Line 5 Eglinton

From Wikipedia, the free encyclopedia

Line 5 Eglinton
TTC - Line 5.svg
Overview
StatusUnder construction
OwnerMetrolinx
LocaleToronto, Ontario, Canada
TerminiMount Dennis
Kennedy
Stations25
Service
TypeLight rail
SystemToronto subway
Operator(s)Toronto Transit Commission[1]
Depot(s)Eglinton Maintenance and Storage Facility
Rolling stockFlexity Freedom
History
Planned opening2022[2]
Technical
Line length19 km (12 mi)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC overhead catenary[3]
Operating speed80 km/h (50 mph)
SignallingBombardier Cityflo 650 CBTC[4]
Route map

Legend
Planned extension west
Mount Dennis
UP Express logo.svg GO Transit logo.svg GO Kitchener logo.svg
Black Creek Drive
Keelesdale
Caledonia
GO Transit logo.svg GO Barrie logo.svg
Fairbank
Oakwood
Cedarvale (Eglinton West)
TTC - Line 1 - Yonge-University-Spadina line.svg
Forest Hill
Chaplin
Avenue
Eglinton
TTC - Line 1 - Yonge-University-Spadina line.svg
Mount Pleasant
Leaside
Laird
West Don River
Sunnybrook Park
Canadian Pacific Railway
Science Centre
Aga Khan Park & Museum
Don Valley Parkway
Wynford
East Don River
Sloane
O'Connor
Pharmacy
Hakimi Lebovic
Golden Mile
Birchmount
Ionview
Kennedy
TTC - Line 2 - Bloor-Danforth line.svg TTC - Line 3 - Scarborough RT line.svg
GO Transit logo.svg GO Stouffville logo.svg
Potential extension east

Line 5 Eglinton, also known as the Eglinton Crosstown or the Crosstown, is a light rail line that is under construction in Toronto, Ontario, Canada. Owned by Metrolinx and operated by the Toronto Transit Commission (TTC), the line will be part of the Toronto subway system as its fifth route. The first phase of the 19-kilometre (12 mi) line will include 25 stops along Eglinton Avenue, from Mount Dennis station underground to Laird station, after which it will run predominantly at-grade within the street's median to Kennedy station, where it will connect underground with Line 2 Bloor–Danforth and Line 3 Scarborough.[3]

The line was conceived in 2007 during the administration of Toronto mayor David Miller as part of Transit City, a large-scale transit expansion plan. Construction of the first phase of the line began in 2011 and was originally expected to be completed in 2020;[5] it has been delayed more than once, and as of October 2020, Metrolinx and Crosslinx (the construction consortium) have not agreed on a specific opening date.[2] The estimated cost of the project in late 2019 was $12.58 billion.[6]

Future extensions towards Toronto Pearson International Airport in the west and the University of Toronto Scarborough[7] in the east were approved by Toronto City Council in 2016,[8] Currently, assessment and pre-construction of the westward extension to Renforth Drive is being progressed by Metrolinx.[9]

History[]

Original concept[]

Line 5 Eglinton was originally conceived as the Eglinton Crosstown LRT, a partially underground light rail line, announced in 2007 by Toronto mayor David Miller and TTC chair Adam Giambrone. It was part of the Transit City plan, which included the implementation of six other light rail lines across Toronto. The original version of the line would have run from Pearson Airport along Silver Dart Drive to Convair Drive. The line would have then turned southwest to a bridge over Highway 401 to reach Commerce Boulevard on the other side, where it would run south to reach Eglinton Avenue and the east end of the Mississauga Transitway. The rest of the line would run east along Eglinton Avenue, including a portion along which the proposed Eglinton West subway line would have been built. The line would then traverse the city, connecting with Line 1 Yonge–University, Line 2 Bloor–Danforth, and Line 3 Scarborough.

There were 43 stops planned for the Eglinton Crosstown LRT, 13 of which would be underground.[10] Surface stops would be spaced on average 500 metres (550 yd) apart and the underground stations would be 850 m (930 yd) apart on average, as constructing numerous underground stops would be costly. The average speed would be 28 kilometres per hour (17 mph),[11][12] compared with the existing bus routes along Eglinton that have an average speed of 16 to 18 km/h (9.9 to 11.2 mph).[13] The line would terminate at Kennedy station to the east in Scarborough where it would meet Line 2 Bloor–Danforth, the proposed Scarborough Malvern LRT and the Stouffville GO train line. The expected cost was CA$4.6 billion.[14] As a result of provincial funding cuts, construction of the line was divided into two phases: phase one would end at Jane Street, and phase two would terminate as had been planned at Pearson Airport.[15]

Rob Ford–era redesigns[]

Miller's successor, Rob Ford, announced the cancellation of Transit City on December 1, 2010, the day he took office.[16] He proposed an alternative titled the "Eglinton–Scarborough Crosstown line", which put the 19-kilometre (12 mi) line along Eglinton Avenue completely underground. The line would have then followed the route of Line 3 Scarborough, thus forming a single line continuously from Black Creek Drive to McCowan. The cost would almost double to $8.2 billion and, compared to the original plan, 18 fewer stops were planned, including the elimination of the connection to Pearson Airport. Most of the additional cost would have come from putting 12 additional stations underground and for converting the Scarborough RT.

On February 8, 2012, in a special meeting, Toronto City Council, led by Karen Stintz, voted 25–18 to override Mayor Ford's modifications to the project.[17] The vote reinstated the original proposal to only construct the portion between Laird Drive and Keele Street underground while the remainder of the line is built along the surface.[17] On November 30, 2012, the environmental assessment was revised, such that the east tunnel portal location would be moved from east of Brentcliffe to east of Don Mills;[18] however, this was reversed in May 2013 after receiving community feedback.[19] In January 2013, city councillors from Scarborough put forward an alternative plan to proceed with the construction of the Eglinton Avenue portion of the line as planned but to exclude the Scarborough RT from the line. In July 2013, plans for an "Eglinton-Scarborough Crosstown" line were abandoned, thereby reverting the entire line back to the plan that had been conceived under Transit City.[20][21]

Construction and implementation[]

Promotional logo of the construction project. Note the use of the Toronto Subway typeface.

Crosslinx[]

Crosslinx Transit Solutions, a consortium of more than 26 companies, was awarded the contract to design, build and finance the Eglinton Crosstown line and to maintain it for 30 years. The contract, which excludes boring the tunnels, is for completing all other remaining work, including the stations and the finishing work within the tunnels. Some of the members of the consortium are SNC-Lavalin, Aecon, EllisDon, ACS Infrastructure Canada, Dragados, IBI Group and Scotiabank. The contract defines a public–private partnership.[22][23]

The 30-year contract to build and maintain the line will total $9.1 billion. Capital costs will be $5.3 billion, with each of the 15 underground stations costing $80–$100 million to build and the ten street-level stops $3–$5 million each. The remainder will be for financing, lifecycle and maintenance costs.[22]

In July 2015, the Crosslinx Transit Solutions Maintenance General Partnership consortium awarded Bombardier Transportation a 30-year contract to maintain Line 5's light-rail vehicles. The contract was worth $403 million.[24] Bombardier will also maintain wayside systems (track and overhead catenary) for Line 5.[25]

Timeline[]

2010[]

On July 28, 2010, Metrolinx ordered four tunnel boring machines (TBMs) from Caterpillar at a cost of $54 million.[26] Each TBM is 10 metres (33 ft) long, 6.5 metres (21 ft) in diameter and weighs 400 tonnes (390 long tons; 440 short tons). They bore 10 metres (33 ft) per day, 16 to 20 metres (52 to 66 ft) below the surface.[27] The TBMs were named Dennis, Lea, Humber, and Don. The names were chosen by Jason Paris, a moderator of the UrbanToronto blog and web forums. Dennis is named after Mount Dennis, Lea is named after Leaside, Humber is named after the Humber River, and Don is named after the Don River. The names Dennis and Lea combined allude to the poet Dennis Lee.[28][29] By the time all four machines reach Yonge Street, enough dirt will have been removed to fill the Air Canada Centre (renamed Scotiabank Arena in 2018) to the height of the CN Tower.[30]

2011[]

In October 2011, the first part of tunnel construction began with the construction of a launch shaft for tunnel boring machines at Black Creek Drive.[31]

On November 9, 2011, in Keelesdale Park, Mayor Rob Ford and Premier Dalton McGuinty officially broke ground on the new project.[32]

2012[]

In May 2012, TTC staff released a report saying that completion of the Eglinton Crosstown was unlikely by 2020 and that a more realistic in-service date would be 2022–2023. The main reason given was that the project management had been transferred from the TTC to Infrastructure Ontario which uses the Alternative Finance and Procurement strategy. That strategy would use a private contractor to complete the project, effectively requiring that contractor to redo all design work already completed by the TTC.[33] The TTC also warned that Metrolinx's aggressive timeline would lead to severe construction-related disruptions to communities and traffic because large stretches of the Eglinton Avenue would have to be torn up concurrently to meet deadlines.[34]

2013[]

In January 2013, Infrastructure Ontario issued a request for qualifications to shortlist companies to construct the line. A request for proposal was expected in mid-2013.[35]

On February 22, 2013, TBMs Dennis and Lea arrived in Keelesdale Park.[36]

In June 2013, the TBMs Dennis and Lea began tunnelling on the line. Traffic on Eglinton Avenue near Keele Street was reduced to one lane in each direction.[37]

On November 12, 2013, Metrolinx awarded a contract to construct the eastern portion of the Crosstown to a joint venture between Aecon Group and ACS Dragados Canada to construct the eastern portion of the line between Yonge Street and Laird Drive.[38]

2014[]

In March 2014, work began to clear utilities and trees on the south side of Eglinton Avenue just east of Brentcliffe Road in order to set up the eastern launch shaft. For two and a half years, traffic around the excavation site will be reduced from two to one lane in each direction. West of the site, more lane restrictions would go into effect to construct head walls (below-ground walls that form the ends of each subway station) at the future Laird, Bayview and Mt. Pleasant stations. There will also be lane restrictions for two years near Hanna Road to build an emergency exit near Leaside High School.[30]

By April 2014, the TBMs had arrived at Caledonia station.[39] In April 2014, The Globe and Mail reported that the two western tunnel boring machines were excavating "approximately 1,000 cubic yards of spoil", per day.[40]

For the year prior to May 2014, the two TBMs Dennis and Lea had been excavating and installing concrete tunnel liners at a rate of approximately 10 metres (33 ft) per day.[41] The tunnels are lined with precast concrete liner segments. Six 2.5-tonne (2.8-ton) segments form each ring.

