Nuclear power in China

From Wikipedia, the free encyclopedia

100
200
300
400
2014
2016
2019
Nuclear power generation in China (TWh)[1][2]
1
2
3
4
5
1999
2005
2010
2015
2019
Nuclear power share of total electricity in China (%)[3][1][2]

China is one of the world's largest producers of nuclear power. The country ranks third in the world both in total nuclear power capacity installed and electricity generated, accounting for around one tenth of global nuclear power generated. Nuclear power contributed 4.9% of the total Chinese electricity production in 2019, with 348.1 TWh. This is an increase of 18.1% from 2018; two new reactors came online in 2019.[2] Recent construction has fallen short of previously announced targets. As of June 2021, China has a total nuclear power generation capacity of 49.6 GW from 50 reactors, with additional 17.1 GW under construction.[4]

Nuclear power has been looked into as an alternative to coal due to increasing concerns about air quality, climate change and fossil fuel shortages.[5][6] In 2009, China's National Development and Reform Commission indicated the intention to raise the percentage of China's electricity produced by nuclear power to 6% by 2020.[7][failed verification] More long-term plans for future capacity are 120-150 GW by 2030.[8]

China has two major nuclear power companies, the China National Nuclear Corporation operating mainly in north-east China, and the China General Nuclear Power Group (formerly known as China Guangdong Nuclear Power Group) operating mainly in south-east China.[9]

China aims to maximize self-reliance on nuclear reactor technology manufacturing and design, although international cooperation and technology transfer are also encouraged. Advanced pressurized water reactors such as the Hualong One are the mainstream technology in the near future, and the Hualong One is also planned to be exported.[10][11] By mid-century fast neutron reactors are seen as the main technology, with a planned 1400 GW capacity by 2100.[12][13][14] China is also involved in the development of nuclear fusion reactors through its participation in the ITER project, having constructed an experimental nuclear fusion reactor known as EAST located in Hefei,[15] as well as research and development into the thorium fuel cycle as a potential alternative means of nuclear fission.[16]

History[]

Qinshan Nuclear Power Plant, located in Zhejiang China

In 1955, the China National Nuclear Corporation (CNNC) was established. On 8 February 1970, China issued its first nuclear power plan, and the 728 Institute (now called )[17] was founded. On 15 December 1991, China's first nuclear power reactor, a 288 MWe PWR at the Qinshan Nuclear Power Plant, was connected to the grid.[18] It is of type CNP-300.

The nuclear safety plan of 2013 stated that beyond 2016 only Generation III plants would be started, and until then only a very few Generation II+ plants would be started.[19]

In 2014 China still planned to have 58 GW of capacity by 2020.[20] However, due to reevaluation following the Fukushima Daiichi nuclear disaster in Japan, few plants commenced construction from 2015, and this target was not met.[21]

In 2019 China had a new target of 200 GWe of nuclear generating capacity by 2035, which is 7.7% out of predicted total electricity generating capacity of 2600 GWe.[2]

Safety and regulation[]

The National Nuclear Safety Administration (NNSA), under the China Atomic Energy Authority, is the licensing and regulatory body which also maintains international agreements regarding safety. It was set up in 1984 and reports to the State Council directly. In relation to the AP1000, NNSA works closely with the US Nuclear Regulatory Commission.

China has requested and hosted 12 Operational Safety Review Team (OSART) missions from IAEA teams to October 2011, and each plant generally has one external safety review each year, either OSART, WANO peer review, or CNEA peer review (with the Research Institute for Nuclear Power Operations).[22]

The challenge (in the proposed rapid build-out of nuclear power) for the government and nuclear companies is to "keep an eye on a growing army of contractors and subcontractors who may be tempted to cut corners".[9] China is advised to maintain nuclear safeguards in a business culture where quality and safety are sometimes sacrificed in favor of cost-cutting, profits, and corruption. China has asked for international assistance in training more nuclear power plant inspectors.[9] In 2011, concerns were raised that rapid nuclear expansion could lead to a shortfall of fuel, equipment, qualified plant workers, and safety inspectors.[23][24]

