuclear News". www.world-nuclear-news.org. Retrieved 3 October 2021.
  9. ^ "First criticality for China's HTR-PM demonstration project - Nuclear Engineering International". www.neimagazine.com. Retrieved 28 October 2021.
  10. ^ "Dual criticality for Chinese demonstration HTR-PM : New Nuclear - World Nuclear News".
  11. ^ "Demonstration HTR-PM connected to grid".
  12. ^ Moormann, Rainer; Kemp, R. Scott; Li, Ju (October 2018). "Caution Is Needed in Operating and Managing the Waste of New Pebble-Bed Nuclear Reactors". Joule. 2 (10): 1911–1914. doi:10.1016/j.joule.2018.07.024.
Retrieved from ""