In early December 2014, Dennis and Lea arrived at Eglinton West station.[42] Dennis stopped to allow Lea to catch up, so that they would arrive at Eglinton West station at the same time.

2015[]

On the weekend of April 18–19, 2015, the boring machines, Dennis and Lea, were lifted out of a shaft west of Allen Road and moved about 100 metres (330 ft) to a shaft just east of Allen Road.[43]

In April 2015, merchants along Eglinton Avenue West were complaining of lost revenue (up to a 35% dip in sales), because construction was discouraging customers with snarled traffic, limited parking options, reduced foot traffic and dusty sidewalks.[44]

By September 2015, the TBMs Don and Humber arrived for assembly in the shaft at Brentcliffe Road before starting to drill the 3.25-kilometre (2.02 mi) section west to Yonge Street.[34][30]

On September 24, 2015, Transportation Minister Steven Del Duca issued a statement saying the Crosstown would not operate until September 2021, in order "to mitigate disruption to the local community and infrastructure as much as possible." The earlier plan had been to open in 2020 with tunnelling and station construction to start in 2012.[45] Infrastructure Ontario has awarded the Crosstown construction contract to Crosslinx, a consortium led by SNC Lavalin. It will take about four years to build the stations, 15 of which will be underground.[34]

On September 29, 2015, TBM Don started to bore the north tunnel from the Brentcliffe Road launching site westwards towards Yonge Street. TBM Humber will start boring the south tunnel approximately one month later.[46]

On November 3, 2015, Del Duca announced that the contract awarded to Crosslinx Transit Solutions to complete the Crosstown and maintain it for 30 years will cost $2 billion less than originally estimated.[22]

2016[]

Future site of Forest Hill station; the House of Chan façade unintentionally collapsed, injuring several passersby.

On March 10, 2016, a ground-breaking ceremony was held at the site of Keelesdale station, the first station to be started for construction along the Eglinton Crosstown line.[47]

In February 2016, work began on the extraction shaft for TBMs Humber and Don, which are digging the eastern segment of the line.[48] However, the hole in the street there will be much smaller than the one near Leslie Street.[30]

On April 18, 2016, at the location of the future Forest Hill station, the façade of the former House of Chan restaurant and the scaffolding that was holding it up collapsed, injuring seven people.[49]

On May 10, TBMs Dennis and Lea, which had been boring the western segment of the line, completed their work by reaching Yonge Street.[50] Dennis and Lea bored 6.4 kilometres (4.0 mi), installing 25,647 precast concrete tunnel segments to construct the 4,279 rings to line the twin tunnels.[27]

On August 17, TBMs Don and Humber, which had been boring the eastern segment of the line, completed their work by reaching Yonge Street. Don and Humber bored 3.3 kilometres (2.1 mi), installing 26,178 precast concrete tunnel segments to construct the 4,363 rings to line the twin tunnels.[27]

On September 1, Bombardier Transportation, which is producing cars for the line, failed to meet the delivery deadline for the pilot vehicle.[51][52] As a result, Metrolinx filed notice to terminate the contract with Bombardier.

On November 3, 2016, Metrolinx filed a "notice of intention" to cancel its contract with Bombardier for the Crosstown's rolling stock.[51][52][53]

2017[]

Cutting face of TBM Don being extracted

On February 10, 2017, Bombardier filed an injunction, seeking to compel Metrolinx to stick with their contract.[52][53][54] Metrolinx responded that Bombardier did deliver a prototype for testing, as required by the contract. However, Metrolinx claimed that the prototype was so incomplete that it would not power up.[55]

Between March 13 and 17, the TBMs Don and Humber were removed in pieces from the extraction shaft on Eglinton Avenue just east of Yonge Street.[56][57]

In July 2017, construction crews began preparation for constructing the eastern at-grade portion of the line[58] by removing the median in the roadway.[59]

On August 9, the first piece of track, a turnout, was installed at the Eglinton Maintenance and Storage Facility (EMSF) in Mount Dennis. The facility was scheduled for completion in late 2018,[59] but construction is now expected to be complete in early 2019.

In December, Toronto City Council approved 10 stop locations for a possible future extension of Line 5 Eglinton west to Peel Region[60] dubbed the "Eglinton West LRT". The 2017 Council-approved locations are Silver Dart, Convair, Renforth, Martin Grove, Widdicombe Hill, Kipling, Wincott, Islington, Royal York, Mulham, Scarlett, Jane, and Mt Dennis.[61]

2018[]

In July 2018, Crosslinx, the construction company building the LRT line, sued Metrolinx, claiming that utility work prior to construction exceeded timelines Metrolinx had specified. Crosslinx sought to extend the 2021 deadline for the opening of the transit line by one year.[62][63] In August 2018, Metrolinx submitted a filing with the Ontario Superior Court of Justice to dismiss the lawsuit. This was based on an agreement with Crosslinx to resolve disputes only after construction has been completed.[64] The lawsuit was settled by Metrolinx in September 2018 under undisclosed terms.[65] It was revealed by the Auditor General of Ontario that one of the terms included an additional $237 million to be paid to Crosslinx for an assurance to meet Metrolinx's 2021 deadline.[66][63]

In October 2018, the Eglinton Maintenance and Storage Facility was substantially complete.[67]

By December 2018, 10 kilometres (6.2 mi) of track had been installed. The line requires 47 kilometres (29 mi) of track in total.[67]

2019[]

On January 8, 2019, Bombardier delivered the first Flexity Freedom vehicle to the Eglinton Maintenance and Storage Facility, which, according to Metrolinx, was "substantially complete and ready to receive the vehicles" by this date.[68]

Laying rails at the O'Connor stop

In January 2019, the first concrete pour for the surface section occurred at the location of the future O'Connor stop at Eglinton Square. Before being encased in concrete, conduit pipes were laid to support communications and power cables for the Crosstown's stations and stops.[69]

From July 1 to late August 2019, Leslie Street at Eglinton Avenue was closed for the installation of tracks and infrastructure at the intersection. During this time, the TTC 51 Leslie bus route turned back at Leslie and Eglinton at a temporary bus loop. The temporary closure allowed work to be completed in one section instead of two, thus eliminating joints in the road and track. This provided a higher quality result, reducing future maintenance. The closure also reduced the construction period at the intersection from six months to two.[70]

In November 2019, Crosslinx informed Metrolinx that it expected the line not to be completed before May 6, 2022, and that the construction costs would total $12.58 billion, an increase of $330 million over previous estimates. The main problems reported were defective caissons (underground watertight compartments) built in the 1950s at Eglinton station, groundwater at the Avenue station site and construction difficulties at the CP Rail bridge adjacent to the Mount Dennis station.[71]

On December 14, 2019, testing began between the Eglinton Maintenance and Storage Facility (EMSF) and the Western portal using Flexity Freedom vehicles, initially testing track clearances at slow speed. On December 17, Crosslinx conducted an inaugural run with staff and guests from the handover platform at the EMSF to the elevated guideway over Black Creek Drive. At that time, overhead wire had been installed between the EMSF to just short of the Keelesdale platform.[72][73]

2020[]

As of the end of January 2020, Crosslinx has laid 50 percent of the line's track.[74]

In February 2020, Metrolinx announced that the line would not open until "well into 2022", a delay from the previous target of September 2021.[75] This is despite Metrolinx reaching a costly settlement with Crosslinx last year, paying the consortium $237 million to commit for a September 2021 deadline.[71] Metrolinx cited reasons for the delay: Crosslinx had started work nine months late, and had been slow to finalize some aspects of the design. Also, at Eglinton station, pipes embedded in concrete built in the 1950s were discovered in a position that impeded excavation for the Crosstown under Line 1 Yonge–University.[76]

In early March 2020, the provincial government announced it would provide $3 million in aid to local merchants negatively affected by Crosstown construction near their businesses. The Ministry of Transportation and Metrolinx would also look into an earlier, partial opening of the Crosstown line.[77]

By March 2020, Crosslinx had installed the first passenger-waiting shelter on the surface section of the line at the Pharmacy stop. The shelters are pre-fabricated and hoisted into position on the LRT boarding platform.[78]

On March 9, 2020, Crosslinx began work to extract tunnel boring machines Dennis and Lea at Duplex Avenue, one block west of Yonge Street.[78]