Following the Fukushima Daiichi nuclear disaster in Japan, China announced on 16 March 2011, that all nuclear plant approvals were being frozen, and that 'full safety checks' of existing reactors would be made.[25][26] Although Zhang Lijun, Vice Minister of Environmental Protection, has indicated that China's overall nuclear energy strategy would continue,[26] some commentators have suggested that additional safety-related costs and public opinion could cause a rethink in favor of an expanded renewable energy program.[26][27] In April 2011, China Daily reported that approvals for construction of nuclear power plants in marine areas have been suspended.[28] The safety inspections were due to finish by October 2011, and the current status of the projects is unclear.[29] In April 2012, Reuters reported that China was likely to resume nuclear power plants approvals sometime during the first half of 2012. The official target of a capacity of 40 GW by 2020 is unchanged but earlier plans to increase this to 86 GW has been reduced to 70-75 GW due shortages of equipment and qualified personnel as well as safety concerns.[30]

China's current methods for storing spent nuclear fuel (SNF) are only sustainable until the mid 2020s, and a policy to handle SNF needs to be developed.[31]

In 2017 new laws strengthened the powers of the National Nuclear Safety Administration, creating new "institutional mechanisms", a clearer "division of labour" and more disclosure of information.[32]

Reactor technologies[]

CPR-1000[]

The most numerous reactor type in China is the CPR-1000, with 22 units operational. This reactor type is a Chinese development of the French 900 MWe three cooling loop design imported in the 1990s, with most of the components now built in China. Intellectual property rights are retained by Areva, which affects CPR-1000 overseas sales potential.[5]

China's first CPR-1000 nuclear power plant, Ling Ao-3, was connected to the grid on 15 July 2010.[33] The design has been progressively built with increasing levels of Chinese components. Shu Guogang, GM of China Guangdong Nuclear Power Project said, "We built 55 percent of Ling Ao Phase 2, 70 percent of Hongyanhe, 80 percent of Ningde and 90 percent of Yangjiang Station."[citation needed]

In 2010 the China Guangdong Nuclear Power Corporation announced the ACPR1000 design, a further design evolution of the CPR-1000 to a Generation III level, which would also replace intellectual property right limited components. CGNPC aimed to be able to independently market the ACPR1000 for export by 2013.[34] A number of ACPR1000 are under construction in China, but for export this design was superseded by the Hualong One.

Hualong One[]

Since 2011 the China General Nuclear Power Group and the China National Nuclear Corporation have been progressively merging their CPR-1000 and ACP1000 designs, to become the joint Hualong One design. Both are three-loop designs originally based on the same French design, but had different nuclear cores. Power output will be 1150 MWe, with a 60-year design life, and would use a combination of passive and active safety systems with a double containment. The first units to be constructed will be Fuqing 5 and 6, followed by Fangjiashan 3 and 4, Fangchenggang 3 and 4. In December 2015 the two companies agreed to create Hualong International Nuclear Power Technology Co as a joint venture to promote the Hualong One in overseas markets,[10] which was officially launched in March 2016.[11]

AP1000[]

Sanmen Nuclear Power Station, located in Zhejiang China

The Westinghouse AP1000 is the main basis of China's move to Generation III technology, and involves a major technology transfer agreement. It is a 1250 MWe gross reactor with two coolant loops. The first four AP1000 reactors are being built at Sanmen and Haiyang, for CNNC and CPI respectively. At least eight more at four sites are firmly planned after them.[18]

In 2016 the build was reported to be running over three years late, mainly due to key component delays and project management issues.[35][36] In February 2018 Sanmen 2 completed hot testing, and in April 2018 Sanmen 1 began fuel loading.[37][38]

In July 2018 the first reactor was connected to the grid with commercial operation expected by the end of the year.[39]

Following Westinghouse's bankruptcy in 2017, it was decided in 2019 to build the Hualong One rather than the AP1000 at Zhangzhou.[40]

EPR[]

In 2007 negotiations started with the French company Areva concerning the EPR third generation reactors. Two Areva EPR reactors have been built at Taishan, and at least two more are planned. The reactors are 4590 MWt, with net power 1660 MWe.

