Kwinana Waste to Energy Plant

From Wikipedia, the free encyclopedia
Kwinana Waste to Energy Plant
Kwinana Waste to Energy Plant under construction, December 2020 02.jpg
The Kwinana Waste to Energy Plant under construction, December 2020
CountryAustralia
LocationKwinana Beach, Western Australia
Coordinates32°12′39″S 115°46′40″E / 32.21083°S 115.77778°E / -32.21083; 115.77778Coordinates: 32°12′39″S 115°46′40″E / 32.21083°S 115.77778°E / -32.21083; 115.77778
StatusUnder construction
Construction beganOctober 2018
Commission dateLate 2021 (planned)
Construction costA$668 million
Owner(s)Avertas Energy
Operator(s)Veolia
Employees60
Thermal power station
Primary fuelWaste
Power generation
Nameplate capacity36 MW
External links
Websiteavertas.com.au

The Kwinana Waste to Energy Plant is a waste-to-energy power station under construction in Kwinana Beach, Western Australia. Once completed, the facility is scheduled to process in excess of 400,000 tonnes (880 million pounds) of waste and will produce 36 MW of power.

Background[]

At the time of project approval, Australia generated 23 million tonnes of waste to landfill every year, with the state of Western Australia having the lowest waste recovery and highest waste generation rate per capita in the country. The geography of Perth, situated on a sandy coastal plain and relying heavily on groundwater as a source of potable water, meant new landfill sites were unlikely to be approved in the metropolitan region and existing ones were nearing capacity.[1] As a consequence, the Government of Western Australia encouraged local councils to end their dependency on landfills by the year 2020 as the practice was not sustainable.[2]

As of the time of approval, the Kwinana plant was scheduled to take up 25 percent of Perth's post-recycling waste that would otherwise be destined for landfill,[3] 400,000 tonnes (880 million pounds) of domestic, commercial and industrial waste.[2]

Overview[]

At the start of construction in October 2018, the Kwinana Waste to Energy Plant was the first large waste-to-energy facility to be constructed in Australia. The facility is intended to take waste otherwise destined for landfill from the Cities of Armadale, Canning, Gosnells, Kwinana, Mandurah and South Perth, as well as the Shires of Murray and Serpentine-Jarrahdale.[2] Approval of the Kwinana plant was followed by the approval of the East Rockingham Waste to Energy facility in January 2020, which is intended to take waste from the Cities of Cockburn, Belmont, Kalamunda and Swan as well as the Shire of Mundaring.[4] A third plant in western Australia, in Port Headland, will use a different low temperature gasification technology, something initially envisioned for the East Rockingham facility as well.[2]

Construction of the facility will employ 800 people and cost A$668 million, while operation, carried out by Veolia, will employ 60. The construction of the facility, carried out by Acciona Construction, received A$23 million in federal funding from the Australian Renewable Energy Agency while a further $90 million in funding were provided by the Clean Energy Finance Corporation.[2]

Power generation at Kwinana will be achieved through thermal grate technology, whereby the burning of waste will be used to heat steam.[2] The waste created in the process will be reused in a brick making plant which will be located at the site.[5]

The plant is owned by Avertas Energy, which is jointly owned by Macquarie Capital and .[6]

References[]

  1. ^ "East Rockingham Waste to Energy". arena.gov.au. Australian Renewable Energy Agency. Retrieved 28 August 2021.
  2. ^ a b c d e f Young, Emma (18 October 2018). "Perth glimpses end of landfill age as Kwinana waste plant build begins". The Sydney Morning Herald. Retrieved 28 August 2021.
  3. ^ "Kwinana Waste to Energy Project". arena.gov.au. Australian Renewable Energy Agency. Retrieved 28 August 2021.
  4. ^ Young, Emma (23 January 2020). "Perth closing in on landfill-free future as global renewables giant buys into waste-to-energy". The Sydney Morning Herald. Retrieved 28 August 2021.
  5. ^ "Kwinana Waste to Energy Project". NS Energy. Retrieved 28 August 2021.
  6. ^ "Avertas Energy - About us". avertas.com.au. Avertas Energy. Retrieved 28 August 2021.

External links[]

Retrieved from ""