On May 4, 2020, Metrolinx reported the first test trip by a light rail vehicle (LRV) in a Line 5 tunnel. The trip was from the Eglinton Maintenance and Storage Facility to just short of the platform at the underground Keelesdale station. The test run was to check clearances, trackwork, and overhead power and communications; it involved several movements in and out of the tunnel at speeds of up to 25 km/h (16 mph).[79]

Science Centre station under construction in June 2020

On October 1, 2020, Crosslinx proposed partially opening Line 5 on February 28, 2022, with the Line 5 portion of Eglinton station not opening until May 2022. However, the direct connection for riders transferring between Lines 1 and 5 at Eglinton station would not be completed until September 2022; until then, passengers who wished to transfer would need to exit to the surface and descend by the entrance next door. Crosslinx says defective infrastructure from 1954 at Eglinton station, difficult hydrogeological conditions and the COVID-19 pandemic have hindered the project. Moody's Investors Service also reported delays at Kennedy, Forest Hill, Mount Pleasant and Cedarvale stations.[2] On October 8, Crosslinx filed a lawsuit against Metrolinx and Infrastructure Ontario, claiming $134 million in unexpected costs due to the pandemic. Metrolinx countered that Crosslinx had been falling behind schedule before the pandemic.[80]

In early December 2020, the first pieces of artwork were being installed at Science Centre and Mount Dennis stations.[81]

2021[]

By early April 2021, tracks had been laid on the surface into the Brentcliffe Portal just east of Brentcliffe Road. This location will be the transition between underground and surface running on Line 5 between Laird station and the Sunnybrook Park stop.[82] In addition, as of April 2021, 85 percent of track had been installed along the entire line.[83]

In April 2021, the last concrete "invert pour" on the line was completed at Eglinton station. The invert pour created the station's base level slab (also called an "invert"), which lies over the "mudslab", a concrete layer that sits on top of the earth.[84]

On May 3, 2021, Crosslinx energized the overhead catenary system between Laird and Kennedy stations for testing purposes. Traction power substations along the surface route supply electricity to the catenary; there will be 15 such substations.[85][86]

On May 17, 2021, Crosslinx won a case in Ontario Superior Court against Metrolinx and Infrastructure Ontario to allow compensation for the extra construction costs and project delays due to the COVID-19 pandemic. The court decision allowed Crosslinx to negotiate with the two provincial agencies for financial compensation and a later completion date. (The completion per the contract was to have been September 2021, later revised to 2022 by Metrolinx.) Crosslinx sought approximately $134 million in compensation for extra safety measures, absenteeism and supply-chain problems due to the COVID-19 pandemic.[87]

Between May 25 and June 2, 2021, six LRVs were delivered by truck from the Eglinton Maintenance and Storage Facility to Eglinton Avenue East and Rosemount Drive along the eastern end of the line. After unloading, each LRV (powered by the catenary) ran westwards to be stored within the Brentcliffe portal. (Until this point, only the section west from Caledonia station had been operational for testing trains.) Clearance and static testing was scheduled to take place in June with LRVs moving at walking speed.[88][89][90]

Effective June 20, 2021, the TTC renumbered the Avenue Rd bus route from 5 to 13 in order to free up the route number 5 for the Eglinton line.[91]

By July 2021, 93 percent of the rail had been installed along the line. At Chaplin station, track work was being completed. However, at neighbouring Avenue station, concrete was still being poured in the tunnel at one end of the station box.[92]

Until late August 2021, Crosslinx had tested the interaction between the vehicles and communications and signal systems east of the Brentcliffe portal. Vehicles ran at slow speeds. On August 24, 2021, Crosslinx started a new phase of testing east of the Brentcliffe portal involving coupled vehicles, increased speed, braking and concurrent vehicle operation.[93]

Unique station names[]

In the planning stages for Line 5 Eglinton, many stations and stops were given working names identical to names of pre-existing stations within the Toronto subway system. On November 23, 2015, a report to the TTC Board recommended giving a unique name to each station within the subway system (including Line 5 Eglinton). Thus, several stations with non-unique working names were renamed, even those which will be comparatively simple on-street surface stops (new name in parentheses): Keele (Keelesdale), Dufferin (Fairbank), Bathurst (Forest Hill), Bayview (Leaside), Leslie (Sunnybrook Park), Don Mills (Science Centre), Victoria Park (O'Connor) and Warden (Golden Mile). Despite its unique name, Eglinton West station will be renamed Cedarvale to avoid confusion with Eglinton station.[94][95][96]

Route[]

Right-of-way[]

An example of green track (along an LRT line in Linz, Austria)

Line 5 Eglinton will run underground for 10 km (6.2 mi) from Mount Dennis to just east of Brentcliffe Road before rising to the surface to continue another 9 km (5.6 mi) to end at Kennedy station.[97] A short portion of the line across the Black Creek valley will be elevated, between Mount Dennis and Keelesdale stations. The right-of-way will have 46.6 kilometres (29.0 mi) of track, including six double crossovers, five mono-directional crossovers and three pocket tracks.[83]

Parts of the surface route will use "green track", that is, track with vegetation growing beside and between the rails. Green track will be used between the Brentcliffe Road tunnel portal (western end of the surface route) and Birchmount Road (Birchmount stop in the east end) with paved gaps at intersections, surface stops and the underground Science Centre station.[98] Each section of green track will have irrigation chambers, a water supply, and an energy source for the irrigation system. Green track will dampen train sounds, absorb runoff water, reduce ambient temperatures in summer and minimize the spread of dust.[99]

Surface stops will be located at accessible, signalized intersections, and will have a transparent design for passenger security. Platforms will have a sign post bearing the stop's name, a barrier along the road to protect waiting passengers, Presto machines, screens displaying the next vehicle arrival time, platform illumination and covered waiting shelters with benches and a passenger assistance intercom. The platforms will be designed for level boarding.[100][101]

Stations and stops[]

The Toronto subway system map as it would appear after the completion of Line 5 Eglinton (orange) and including the proposed Scarborough Subway Extension
Station/Stop[102] Type Notes
Mount Dennis Surface Direct connection to GO Transit logo.svg GO Kitchener logo.svg Kitchener line, UP Express logo.svg Union Pearson Express
Keelesdale Underground Located at Keele Street
Caledonia Underground Located west of Caledonia Road; connection to GO Transit logo.svg GO Barrie logo.svg Barrie line
Fairbank Underground Located at Dufferin Street
Oakwood Underground Located at Oakwood Avenue
Cedarvale (Eglinton West) Underground Connection to TTC - Line 1 - Yonge-University-Spadina line.svg Yonge–University at the current Eglinton West station, to be renamed Cedarvale when Line 5 opens[95]
Forest Hill Underground Located at Bathurst Street
Chaplin Underground Located at Chaplin Crescent
Avenue Underground Located at Avenue Road
Eglinton Underground Connection to TTC - Line 1 - Yonge-University-Spadina line.svg Yonge–University
Mount Pleasant Underground Located at Mount Pleasant Road
Leaside Underground Located at Bayview Avenue
Laird Underground Located at Laird Drive
Sunnybrook Park On-street Located at Leslie Street
Science Centre Underground Located at Don Mills Road
Aga Khan Park & Museum On-street Located on the west side of Don Valley Parkway
Wynford On-street Located at Wynford Drive
Sloane On-street Located at Bermondsey Road and Sloane Avenue
O'Connor On-street Located at Victoria Park Avenue
Pharmacy On-street Located at Pharmacy Avenue
Hakimi Lebovic On-street Located at Lebovic Avenue and Hakimi Avenue
Golden Mile On-street Located at Warden Avenue
Birchmount On-street Located at Birchmount Road
Ionview On-street Located at Ionview Road
Kennedy Underground Connection to TTC - Line 2 - Bloor-Danforth line.svg Bloor–Danforth, TTC - Line 3 - Scarborough RT line.svg Scarborough and GO Transit logo.svg GO Stouffville logo.svg Kennedy GO Station for Stouffville line

Public art[]

As part of the Crosstown project, six stations along Line 5 Eglinton – Mount Dennis, Caledonia, Cedarvale (Eglinton West), Eglinton, Science Centre and Kennedy – will feature eight artworks. These stations were chosen because they are all interchange stations expected to host higher passenger volumes.[103]

All artworks will be integrated into station design and construction rather than being stand-alone pieces. Because of the controversy over the artwork LightSpell at Pioneer Village station, in which commuters can display messages that can violate the 2009 revision of TTC's By-Law No. 1, none of the Line 5 artworks will be interactive. The art budget is about $10 million. About $1 million of that budget will be used for digital art to appear on screens at stations along the line.[103]

Operations[]

Operating characteristics of the line include:

  • There will be three types of train control on the line. Automatic Train Control (ATC) without a driver onboard is used within the Eglinton Maintenance and Storage Facility. In the underground segment between Mount Dennis and Laird stations, an on-board driver will operate train doors and push a button to depart a station, with ATC controlling the train until the next station. Between Laird and Kennedy stations, the driver controls all train functions.[104][105]
  • On the surface, the line will have dedicated right-of-way transit lanes separate from regular traffic[11] and usage of priority signalling at intersections to ensure certainty in travel times – unlike the streetcars in downtown Toronto or on St. Clair Avenue.[101]
  • Light rail vehicles and subways can both travel as fast as 80 kilometres per hour (50 mph). However, actual speed is determined by the spacing of the stops and the dwell times at stops. Line 5 vehicles will have an average speed of 28 kilometres per hour (17 mph). As a comparison, the average speed of the subway Line 2 Bloor–Danforth is 32 kilometres per hour (20 mph).[106]
  • The projected ridership of the line is 5,400 passengers per hour in the peak direction by 2031, but the capacity of the vehicles is 15,000 passengers per hour per direction.[11]
  • The surface section of the line will run on a proof-of-payment system but the underground stations will have regular fare gates and staff; Presto cards will be available for use across the entire line.[107]
  • Metrolinx requires 76 Flexity Freedom LRVs to operate the line.[108]
  • Annual operating and maintenance costs are estimated to be $80 million upon opening of the line. However, fare revenue and the costs saved by eliminating Eglinton bus service would result in a net annual cost of $39 million.[109]
  • There will a total of 12 turnbacks along the line to reverse LRT trains—seven at underground stations and five on the surface section. Avenue Station and Laird Station will be turnback stations that also have a storage track that trains can enter and exit in either direction. The storage tracks will accommodate a train in case of an emergency or change in service as well as allowing for a change of direction.[58]

Rolling stock[]

Front view of Bombardier's Flexity Freedom vehicles at the Eglinton Maintenance and Storage Facility during Doors Open 2019

As the line is owned by the province of Ontario, Metrolinx chose the Bombardier Flexity Freedom light rail vehicle, which uses standard gauge rather than the TTC's own slightly larger gauge. Metrolinx wanted to avoid using a custom gauge in order to secure a better price from the manufacturer and to create a standard for other light-rail projects in the province.[110] The vehicles have an operator's cab at only one end of the vehicle; thus, the LRVs must be run in back-to-back coupled pairs.[111] Trains will use automatic train control within the tunnelled portion of the line.[104] Like the Flexity Outlook vehicles Bombardier built for the TTC's streetcar system, initial work building the chassis was performed at Bombardier's Mexican plant in Ciudad Sahagún, Hidalgo, with final assembly at Bombardier's plant in Thunder Bay.[112]

In 2010, Metrolinx had ordered 182 Flexity Freedom vehicles not only for Line 5 but for other light-rail projects in Ontario. The first two deliveries were expected in the second quarter of 2015 but had not arrived by May 2017. After being unsure if a timely delivery of the Bombardier vehicle order could be relied upon, Metrolinx reduced the Bombardier order from 182 to 76 to supply just Line 5 and made a contingency order with Alstom for 61 Citadis Spirit vehicles, of which 44 would be for Line 5 and the remaining 17 for Line 6 Finch West.[113] If the Flexity order did arrive after all, surplus Alstom vehicles would be used on other Metrolinx projects (most likely the Hurontario LRT in Mississauga in Peel Region).[114][115] On October 30, 2018, Bombardier announced that the first Flexity Freedom vehicle had completed its in-house testing and would be delivered for on-site testing in Toronto in November 2018.[116] However, the first vehicle arrived late, on January 8, 2019.[68] As a commissioning test, each vehicle must travel 600 km (370 mi) before accepting passengers.[73]

Eglinton Maintenance and Storage Facility[]

Bombardier Flexity Freedom LRV on the car-wash track at the EMSF

A maintenance and storage facility is required for Line 5, given the new technology employed, track gauge and the number of vehicles ordered. The Eglinton Maintenance and Storage Facility will have storage for 162 Flexity Freedom LRT vehicles and have extensive maintenance facilities to keep them running smoothly.[117] The facility is being built near the line's western terminus at Mount Dennis station on lands formerly occupied by Kodak's Toronto campus[118][119][120] and near the Mount Dennis bus garage.

Extensions[]

Under Mayor John Tory, Toronto City Council approved two extensions for Line 5 Eglinton, to the east and to the west, on March 31, 2016.[8] As of 2020, the Eglinton West LRT is an active project,[121] but the Eglinton East LRT is not.[122]

Eglinton West LRT[]

hide
Eglinton West LRT
Legend
Airport extension
Link Train
Pearson Terminal 1
Link Train Toronto Pearson International Airport UP Express logo.svg
Union Pearson Express
Silver Dart
Convair
Renforth
MiWay logo Aug2010.pngMississauga TransitwayGO bus symbol.svg
Highway 427
Mimico Creek
Martin Grove
Kipling
Islington
Royal York
Scarlett
Humber River
Jane
Mount Dennis
UP Express logo.svg GO Transit logo.svg GO Kitchener logo.svg

Surface station plan (2007–2019)[]

In a later phase, Metrolinx had planned for the Eglinton Crosstown to be extended westwards from Mount Dennis along Eglinton Avenue West to Toronto Pearson International Airport. However, during the 2014 Toronto mayoral election, John Tory proposed SmartTrack, which would have included a heavy rail transit line established along this section of Eglinton Avenue.[123][124] In 2016, the City of Toronto released a feasibility report that found this proposal would have significant capital costs ranging from $3.6 billion to $7.7 billion. In comparison, extending the Eglinton Crosstown as approved would cost $1.3 billion. It was also found that a light rail transit line would attract higher ridership than a heavy rail line.[125]

The City of Toronto's chief planner recommended the extension of the Eglinton Crosstown line (referred to as Crosstown West) to Pearson Airport in lieu of establishing SmartTrack on Eglinton Avenue, based upon negative community impacts, higher costs, and lower projected ridership associated with a heavy rail corridor.[125] On January 19, 2016, Tory agreed with the analysis and supported Metrolinx's original plan of extending the Crosstown.[126] Tory included the Crosstown West as a light-rail component of his SmartTrack plan.[127]

In June 2016, the estimated completion date was 2023.[128] The estimated cost to build the Eglinton West LRT was $2.47 billion of which the City of Toronto would contribute $1.18 billion, the federal government would contribute $822.9 million, and the City of Mississauga and the Greater Toronto Airports Authority (GTAA) would be asked to contribute $470 million for the portion of the line in Mississauga. Approvals for the financing were still to be secured as of November 2, 2016.[129]

Public meetings for the extension, renamed the Eglinton West LRT, began November 13, 2017.[130][131]

The 2010 Environmental Assessment for Transit City originally considered an entirely at-grade light rail line running west from Weston Road and Mount Dennis station. However, by October 2017, the City was considering grade separation using fly-overs and fly-unders at six intersections: Martin Grove Road, Kipling Avenue, Islington Avenue, Royal York Road, Scarlett Road, and Jane Street, with surface running between stations.[132][133][134]

On November 21, 2017, City staff recommended just 10 stops along Eglinton West between Mount Dennis station and Renforth station on the Mississauga Transitway. The most recent recommendation dropped the stops at Rangoon, East Mall, and Russell / Eden Valley.[135][136]

At a City executive committee meeting on November 28, 2017, City staff recommended building the extension without any grade separation. City staff had concluded that a fully at-grade extension would provide better access for transit users and have fewer environmental impacts. Grade separation would have little improvement on traffic because the at-grade option would use signal coordination; however, grade separation would require fewer restrictions on left turns. There would be no difference in development potential with either option. However, because of feedback from the public and local politicians, Mayor John Tory recommended more study on grade separation.[134] A fully at-grade extension was estimated to cost $1.5 to $2.1 billion. Grade separation would add an extra $881.9 million to $1.32 billion to that cost.[134]

Grade-separated station plan (2019–present)[]

In April 2019, Ontario premier Doug Ford, the brother of former Toronto mayor Rob Ford, announced a plan for transit in the Greater Toronto Area. This included the planned extension of Line 5 Eglinton west to Pearson Airport with a section of the line built underground from Royal York to Martin Grove.[137] In February 2020, Metrolinx released an initial business case analysis of the project with four options, including three which were below-grade.[138] Metrolinx ultimately decided on a mostly grade-separated line with 7 stations (4 underground, 2 elevated, 1 at ground level).[121]

Building a mostly grade-separated extension is expected to cost $4.7 billion and would have 7 stations and an estimated 37,000 daily boardings. For comparison, a surface line would have cost $2.9 billion and have had 10 ground-level stations and an estimated 42,500 daily boardings. Travel time savings on an underground line would be double that for a surface line, but the reduction in stations would lead to a lower estimated ridership.[139] Doug Ford preferred underground construction.[140]

As of 2020, Metrolinx hoped to start work on the tunnel launch shaft in the second or third quarter of 2021, with tunnelling beginning in the second or third quarter of 2022. The launch shaft will be located adjacent to Renforth station while the extraction shaft will be located 500 metres (1,600 ft) west of Scarlett Road. The underground stations will be built using the cut and cover method. A tunnel-boring machine (TBM) will be used for tunnelling the 6 kilometres (3.7 mi) to Renforth.[141] The extension is expected to be completed between 2030 and 2031.[142]

Extension construction[]

In May 2021, the consortium West End Connectors was awarded the contract to design, build and finance the tunnels for the extension, permitting the consortium to set up the tunnel launch site at Renforth Drive and Commerce Boulevard. Construction between Martin Grove Road and Scarlett Road is expected to start in the second quarter of 2022. West End Connectors is a consortium of companies that includes Aecon Infrastructure Management, Dragados Canada, Ghella Canada, TYPSA, EXP Services, Dr. G. Sauer & Partners, Pedelta Canada, ACS Infrastructure Canada, Aecon Concessions, Scotiabank Capital and Ghella Investments & Partnerships.[143]

Extension description[]