In 2016 the build was reported to be running over three years late, mainly due to key component delays and project management issues.[35][36] In June 2018 the first reactor achieved criticality with full operation expected by the end of the year.[41] On 12 December 2018 the Taishan-1 EPR began full commercial operation.[42]

In October 2008, Areva and CGNPC announced establishment of an engineering joint venture as a technology transfer vehicle for development EPR and other PWR plants in China and later abroad. The JV will be held 55% by CGNPC and other Chinese interests, and 45% by Areva. It will engineer and procure equipment for both the EPR and the CPR-1000.

CAP1400[]

In 2008 and 2009, Westinghouse made agreements to work with the State Nuclear Power Technology Corporation (SNPTC) and other institutes to develop a larger version of the AP1000, the CAP1400 of 1,400 MWe capacity, possibly followed by a 1,700 MWe design. China will own the intellectual property rights for these larger designs. Exporting the new larger units may be possible with Westinghouse's cooperation.[5]

In December 2009, a Chinese joint venture was set up to build an initial CAP1400 near the HTR-10 Shidaowan site.[5][43]

In September 2014 the Chinese nuclear regulator approved the design safety analysis following a 17-month review.[44] In May 2015 the CAP1400 design passed an International Atomic Energy Agency's Generic Reactor Safety Review.[45] In 2015 site preparation started, and approval to progress was expected by the end of the year.[46][47] However, as of 2017, construction approval has been delayed mainly because of the long delays in completing the first AP1000.[48] Equipment for the CAP1400 is being manufactured, and as of 2021 construction of two units is underway at Huaneng Group's Shidaowan site in Shandong province while the official approval is still pending.[49][50]

In September 2020, with construction design of the demonstration units over 99% complete, China's State Power Investment Corporation launched the design for more widespread deployment consideration. It was given the name Guohe One.[51]

CANDU reactors[]

Two AECL 728MW CANDU-6 reactors are located at the Qinshan Nuclear Power Plant, the first went online in 2002,the second in 2003. CANDU reactors can use low grade reprocessed uranium from conventional reactors as fuel, thereby reducing China's stock of spent nuclear fuel.[52]

In September 2016 it was announced that SNC-Lavalin has signed an agreement in principle with CNNC and the Shanghai Electric Group to design, market and build the advanced CANDU reactor.[53]

VVER[]

The first two VVER-1000 units at Tianwan Nuclear Power Plant

Russia's Atomstroyexport was general contractor and equipment provider for the Tianwan AES-91 power plants using the V-428 version of the well-proven VVER-1000 reactor of 1060 MWe capacity. Russia's Energoatom is responsible for maintenance from 2009. Two further Tianwan units will use the same version of the VVER-1000 reactor.

On 7 March 2019 China National Nuclear Corporation (CNNC) and Atomstroyexport signed the detailed contract for the construction of four VVER-1200s, two each at the Tianwan Nuclear Power Plant and the Xudabao Nuclear Power Plant. Construction will start in May 2021 and commercial operation of all the units is expected between 2026 and 2028.[54]

Generation IV reactors[]

Control room of HTR-10 reactor at Tshinghua University

China is developing several generation IV reactor designs. The HTR-PM, a HTGR, is under construction. The HTR-PM is a descendant of the AVR reactor, and it is partly based on the earlier Chinese HTR-10 reactor. A sodium-cooled fast reactor, the CFR-600, is also under construction.

ACP100 small modular reactor[]

In July 2019 China National Nuclear Corporation announced it would start building a demonstration ACP100 small modular reactor (SMR) on the north-west side of the existing Changjiang Nuclear Power Plant by the end of the year.[55] Design of the ACP100 started in 2010. It is a fully integrated reactor module with an internal coolant system, with a 2-year refuelling interval, producing 385 MWt and about 125 MWe.[56]

Nuclear power plants[]

Nuclear power plants in China (view)
Red pog.svg Active plants
Green pog.svg Under construction plants
Blue pog.svg Firmly planned plants

Most nuclear power plants in China are located on the coast and generally use seawater for cooling a direct once-through cycle. The New York Times has reported that China is placing many of its nuclear plants near large cities, and there is a concern that tens of millions of people could be exposed to radiation in the event of an accident.[9] China's neighboring Daya Bay and Lingao nuclear plants have around 28 million people within a 75-kilometre radius that covers Hong Kong.[57]

Future projects[]

Following the Fukushima accident and consequent pause in approvals for new plants, the target adopted by the State Council in October 2012 became 60 GWe by 2020, with 30 GWe under construction. In 2015 the target for nuclear capacity on line in 2030 was 150 GWe, providing almost 10% of electricity, and 240 GWe in 2050 providing 15%.

However, from 2016 to 2018 there was a further hiatus in the new build programme, with no new approvals for at least two years, causing the programme to slow sharply. Delays in the Chinese builds of AP1000 and EPR reactors, together with the bankruptcy in the U.S. of Westinghouse, the designer of the AP1000, have created uncertainties about the future direction. Also some regions of China now have excess generation capacity, and it has become less certain to what extent electricity prices can economically sustain nuclear new build while the Chinese government is gradually liberalising the generation sector.[48][58]

In 2018 a Nuclear Engineering International journal analysis suggests a below-plan capacity of 90 GWe is plausible for 2030.[59] As of 2020, China had 45GW of operational nuclear power, with 11GW under construction (see Table below)

Bloomberg News reported that the 2020 National People's Congress supported future building of 6 to 8 reactors a year, which Bloomberg considered likely to be dominated by the domestic Hualong One design.[60] In 2019 China had a new target of 200 GWe of nuclear generating capacity by 2035, which is 7.7% out of predicted total electricity generating capacity of 2600 GWe.[2]

The role of the IPPs[]

The first major successful profitable commercial project was the Daya Bay Nuclear Plant, which is 25% owned by CLP Group of Hong Kong and exports 70% of its electricity to Hong Kong. Such imports supply 20% of Hong Kong's electricity.

In order to access the capital needed to meet the 2020 target of 80GW, China has begun to grant equity in nuclear projects to China's Big Five power corporations:

  • Huaneng Group,
  • Huadian Group – Fujian Fuqing nuclear power project II and III
  • Datang Group,
  • China Power Investment Group – Jiangxi Pengze Nuclear
  • Guodian Group

Like the two nuclear companies China National Nuclear Corporation and China Guangdong Nuclear Power Group (CGNPG) the Big Five are State-owned "Central Enterprises" (中央企业) administered by SASAC. However, unlike the two nuclear companies, they have listed subsidiaries in Hong Kong and a broad portfolio of thermal, hydro and wind.

Summary of nuclear power plants[]

Summary table of nuclear power plants in China[61][3]
Nuclear power plant operational reactors reactors under construction reactors planned total
units net capacity
(MW)
units net capacity
(MW)
units net capacity
(MW)
units net capacity
(MW)
Bailong N/A N/A 6 6,600 6 6,600
Changjiang 2 1,202 1 1000 1 1000 4 3,202
CEFR 1 20 N/A N/A 1 20
Daya Bay (Dayawan) 2 1,888 N/A N/A 2 1,888
Fangchenggang 2 2,000 2 2,000 2 2,000 6 6,000
Fangjiashan 2 2,024 N/A N/A 2 2,024
Fuqing 5 5,000 1 1,000 N/A 6 6,000
Haiyang 2 2,340 N/A 6 6,600 8 8,940
Hongyanhe 5 5,305 1 1,061 N/A 6 6,366
Huizhou/Taipingling N/A 2 2,232 N/A 2 2,232
Ling Ao 4 3,914 N/A N/A 4 3,914
(Shanwei) N/A N/A 2 2,200 2 2,200
Ningde 4 4,072 N/A 2 2,100 6 6,172
N/A N/A 2 2,200 2 2,200
Qinshan 7 4,110 N/A N/A 7 4,110
[62] N/A 1 1,000 5 5,000 6 6,000
Sanmen 2 2,314 N/A 2 2,314 4 4,628
Shidao Bay (Shidaowan) N/A 3 3,000 N/A 3 3,000
Taishan 2 3,320 N/A N/A 2 3,320
N/A N/A 4 4,400 4 4,400
Tianwan 6 6,080 1 1,100 1 1,100 8 8,280
Xianning N/A N/A 2 2,200 2 2,200
Xiapu N/A 2 1,000 N/A 2 1,000
Xudabao N/A 1 1,100 3 3,300 4 4,400
Yangjiang 6 6,120 N/A N/A 6 6,120
Zhangzhou N/A 2 2,200 4 4,400 6 6,600
Total 50 47,518 16 15,727 45 48,061 111 111,306
Operational and uc. data based on data from IAEA's PRIS system