The extension will run 9.2 kilometres (5.7 mi) from Weston Road to Renforth Drive in Mississauga serving seven new stations.[139] West of Mount Dennis, the line would emerge from a tunnel and become elevated for stops at Jane Street and Scarlett Road and in order to cross the Humber River. It would travel underground between Royal York Road and Martin Grove Road. The line would then come to the surface for a stop at Renforth station.[142]

Station[144] Type Notes
Renforth Surface Located on the north side of the Mississauga Transitway
Martin Grove Underground Located on north side of Eglinton Avenue at the northeast corner with Martin Grove Road
Kipling Underground Located under Eglinton Avenue on the west side of Kipling Avenue with an entrance at the northwest corner and an emergency exit at the west end of the platform
Islington Underground Located on north side of Eglinton Avenue at the northeast corner with Islington Avenue
Royal York Underground Located on north side of Eglinton Avenue at the northwest corner with Royal York Road
Scarlett Elevated Located on north side of Eglinton Avenue above Scarlett Road
Jane Elevated Located on north side of Eglinton Avenue above Jane Street

For turning back trains, there will be crossovers on the west side of Jane station and on the east side of Renforth station. When the line is extended further west to the airport, there will be an additional crossover on the west side of Renforth station. Both Jane and Renforth stations will have pocket tracks.[145]

Later expansion[]

A later phase of the extension would connect Renforth station with the Mississauga Transitway, then run north along Commerce Boulevard to an elevated bridge which would carry the line over Highway 401. The line would become elevated again for a stop at Convair Drive, serving the GTAA headquarters and the aircraft and airfield maintenance areas, then at-grade for a stop at Silver Dart Drive, serving some car rental facilities. The rest of the route to Pearson has not been finalized as of 2020, but the line is intended to terminate at the proposed Pearson Regional Transit Centre located north of Pearson Airport Terminals 1 and 3.[142]

Eglinton East LRT[]

To complement the Scarborough Subway Extension, the planned extension of Line 2 Bloor–Danforth to Scarborough Town Centre, the City of Toronto drafted a plan to extend Line 5 Eglinton farther east into Scarborough to terminate at the University of Toronto Scarborough campus.[146]

The 12-kilometre (7.5 mi) extension would connect with Eglinton GO Station and Guildwood GO Station and pass through "neighbourhood improvement areas" (often low-income areas) such as Eglinton East, Scarborough Junction, Morningside, Scarborough Village and West Hill.[147] The extension would add 18 new stops east of Kennedy station and serve an estimated 43,400 additional riders per day (a ridership similar to that of the Line 4 Sheppard subway).[148]

The east extension follows the alignment of the Scarborough Malvern LRT, which was proposed as part of Transit City.[149] In 2010, the Scarborough Malvern LRT was cancelled by Mayor Rob Ford, despite having been approved by Toronto City Council and the Government of Ontario in 2009.[150][151]

In early 2016, the plan for the Scarborough Malvern LRT was revived and rebranded as "Crosstown East"[147] before being renamed again to "Eglinton East" in 2017.[152] As of November 2017, the project was mostly unfunded, with the cost estimated at $1.6 billion to $1.7 billion, with an estimated completion date of 2023.[152][127]

At a November 2017 public meeting, City staff presented the possibility of extending the Eglinton East LRT by six stops to Malvern Town Centre. The Malvern extension would be 4.2 to 4.7 kilometres (2.6 to 2.9 mi) long.[152] The extension to Malvern Town Centre would have seven stops: at Pan Am Drive, Sheppard/Morningside, Brenyon Way, Murison Boulevard, Sheppard/Neilson, Wickson Trail, and Malvern Town Centre.[153]

In April 2019, Ontario premier Doug Ford announced a plan for Toronto rapid transit which included the Eglinton West LRT, the Scarborough Subway Extension, the Yonge North Extension and the Ontario Line. The Eglinton East LRT was noticeably not included and was left off the accompanying map.[122] As of October 2020, the City of Toronto and the TTC are in the process of implementing bus-only lanes from Kennedy station to the University of Toronto Scarborough campus via Eglinton Avenue, Kingston Road and Morningside Avenue as part of the RapidTO bus rapid transit scheme, which approximates the route of the Eglinton East LRT. The lanes are anticipated to be fully installed and operational by November. As well as "red carpet" bus lanes, bus stops are also being consolidated to approximately the same configuration and frequency of proposed LRT stations, with certain lower-order curbside stops – such as those at Huntington Avenue, Brimley Road, Oswego/Barbados Roads and Torrance Avenue – being removed entirely.[154]

In December 2020, the City of Toronto announced changes to the Eglinton East LRT proposal. The tunnel portal would be extended eastwards to Huntington Avenue due to changes in the Scarborough Subway Extension project, which involved modifying the depth of the tunnel as well as adding a third subway track for service improvements. A station at Midland Avenue was moved underground as a result. A new maintenance and storage facility north of UTSC was added to the plan as a result of the Sheppard East LRT cancellation. Originally, both the Eglinton East LRT and the Sheppard East LRT were to have shared a maintenance and storage facility at Conlins Road east of Sheppard and Morningside. The other aspects of the project remained the same, including a tunnel under Kingston Road and Morningside Avenue due to traffic congestion at the Kingston/Lawrence and Morningside area.[155]

As of February 2021, the estimated cost of the Eglinton East extension was $4.2 billion. Since the province had since agreed to fully fund the Scarborough Subway Extension, Mayor John Tory requested that the $1.2 billion the city had accumulated for that project be redirected to the Eglinton East line.[156]

See also[]

References[]