Fuel cycle[]

China is evaluating the construction of a high level waste (HLW) repository in the Gobi Desert, probably constructed near starting around 2041.[63]

Companies[]

Research[]

The relative lack of water available for cooling reactors west of the Heihe–Tengchong Line (the area shown in yellow) is seen as a limiting factor for the development of traditional forms of nuclear power there.

In January 2011, the Chinese Academy of Sciences began the TMSR research and development project to create reactors which, among other advances, will be air-cooled. A small prototype reactor of this type, the TMSR-LF1, is planned.[64] The LF1 will be sited in Gansu province,[65] in an industrial park in Minqin County.[66]

In February 2019, China's State Power Investment Corporation (SPIC) signed a cooperation agreement with the Baishan municipal government in Jilin province for the Baishan Nuclear Energy Heating Demonstration Project, which would use a China National Nuclear Corporation DHR-400 (District Heating Reactor 400 MWt).[67][68]

Public opposition[]

China is experiencing civil protest over its ambitious plans to build more nuclear power plants following the Fukushima nuclear disaster. There has been "inter-provincial squabble" over a nuclear power plant being built near the southern bank of the Yangtze River. The plant in the centre of the controversy is located in Pengze county in Jiangxi and across the river the government of Wangjiang county in Anhui wants the project shelved.[69]

More than 1,000 people protested in Jiangmen City Hall in July 2013 to demand authorities abandon a planned uranium-processing facility that was designed as a major supplier to nuclear power stations. The Heshan Nuclear Power Industry Park was to be equipped with facilities for uranium conversion and enrichment as well as the manufacturing of fuel pellets, rods and finished assemblies. Protesters feared the plant would adversely affect their health, and the health of future generations. As the weekend protest continued, Chinese officials announced the state-run project's cancellation.[70]

By 2014, concerns about public opposition caused Chinese regulators to develop public and media support programmes, and developers to begin outreach programmes including site tours and visitor centres.[71]

In 2020 Bloomberg News reported that public opposition had stopped nuclear power construction on inland river sites, and caused the cancellation of a nuclear fuel plant in Guangdong in 2013.[60]

See also[]

References[]

  1. ^ Jump up to: a b "China's nuclear power generation rises in 2018 - Xinhua | English.news.cn". xinhuanet.com. Archived from the original on 2 May 2019. Retrieved 2 May 2019.
  2. ^ Jump up to: a b c d e "China's nuclear power output jumps 18% year on year". World Nuclear News. 24 February 2020. Retrieved 25 February 2020.
  3. ^ Jump up to: a b International Atomic Energy Agency (2018). "Power Reactor Information System (PRIS): China, People's Republic of". IAEA. Archived from the original on 28 August 2018. Retrieved 29 August 2018.
  4. ^ https://www.world-nuclear.org/information-library/country-profiles/countries-a-f/china-nuclear-power.aspx
  5. ^ Jump up to: a b c d "Nuclear Power in China". World Nuclear Association. 2 July 2010. Archived from the original on 12 February 2013. Retrieved 18 July 2010.
  6. ^ "[宁德] 宁德核电站在福鼎开工-图 - 福建之窗 66163.com". Fjnews.66163.com. 7 March 2008. Archived from the original on 7 July 2011. Retrieved 24 September 2013.
  7. ^ Suga, Masumi; Shunichi Ozasa (7 September 2009). "China to Build More Nuclear Plants, Japan Steel Says". Bloomberg.com. Retrieved 15 February 2011.
  8. ^ David Stanway (14 March 2016). "China's total nuclear capacity seen at 120-150 GW by 2030 - CGN". Reuters. Archived from the original on 15 March 2016. Retrieved 16 March 2016.
  9. ^ Jump up to: a b c d Keith Bradsher (15 December 2009). "Nuclear Power Expansion in China Stirs Concerns". New York Times. Archived from the original on 19 July 2016. Retrieved 21 January 2010.
  10. ^ Jump up to: a b "Chinese firms join forces to market Hualong One abroad". World Nuclear News. 31 December 2015. Archived from the original on 6 February 2016. Retrieved 6 February 2016.
  11. ^ Jump up to: a b "Hualong One joint venture officially launched". World Nuclear News. 17 March 2016. Archived from the original on 18 March 2016. Retrieved 17 March 2016.
  12. ^ Brook, Barry. "Summary of China's fast reactor programme". Brave New Climate. Archived from the original on 20 April 2016. Retrieved 13 April 2016.
  13. ^ "Fast Reactor Technology Development for Sustainable Supply of Nuclear Energy in China - China International Nuclear Symposium November 23-25, 2010, Beijing" (PDF). XU MI - China Institute of Atomic Energy. Archived (PDF) from the original on 28 September 2016.
  14. ^ "PACIFIC NUCLEAR COUNCIL (PNC) - 2nd QUARTER 2015 MEETING - Thursday, April 23, 2015 - Beijing, CHINA- Meeting Minutes (Final)" (PDF). Archived from the original (PDF) on 22 April 2016.
  15. ^ "China to build world's first "artificial sun" experimental device". People's Daily Online. 21 January 2006. Archived from the original on 5 June 2011. Retrieved 22 March 2011.
  16. ^ Ambrose Evans-Pritchard, 20 March 2011, Safe nuclear does exist, and China is leading the way with thorium Archived 25 March 2018 at the Wayback Machine, Telegraph UK
  17. ^ "Archived copy". Archived from the original on 16 February 2015. Retrieved 16 February 2015.CS1 maint: archived copy as title (link)
  18. ^ Jump up to: a b Daogang Lu (North China Electric Power University) (May 2010). "The Current Status of Chinese Nuclear Power Industry and Its Future". e-Journal of Advanced Maintenance. Japan Society of Maintenology. 2 (1). Archived from the original on 22 July 2011. Retrieved 14 August 2010.
  19. ^ Yun Zhou (31 July 2013). "China: The next few years are crucial for nuclear industry growth". Ux Consulting. Nuclear Engineering International. Archived from the original on 21 September 2013. Retrieved 8 August 2013.
  20. ^ "Start-up nearing for Chinese units". World Nuclear News. 25 March 2014. Archived from the original on 3 April 2014. Retrieved 31 March 2014.
  21. ^ "Archived copy". Archived from the original on 22 May 2018. Retrieved 21 May 2018.CS1 maint: archived copy as title (link)
  22. ^ "Nuclear Power in China". World Nuclear Association. October 2013. Archived from the original on 3 November 2013. Retrieved 25 October 2013.
  23. ^ "China Should Control Pace of Reactor Construction, Outlook Says". Bloomberg News. 11 January 2011. Archived from the original on 24 December 2014. Retrieved 10 March 2017.