  1. ^ Consiglio, Alex (October 3, 2012). "TTC to operate city's new LRT lines". Toronto Star. Retrieved November 1, 2012.
  2. ^ Jump up to: a b c Spurr, Ben (October 1, 2020). "New report says the Eglinton Crosstown LRT could open five months late — and without its Eglinton stop". Toronto Star. Retrieved October 1, 2020.
  3. ^ Jump up to: a b "Eglinton LRT 2012 update" (PDF). Metrolinx. February 2012. Archived from the original (PDF) on February 13, 2013. Retrieved November 1, 2013.
  4. ^ "Bombardier's Rail Control Division Further Expands North American Presence". Bombardier Transportation. October 8, 2015. Archived from the original on January 9, 2019. Retrieved May 18, 2020.
  5. ^ "FAQs". Eglinton Crosstown: The Project. Metrolinx. Retrieved February 12, 2017. Q: What is the timeline for the project? A:The project will be complete in 2021
  6. ^ Spurr, Ben (December 30, 2019). "Eglinton Crosstown LRT could be $330 million over budget and open seven months late, internal documents warn". Toronto Star. Archived from the original on March 14, 2020. Retrieved April 19, 2020.
  7. ^ "Eglinton-Scarborough Crosstown Update" (PDF). Metrolinx. June 23, 2011.
  8. ^ Jump up to: a b "Agenda Item History". app.toronto.ca. Retrieved September 7, 2020.
  9. ^ "Next steps announced for Eglinton Crosstown West subway extension into Etobicoke, Mississauga". Global News. Retrieved September 7, 2020.
  10. ^ "Eglinton Crosstown Light Rail Transit stops and stations" (PDF). City of Toronto. November 2010. Retrieved July 30, 2011.
  11. ^ Jump up to: a b c "Eglinton Crosstown Backgrounder". Metrolinx. Retrieved November 8, 2013.
  12. ^ "Document d'information – Eglinton Crosstown" (in French). Metrolinx. Archived from the original on November 7, 2019. Retrieved May 9, 2020.
  13. ^ Spears, John (August 9, 2008). "Distance between LRT stops criticized". Toronto Star. Retrieved August 14, 2008.
  14. ^ "Eglinton Transit City line may survive". CBC News. January 4, 2011. Retrieved April 24, 2011.
  15. ^ "Truncated version of Transit City does not satisfy mayor". East York Mirror. May 6, 2010. Archived from the original on May 28, 2021. Retrieved May 28, 2021.
  16. ^ D'Cruz, Andrew (December 1, 2010). "Mayor Rob Ford: "Transit City is over"". Toronto Life. Archived from the original on December 4, 2010. Retrieved August 4, 2014.
  17. ^ Jump up to: a b Kalinowski, Tess; Dale, Daniel (February 9, 2012). "Special transit meeting: Mayor Rob Ford dismisses council's vote against his subway plan". Toronto Star. Toronto. Archived from the original on February 10, 2012.
  18. ^ http://thecrosstown.ca/news-media/whats-new/Online-Consultation-Laird-Don-Valley
  19. ^ Kalinowski, Tess (May 12, 2013). "Metrolinx puts Leslie back on the Crosstown map". Toronto Star. Retrieved November 8, 2013.
  20. ^ Kalinowski, Tess (May 6, 2013). "Scarborough councillors seek subway line instead of LRT: A group of Toronto councillors wants to replace the planned LRT for Scarborough with a subway. But a subway would cost $500 million more". Toronto Star. Archived from the original on July 3, 2013. Retrieved July 3, 2013. An LRT would use the same route as the SRT. It would be 9.9 kilometres (6.2 mi) versus 7.6 kilometres (4.7 mi) of subway. The LRT would have seven stations, the subway, only three.
  21. ^ Kalinowski, Tess (January 17, 2013). "TTC report threatens to reopen Scarborough subway debate: One commissioner says it's proof Scarborough can have a new subway line under construction within the decade, but Metrolinx dismisses that". Toronto Star. Archived from the original on September 26, 2013. Retrieved July 3, 2013. Glenn DeBaeremaeker (Ward 38, Scarborough Centre) said the latest TTC report gives him new confidence that there will be a subway underway in Scarborough within a decade.
  22. ^ Jump up to: a b c Kalinowski, Tess (November 3, 2015). "$9.1B Crosstown LRT mega-contract comes in under estimates". Toronto Star. Retrieved November 3, 2015.
  23. ^ Moore, Oliver (November 3, 2015). "Ontario government shaves $2-billion off Eglinton Crosstown LRT price tag". The Globe and Mail. Retrieved November 3, 2015.
  24. ^ "Bombardier wins $403M Eglinton Crosstown maintenance contract". Canadian Manufacturing. July 27, 2015. Archived from the original on September 21, 2020. Retrieved April 28, 2021.
  25. ^ "Bombardier awarded 30-year services contract for Toronto's Finch West Light Rail Transit project". GlobeNewswire. December 23, 2020. Archived from the original on December 27, 2020. Retrieved April 28, 2021.
  26. ^ Kalinowski, Tess (July 28, 2010). "Metrolinx orders tunneling machines". Toronto Star.
  27. ^ Jump up to: a b c McKenzie, Daniel (August 17, 2016). "Big dig wraps for Eglinton Crosstown LRT". Toronto Sun. Retrieved August 18, 2016.
  28. ^ "Announcing the winning names of the Tunnel Boring Machine Naming Contest..." Metrolinx. June 5, 2013. Retrieved February 12, 2017. The most popular set of names were shortlisted and voted on by the public. Thank you to Jason Paris (Dennis and Lea), Graham Gersdorff, Val Dodge and Reiner Kravis (Don and Humber) of Toronto for submitting the winning names!
  29. ^ Leal, Brandon (June 5, 2013). "Eglinton Crosstown TBMs get a Personality and a Send-Off". Urban Toronto. Retrieved February 12, 2017. In October 2012 Metrolinx announced a near month long contest public contest to name the tunnel boring machines (TBM).
  30. ^ Jump up to: a b c d Winsa, Patty (March 21, 2014). "Metrolinx begins its big eastern dig on the Eglinton Crosstown LRT: Get ready for traffic". Toronto Star. Archived from the original on March 23, 2014. Parts for the next two tunnel-boring machines to work on digging underground parts of the line — nicknamed Don and Humber — will arrive this summer and be assembled in the shaft, before they start drilling the 3.25-kilometre section west to Yonge St.
  31. ^ Thompson, John (March 8, 2016). "Eglinton Crosstown under way, underground". Railway Age. Retrieved March 5, 2020.
  32. ^ Alcoba, Natalie (November 9, 2011). "Ford, McGuinty get up-close look at Eglinton LRT construction". National Post. Retrieved August 4, 2014.
  33. ^ Chu, Showwei (May 29, 2012). "Eglinton LRT unlikely to meet 2020 completion date: TTC report". Citytv News. Toronto. Archived from the original on January 19, 2013. Retrieved June 25, 2012.
  34. ^ Jump up to: a b c Kalinowski, Tess (September 24, 2015). "Eglinton Crosstown to open a year later than expected". Toronto Star. Retrieved September 24, 2015.
  35. ^ "Request for Qualifications Issued for the Eglinton Crosstown LRT and Scarborough LRT Lines". Infrastructure Ontario. January 22, 2013. Retrieved March 10, 2013.
  36. ^ Kalinowski, Tess (February 22, 2013). "Eglinton Crosstown LRT tunneling a step closer". Toronto Star. Retrieved August 4, 2014.
  37. ^ "Machines begin tunnelling for Eglinton Crosstown LRT". CBC News. June 5, 2013. Retrieved July 5, 2013.
  38. ^ Landau, Jack (November 12, 2013). "Metrolinx Awards Contract for Crosstown LRT East Tunnel Section". Urban Toronto. Archived from the original on September 3, 2014. Retrieved October 12, 2014. As tunnel boring machines continue to etch their path eastbound underneath Eglinton Avenue from Keele Street for the western leg of the Eglinton Crosstown LRT project, a winning bidder has been announced for the eastern section of tunnel, which will run from Brentciffe Road to Yonge Street, starting just east of the easternmost underground station at Laird Drive.
  39. ^ Alamenciak, Tim (April 30, 2014). "Eglinton Crosstown LRT back on schedule, engineer says". Toronto Star. Archived from the original on August 3, 2014. Retrieved January 22, 2015. "It's a seemingly simple process that's actually very high tech," said Kramer. The first of the two tunneling machines (dubbed Dennis) entered the ground June of 2013 and has made it to Caledonia Rd. from its starting point at Black Creek Dr. The other machine, Lea, is just behind.
  40. ^ Moore, Oliver (April 29, 2014). "Underground for now, construction proceeds on Eglinton LRT". The Globe and Mail. Archived from the original on December 21, 2014. Retrieved January 22, 2015. Headwalls that will form the box of the stations have been installed at Keele Street and Caledonia Road, and work is under way on one at Dufferin Street. The TBMs go right through headwalls after they have been built, in order to ensure a tight seal, and the two at work in this area are now on either side of what will eventually be the Caledonia LRT station.
  41. ^ Gupta, Rahul (May 9, 2014). "Eglinton LRT: Construction activity well underway on both sides of Allen Road". Inside Toronto. Archived from the original on January 23, 2015. Retrieved January 22, 2015. Digging 50 feet below street level, the 81-metre long TBMs nicknamed Dennis and Lea are located in the vicinity of Caledonia Road, one of 12 underground Crosstown stations planned for the route. They are expected to reach the Allen later this year, when they will be redeployed beyond Eglinton West subway station to continue the dig east towards Yonge Street.
  42. ^ Eglinton Crosstown TBM Tracker
  43. ^ Carville, Olivia (April 19, 2015). "An exciting glimpse at boring machines on Eglinton". Toronto Star.
  44. ^ Pelley, Lauren (April 19, 2015). "Eglinton businesses feeling sting of Crosstown construction". Toronto Star.
  45. ^ Collins, Jack (May 19, 2010). "Achieving 5 in 10 – A Revised Plan for the Big 5 Transit Projects" (PDF). Metrolinx. Retrieved September 27, 2015. Complete and in-service by 2020
  46. ^ "Launch of tunnel boring machines and tunnelling work in the east". Metrolinx. October 1, 2015. Retrieved October 13, 2015.
  47. ^ "Crews break ground on 1st of 25 Eglinton Crosstown stations". CBC News. March 10, 2016. Retrieved March 22, 2016.
  48. ^ "Temporary Closure of Holly Street at Eglinton Avenue East". Metrolinx. February 24, 2016. Retrieved February 12, 2017. The extraction shaft is required to be completed in advance of receiving the two TBMs (Don and Humber), which are currently tunnelling westward from their start-point, just east of Brentcliffe Road.