  24. ^ Jonathan Watts (25 August 2011). "WikiLeaks cables reveal fears over China's nuclear safety". The Guardian. London. Archived from the original on 30 September 2013. Retrieved 12 December 2016.
  25. ^ the CNN Wire Staff (16 March 2011). "China freezes nuclear plant approvals - CNN.com". Edition.cnn.com. Archived from the original on 28 June 2011. Retrieved 16 March 2011.
  26. ^ Jump up to: a b c Will China's nuclear nerves fuel a boom in green energy? Archived 21 March 2011 at the Wayback Machine Channel 4, published 17 March 2011. Retrieved 17 March 2011
  27. ^ China’s Nuclear Energy Program Post-Fukushima Archived 18 March 2011 at the Wayback Machine China Bystander, published 16 March 2011. Retrieved 17 March 2011
  28. ^ Chris Oliver (6 April 2011). "China suspends waterfront nuclear-power approvals". Market Watch. Archived from the original on 16 October 2012. Retrieved 7 April 2011.
  29. ^ "China urges IAEA to enhance nuclear safeguards". Bloomberg Businessweek. 1 November 2011. Archived from the original on 29 July 2013. Retrieved 5 November 2011.
  30. ^ "Judy Hua and David Stanway, China launches new 650 MW nuclear reactor, 9 April 2012". Uk.reuters.com. 9 April 2012. Archived from the original on 27 September 2013. Retrieved 24 September 2013.
  31. ^ Rob Forrest (2 June 2014). "China's Nuclear Program and Spent Fuel Storage" (PDF). CISAC, Stanford University. Archived from the original (PDF) on 14 December 2014. Retrieved 14 December 2014.
  32. ^ Stanway, David (1 September 2017). "China's legislature passes nuclear safety law". Reuters. Archived from the original on 1 September 2017. Retrieved 1 September 2017.
  33. ^ "First power at China's Ling Ao". Nuclear Engineering International. 16 July 2010. Archived from the original on 13 June 2011. Retrieved 17 July 2010.
  34. ^ "China prepares to export reactors". World Nuclear News. 25 November 2010. Archived from the original on 30 December 2010. Retrieved 18 December 2010.
  35. ^ Jump up to: a b Steve Kidd (23 February 2015). "How serious are the delays in China's nuclear programme?". Nuclear Engineering International. Archived from the original on 2 April 2015. Retrieved 8 March 2015.
  36. ^ Jump up to: a b Steve Thomas (29 October 2016). "China's Nuclear Power Plans Melting Down". The Diplomat. Archived from the original on 29 October 2016. Retrieved 30 October 2016.
  37. ^ "Hot testing of Sanmen 2 AP1000 completed". world-nuclear-news.org. Archived from the original on 11 May 2018. Retrieved 24 May 2018.
  38. ^ "Fuel loading under way at Chinese AP1000". world-nuclear-news.org. Archived from the original on 24 May 2018. Retrieved 24 May 2018.
  39. ^ "Archived copy". Archived from the original on 10 July 2018. Retrieved 11 July 2018.CS1 maint: archived copy as title (link)
  40. ^ "Permits issued for construction of new Chinese plant". World Nuclear News. 15 October 2019. Archived from the original on 15 October 2019. Retrieved 15 October 2019.
  41. ^ "Archived copy". Archived from the original on 15 July 2018. Retrieved 11 July 2018.CS1 maint: archived copy as title (link)
  42. ^ https://www.world-nuclear.org/reactor/default.aspx/TAISHAN-1
  43. ^ "New reactor design taking shape in China". World Nuclear News. 15 January 2014. Archived from the original on 16 January 2014. Retrieved 16 January 2014.
  44. ^ "CAP1400 preliminary safety review approved". World Nuclear News. 9 September 2014. Archived from the original on 10 September 2014. Retrieved 10 September 2014.
  45. ^ "Large-scale Chinese reactor design passes IAEA safety review". World Nuclear News. 5 May 2016. Archived from the original on 4 October 2016. Retrieved 20 September 2016.
  46. ^ "China looks forward to reactor firsts". World Nuclear News. 14 September 2015. Archived from the original on 23 September 2015. Retrieved 24 September 2015.
  47. ^ LIAO Liang (September 2015). INTRODUCTION of CAP1400 (PDF). SNERDI (Report). IAEA. Archived (PDF) from the original on 4 October 2016. Retrieved 24 February 2016.
  48. ^ Jump up to: a b Kidd, Steve (10 August 2017). "Nuclear in China - why the slowdown?". Nuclear Engineering International. Archived from the original on 30 December 2017. Retrieved 30 December 2017.
  49. ^ "KSB coolant pump certified for use in Chinese NPPs". Nuclear Engineering International. 22 August 2019. Retrieved 11 September 2020.
  50. ^ "China readying for nuclear expansion, says Zheng". World Nuclear News. 11 September 2020. Retrieved 11 September 2020.
  51. ^ "China launches CAP1400 reactor design". World Nuclear News. 29 September 2020. Retrieved 29 September 2020.
  52. ^ "Archived copy". Archived from the original on 22 June 2017. Retrieved 21 June 2017.CS1 maint: archived copy as title (link)
  53. ^ Marotte, Bertrand (22 September 2016). "SNC-Lavalin strikes deal to build nuclear reactors in China". The Globe and Mail. Archived from the original on 19 April 2017. Retrieved 6 September 2017.
  54. ^ "AtomStroyExport unveils schedule for China projects". World Nuclear News. 3 April 2019. Archived from the original on 3 April 2019. Retrieved 3 April 2019.
  55. ^ "CNNC launches demonstration SMR project". World Nuclear News. 22 July 2019. Archived from the original on 22 July 2019. Retrieved 22 July 2019.
  56. ^ "Specific Design Consideration of ACP100 for Application in the Middle East and North Africa Region" (PDF). CNNC. 2 October 2017. Retrieved 22 July 2019.
  57. ^ Declan Butler (21 April 2011). "Reactors, residents and risk". Nature. 472 (7344): 400–1. doi:10.1038/472400a. PMID 21525903. S2CID 4371109. Archived from the original on 24 April 2011. Retrieved 22 April 2011.
  58. ^ David Stanway, Geert De Clercq (15 January 2018). "So close yet so far: China deal elusive for France's Areva". Times of Oman. Archived from the original on 13 February 2018. Retrieved 12 February 2018.
  59. ^ Kidd, Steve (1 August 2018). "Nuclear in China - where is it heading now?". Nuclear Engineering International. Archived from the original on 15 September 2018. Retrieved 15 September 2018.
  60. ^ Jump up to: a b "China to Dominate Nuclear as Beijing Bets on Homegrown Reactors". Bloomberg News. 1 June 2020. Retrieved 4 June 2020.
  61. ^ "China Nuclear Power | Chinese Nuclear Energy - World Nuclear Association". www.world-nuclear.org. Archived from the original on 7 September 2016. Retrieved 15 June 2018.
  62. ^ "Construction of new Chinese power plant begins : New Nuclear - World Nuclear News". www.world-nuclear-news.org. Retrieved 5 January 2021.
  63. ^ Tony Vince (8 March 2013). "Rock solid ambitions". Nuclear Engineering International. Archived from the original on 26 January 2016. Retrieved 9 March 2013.
  64. ^ Dai Zhimin, Zou Yang, and Chen Kun (4 November 2016). "Thorium Molten Salt Reactors (TMSR) Development in China" (PDF). International Atomic Energy Agency. Archived (PDF) from the original on 8 July 2018. Retrieved 7 July 2018.CS1 maint: multiple names: authors list (link)
  65. ^ "中科院与甘肃省签署钍基熔盐堆核能系统项目战略合作框架协议----中国科学院". Archived from the original on 8 July 2018. Retrieved 7 July 2018.
  66. ^ http://finance.eastmoney.com/news/1350,20180329850624284.html Archived 8 July 2018 at the Wayback Machine 实验平台及配套项目拟选址于武威市民勤县红砂岗工业集聚区,南侧紧邻纬七路、东侧紧邻东环路。
  67. ^ "China signs agreement for nuclear heating demonstration project". Nuclear Engineering International. 14 March 2019. Retrieved 18 March 2019.
  68. ^ "CNNC completes design of district heating reactor". World Nuclear News. 7 September 2018. Archived from the original on 24 March 2019. Retrieved 18 March 2019.
  69. ^ "China faces civic protests over new nuclear power plants". msn.com. 17 February 2012. Archived from the original on 28 September 2013. Retrieved 26 February 2012.
  70. ^ Calum MacLeod (16 July 2013). "Protesters win environmental battle in China". USA TODAY. Archived from the original on 12 June 2015. Retrieved 6 September 2017.
  71. ^ Lucy Hornby (26 May 2014). "People power holds key to China's nuclear plans". Financial Times. Archived from the original on 29 May 2014. Retrieved 26 May 2014.

External links[]

Retrieved from ""