  49. ^ Johnston, Paul (April 18, 2016). "Eglinton scaffolding collapse injures 7, including baby: paramedics". CP24. Bell Media Inc. Retrieved February 11, 2020.
  50. ^ "Crosstown Tunnelling Reaches Yonge Street". Ministry of Transportation of Ontario. May 10, 2016. Retrieved February 12, 2017. Today Tunnel Boring Machines (TBMs) Dennis and Lea, boring the western segment tunnels, arrived at Yonge Street having travelled 6,419 metres from where they started at Black Creek Drive in spring 2013.
  51. ^ Jump up to: a b Spurr, Ben (November 3, 2016). "Metrolinx says it intends to cancel Bombardier LRV contract". Toronto Star. Retrieved February 12, 2017. The ministry of transportation confirmed to the Star on Thursday that Metrolinx, the provincial transit agency, has issued a formal notice of intent to terminate its $770-million contract for up to 182 Bombardier LRVs.
  52. ^ Jump up to: a b c Jeff, Shaun (February 10, 2017). "Bombardier taking Metrolinx to court over threats to scrap light-rail vehicle deal". Toronto Sun. Retrieved February 12, 2017. Bombardier filed an injunction Friday with Ontario's Superior Court in response to what the company calls "unjustified threats" to kill a $770-million contract signed in 2010.
  53. ^ Jump up to: a b Spurr, Ben (February 10, 2017). "Bombardier taking Metrolinx to court". Toronto Star. Retrieved February 12, 2017. Bombardier's legal gambit comes three months after Metrolinx issued the company a notice of intention to cancel its contract for up to 182 light rail vehicles.
  54. ^ "Transport minister fires back at Bombardier for court injunction against Metrolinx". CBC News. February 10, 2017. Retrieved February 12, 2017. In a statement, Bombardier says the goal of the injunction application is to encourage Metrolinx to 'resume good faith discussions.'
  55. ^ Moore, Oliver (February 14, 2017). "Metrolinx rejects Bombardier's claims of laxity in wake of court filing". The Globe and Mail. Retrieved February 15, 2017. A senior person at Bombardier familiar with the process says the company had to go to court after months of behind-the-scenes talks with Metrolinx hit an impasse.
  56. ^ "Join us March 13 to say farewell to the Crosstown's TBM". Metrolinx. October 3, 2017. Retrieved March 13, 2017. Metrolinx invites you to join us throughout the week of March 13, 2017 to watch the pieces of being lifted and transported offsite. We will start the process of extracting the tunnel boring machines (TBM) from the completed east tunnels, and say farewell to our faithful helpers, TBM Don and TBM Humber. The TBMs will be disassembled and lifted from extraction shaft just east of Yonge & Eglinton in four oversized sections over four days. ... Each piece will be lifted from the extraction shaft in the morning, and placed on the ground within the construction zone. Later, after 9 p.m. that night, the piece will be loaded onto a large truck and hauled away. TBM Don, the machine that bored the north tunnel, will be removed first.
  57. ^ Dolski, Megan (March 13, 2017). "Work starts on stations, tracks for Eglinton-Crosstown LRT". Toronto Star. Retrieved March 14, 2017.
  58. ^ Jump up to: a b "Eglinton Crosstown LRT Updates – July 2017". Metrolinx. July 14, 2017. Retrieved July 14, 2017.
  59. ^ Jump up to: a b "Eglinton Crosstown LRT Updates – August 2017". Metrolinx. August 11, 2017. Retrieved August 11, 2017.
  60. ^ "Shop the Largest Online Selection Harley Davidson Motocycle Parts Online Now – Clearance Sale up to 60% OFF".
  61. ^ "Shop the Largest Online Selection Harley Davidson Motocycle Parts Online Now – Clearance Sale up to 60% OFF".
  62. ^ Spurr, Ben (July 11, 2018). "Companies building Eglinton Crosstown LRT sue Metrolinx for breach of contract". The Star. Retrieved August 8, 2018.
  63. ^ Jump up to: a b "Auditor-General says Metrolinx paid massive settlement without thoroughly reviewing claim". Retrieved December 18, 2018.
  64. ^ Spurr, Ben (August 8, 2018). "Metrolinx asks court to block lawsuit over Eglinton Crosstown LRT line". The Star. Retrieved August 8, 2018.
  65. ^ "LRT legal challenge settled with terms kept confidential". The South Bayview Bulldog. September 7, 2018. Retrieved September 24, 2018.
  66. ^ "Metrolinx—LRT Construction and Infrastructure Planning" (PDF). www.auditor.on.ca. Retrieved December 18, 2018.
  67. ^ Jump up to: a b "Eglinton Crosstown Update". Metrolinx. January 11, 2019. Retrieved January 13, 2019.
  68. ^ Jump up to: a b "Bombardier delivers first LRV for Eglinton Crosstown, on track for TTC streetcar delivery". CityNews. January 8, 2019. Retrieved January 8, 2019.
  69. ^ "East Guideway Concrete Pour". Metrolinx. February 15, 2019. Retrieved April 7, 2019.
  70. ^ "Proposed Leslie Street Closure". March 29, 2019. Retrieved April 3, 2019.
  71. ^ Jump up to: a b "Eglinton Crosstown LRT could be $330 million over budget and open seven months late, internal documents warn | The Star". thestar.com. December 30, 2019. Retrieved February 19, 2020.
  72. ^ @GreggLintern (December 14, 2019). "Light rail at the end of the tunnel" (Tweet) – via Twitter.
  73. ^ Jump up to: a b "Training tale – First Eglinton Crosstown light rail vehicle hits tracks of main Toronto line". Metrolinx. January 9, 2020. Archived from the original on December 27, 2019. Retrieved December 20, 2019.
  74. ^ "Eglinton Crosstown Update February 2020". Metrolinx. February 2020. Archived from the original on February 21, 2020. Retrieved February 21, 2020.
  75. ^ "Eglinton Crosstown LRT won't be ready until 'well into 2022,' Metrolinx says". CBC News. February 18, 2020. Retrieved February 18, 2020.
  76. ^ Spurr, Ben (February 17, 2020). "Eglinton Crosstown faces another setback, delayed until 2022". Toronto Star. Retrieved February 18, 2020.
  77. ^ Rider, David (March 9, 2020). "Ford government pledges $3M for businesses affected by Eglinton LRT construction". Toronto Star. Retrieved March 10, 2020.
  78. ^ Jump up to: a b "Eglinton Crosstown Update". Metrolinx. March 13, 2020. Archived from the original on March 16, 2020. Retrieved March 16, 2020.
  79. ^ "See video of the first time a light rail vehicle passes through a Crosstown tunnel". Metrolinx. May 4, 2020. Archived from the original on May 9, 2020. Retrieved May 9, 2020.
  80. ^ "In 'extraordinary step,' company building Eglinton Crosstown hits province with lawsuit". Canadian Broadcasting Corporation. October 8, 2020. Retrieved October 8, 2020.
  81. ^ "The art of the line – How Toronto's Crosstown LRT is adding creative touches to transit design". December 9, 2020.
  82. ^ "Crosstown LRT crews complete installation of rail on important stretch of Toronto's Brentcliffe Portal". Metrolinx. April 7, 2021. Archived from the original on April 11, 2021. Retrieved April 13, 2021.
  83. ^ Jump up to: a b "Crosstown projects sees new track brought in for light rail vehicles". Metrolinx. April 29, 2021. Archived from the original on April 29, 2021. Retrieved April 29, 2021.
  84. ^ "Crosstown LRT projects sees significant concrete milestones as well as main entrance features at Science Centre Station". Metrolinx. April 21, 2021. Archived from the original on April 21, 2021. Retrieved April 21, 2021.
  85. ^ "Overhead Catenary System Energization between Laird Drive and Kennedy Road". Metrolinx. May 3, 2021. Archived from the original on May 1, 2021. Retrieved May 1, 2021.
  86. ^ "Powering up the Eglinton Crosstown LRT for the first time". Metrolinx. May 10, 2021. Archived from the original on May 10, 2021. Retrieved May 10, 2021.
  87. ^ Spurr, Ben (May 17, 2021). "Eglinton Crosstown LRT to cost more and take longer, after builder scores legal victory". Toronto Star. Retrieved May 18, 2021.
  88. ^ "Light Rail Vehicle Delivery and Testing between Laird Dr. and Kennedy Rd". Metrolinx. Archived from the original on May 13, 2021. Retrieved May 13, 2021.
  89. ^ "Get an update on the first batch of Eglinton Crosstown LRT vehicles as they begin their testing journey". Metrolinx. May 27, 2021. Archived from the original on May 27, 2021. Retrieved June 8, 2021.
  90. ^ "See new videos of Crosstown light rail vehicles arrive in preparation for testing to come". Metrolinx. June 3, 2021. Archived from the original on June 3, 2021. Retrieved June 8, 2021.
  91. ^ "TTC to renumber 5 Avenue and 6 Bay bus routes to prepare for future rapid transit lines". Toronto Transit Commission. June 18, 2021. Archived from the original on June 22, 2021. Retrieved June 21, 2021.
  92. ^ "Crews use unusual formwork on Crosstown LRT project as team gets closer to putting down all rail". Metrolinx. July 12, 2021. Archived from the original on July 12, 2021. Retrieved July 12, 2021.
  93. ^ "Testing begins as Crosstown LRT vehicles make their first move along Eglinton Avenue". Metrolinx. August 24, 2021. Retrieved August 28, 2021.
  94. ^ "Line 5 Eglinton Station Names" (PDF). Board Presentation. Toronto Transit Commission. November 23, 2015. Retrieved November 30, 2015. In order to reduce confusion with Eglinton Station and Line 5 Eglinton, Eglinton West Station will be renamed. ... TTC staff evaluated the initial report and the proposed names and provided feedback and recommendations. A primary TTC concern was to avoid replication and redundancy with existing TTC station names. The proposed names are unique and are not likely to be confused with existing station names.
  95. ^ Jump up to: a b Kalinowski, Tess (November 24, 2015). "Eglinton West station to become 'Cedarvale' because of Crosstown LRT". Toronto Star. Retrieved November 24, 2015.
  96. ^ "Eglinton Crosstown Line Station and Stop Names". Metrolinx. October 2, 2015. Retrieved October 2, 2015.
  97. ^ "City of Toronto: Get Involved > Eglinton Crosstown Light Rail Transit (LRT) > Frequently Asked Questions > Stations and Stops". City of Toronto. August 20, 2011. Archived from the original on October 21, 2011. Retrieved October 24, 2011.
  98. ^ "Science Centre Station and West At-Grade (Sunnybrook Park Stop to O'Connor Stop) Open House". Metrolinx. November 14, 2017. p. 29. Retrieved November 14, 2017.
  99. ^ "The Eglinton Crosstown LRT is going green". Metrolinx. August 4, 2021. Retrieved August 30, 2021.
  100. ^ "Sunnybrook Park stop is more light in Crosstown progress". Metrolinx. May 6, 2019. Retrieved May 14, 2019.
  101. ^ Jump up to: a b "Transit Facts – Surface Section" (PDF). Metrolinx. Archived from the original (PDF) on May 9, 2020. Retrieved May 9, 2020.
  102. ^ "Stations and Stops". Metrolinx. Retrieved January 10, 2018.
  103. ^ Jump up to: a b Spurr, Ben (January 15, 2018). "Art installations will enliven Eglinton Crosstown LRT". Toronto Star. Retrieved January 18, 2018.
  104. ^ Jump up to: a b "How will the Eglinton Crosstown LRT's automatic train control work? We break down every major element in an infographic". Metrolinx. December 9, 2019. Archived from the original on January 9, 2020. Retrieved January 9, 2020.
  105. ^ Munro, Steve (June 17, 2013). "Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8)". Steve Munro. Archived from the original on March 4, 2015. Retrieved June 17, 2013.
  106. ^ "Light Rail Transit Facts". Metrolinx. May 31, 2015. Retrieved May 31, 2015.
  107. ^ TTC/City Of Toronto (March 2010). "Eglinton Crosstown Environmental Report" (PDF). Retrieved April 8, 2019.
  108. ^ Spurr, Ben (July 20, 2016). "Metrolinx threatens legal action over late delivery of light rail vehicles". Toronto Star. Retrieved July 20, 2016.
  109. ^ Spurr, Ben; Pagliaro, Jennifer (October 31, 2016). "Report outlines steep costs of running new Toronto transit lines". Toronto Star. Retrieved October 31, 2016.
  110. ^ "Transit City measures up to international standard". Toronto Star. January 6, 2010. Retrieved October 4, 2014.
  111. ^ Bow, James (June 13, 2019). "The Toronto Flexity Freedom Light Rail Vehicles". Transit Toronto. Retrieved February 22, 2020.
  112. ^ Spurr, Ben (March 2, 2017). "Metrolinx in talks with another company to replace Bombardier vehicles as fears mount over $500,000 a day late fees". Toronto Star. Retrieved May 12, 2017.
  113. ^ Spurr, Ben (May 12, 2017). "Province had no choice but to seek Bombardier substitute for Eglinton LRT: Del Duca". Toronto Star. Retrieved May 12, 2017.
  114. ^ "Metrolinx statement on Alstom/Bombardier". Metrolinx. Retrieved May 12, 2017.
  115. ^ Spurr, Ben (May 13, 2017). "How do TTC's streetcar options compare? It's Bombardier versus Alstom". Toronto Star. Retrieved May 13, 2017.
  116. ^ Spurr, Ben (October 30, 2018). "First Eglinton Crosstown LRT vehicle to be ready in November, Bombardier says". Toronto Star. Retrieved October 30, 2018. The company plans to ship the vehicle to Toronto next month, and has a target of delivering five more by mid-February. It intends to supply the entire fleet of 76 vehicles to Metrolinx, the provincial agency that's building the Crosstown, in time for the line's opening.
  117. ^ "Keele Street to Jane Section and Black Creek Maintenance & Storage Facility Environmental Project Report Addendum Online Consultation". Metrolinx. 2016. Archived from the original on July 25, 2016. Ultimate storage yard capacity of 162 vehicles;
  118. ^ Lorinc, John (November 23, 2012). "Down (but not out) Mount Dennis area pins hopes on Metrolinx". The Globe and Mail. Archived from the original on March 4, 2016. Retrieved March 28, 2013. A sprawling storage and maintenance facility for the light-rail vehicles will be built on the Kodak site within a few years.
  119. ^ Munro, Steve (February 17, 2010). "Eglinton LRT: Trouble Brewing in Mt. Dennis (Update 2)". Archived from the original on March 4, 2015. Some speakers addressed the use of the Kodak lands for the proposed carhouse, and asked that alternative schemes be considered. Part of this relates to a proposed "big box" development on the land. However, Council approved the acquisition of this property, by expropriation if necessary, in December.
  120. ^ Kalinowski, Tess (February 16, 2010). "Residents ask TTC for LRT tunnel through Mount Dennis". Toronto Star. Archived from the original on October 3, 2013. In addition to the $4.6 billion the province has committed to the Eglinton LRT, the centrepiece of Toronto's Transit City plan, the TTC also wants to build a carhouse on the old Kodak lands in Mount Dennis.
  121. ^ Jump up to: a b "Eglinton Crosstown West Extension". Metrolinx. Retrieved September 21, 2020.
  122. ^ Jump up to: a b "Eglinton East LRT left out of Ontario's new transit plan". Centennial Community and Recreation Association. March 24, 2020. Archived from the original on March 24, 2020. Retrieved August 19, 2020.
  123. ^ Munro, Steve (September 16, 2014). "John Tory's "SmartTrack": Will That Train Ever Leave The Station?". Steve Munro.
  124. ^ Munro, Steve (October 17, 2014). "SmartTrack: That Pesky Curve in Mount Dennis". Steve Munro.
  125. ^ Jump up to: a b Keesmaat, Jennifer (January 18, 2016). "SmartTrack Western Corridor Feasibility Review" (PDF). City of Toronto. Retrieved February 12, 2017. The feasibility review examined heavy rail corridor options from several perspectives: technical requirements for heavy rail, service concept and integration with RER, regulatory requirements for heavy rail, land use compatibility and impacts, and cost.
  126. ^ "SmartTrack still on track despite changing plan, Mayor Tory says". Toronto Star. January 19, 2016.
  127. ^ Jump up to: a b Moore, Oliver (July 13, 2016). "Toronto City Council approves planning for raft of transit projects". The Globe and Mail. Retrieved July 14, 2016.
  128. ^ Spurr, Ben; Pagliaro, Jennifer (June 26, 2016). "Mayor John Tory's transit priorities face financial, political challenge: analysis". Toronto Star. Retrieved July 20, 2016.
  129. ^ Grewal, San (November 2, 2016). "Mississauga fumes over $470 million Toronto LRT funding assumption". Toronto Star. Retrieved November 2, 2016.
  130. ^ Johnson, Andrew (November 7, 2017). "Public Meetings for Eglinton West LRT to Begin November 13th". Urban Toronto. Retrieved November 13, 2017.
  131. ^ "About the Eglinton West LRT". Eglinton West LRT. City of Toronto. Retrieved November 13, 2017.
  132. ^ Johnson, Andrew (November 7, 2017). "Public Meetings for Eglinton West LRT to Begin November 13th". UrbanToronto. Retrieved November 22, 2017.
  133. ^ "Eglinton West LRT: Stage One Report" (PDF). Municipal government of Toronto. October 3, 2017. Retrieved November 22, 2017.
  134. ^ Jump up to: a b c Pagliaro, Jennifer (November 28, 2017). "Tory backs second look at tunnelled Eglinton West LRT". Toronto Star. Retrieved November 29, 2017.
  135. ^ "Attachment 2 Eglinton West LRT Extension Technical & Planning Update" (PDF). City of Toronto. October 3, 2017. p. 2. Retrieved November 22, 2017.
  136. ^ Pagliaro, Jennifer (November 21, 2017). "City staff recommend moving ahead on SmartTrack stations despite financing uncertainty". Toronto Star. Retrieved November 22, 2017. A report from city staff released Tuesday ... recommends a 10-stop LRT along Eglinton Ave. West.
  137. ^ "What you need to know about Doug Ford's contentious plan for transit in the GTA". CBC News. Canadian Broadcasting Corporation. April 10, 2019. Retrieved December 21, 2019.
  138. ^ "Eglinton Crosstown West Extension Initial Business Case" (PDF). metrolinx.com. Metrolinx. February 2020. Retrieved March 6, 2020.
  139. ^ Jump up to: a b Spurr, Ben (September 20, 2020). "Burying the Eglinton West LRT will cost an extra $1.8 billion and may serve fewer local riders. So why do it?". Toronto Star. Retrieved September 21, 2020.
  140. ^ Moore, Oliver (February 28, 2020). "Costs of major transit projects will far exceed their benefits, according to Metrolinx reports". The Globe and Mail. Retrieved March 17, 2020.
  141. ^ "Eglinton Crosstown West Extension Information Session" (PDF). metrolinxengage.com. Metrolinx. April 2020. Retrieved April 15, 2020.
  142. ^ Jump up to: a b c Mackenzie, Robert (March 17, 2020). "Metrolinx's Eglinton West LRT Business Case Goes Underground". UrbanToronto. Retrieved September 21, 2020.
  143. ^ "Eglinton Crosstown West Extension deal signed and sealed". Metrolinx. May 20, 2021. Archived from the original on May 21, 2021. Retrieved May 21, 2021.
  144. ^ "Eglinton Crosstown West Extension – Neighbourhood Updates". Metrolinx. Retrieved July 14, 2021.
  145. ^ "Eglinton Crosstown West Extension - LIVE Meeting". Metrolinx. August 19, 2021. p. 0:28:33–0:30:37.
  146. ^ Moore, Oliver; Gee, Marcus (January 20, 2016). "Scarborough subway would shrink under plan to extend Eglinton Crosstown". The Globe and Mail. Retrieved November 30, 2017.
  147. ^ Jump up to: a b Pagliaro, Jennifer; Kalinowski, Tess (January 16, 2016). "New Scarborough transit plan 'buys peace in the land'". Toronto Star. Retrieved January 20, 2016.
  148. ^ Keenan, Edward (June 2, 2016). "Priority should be alternative transit routes into downtown: Keenan". Toronto Star. Retrieved June 5, 2016.
  149. ^ "Scarborough Malvern Light Rail Transit (LRT): Notice of Completion of the Environmental Project Report" (PDF). City of Toronto. October 16, 2009. Retrieved February 12, 2017. The Toronto Transit Commission (TTC) and the City of Toronto have completed an Environmental Project Report (EPR) for the fifteen kilometre Scarborough Malvern Light Rail Transit (LRT) which would connect Kennedy Subway Station with north-eastern Scarborough.
  150. ^ "Request for Approval of the Scarborough-Malvern LRT Environmental Assessment Study – City Council Decision". City Of Toronto. September 30, 2009. Retrieved February 12, 2017. City Council approve the recommendations of the Scarborough-Malvern LRT Transit Project Assessment Study and authorize submission of the Environmental Project Report (EPR) to the Ministry of the Environment.
  151. ^ "Minister's Notice to Proceed" (PDF). Ministry of Transportation of Ontario. December 15, 2009. Retrieved February 12, 2017.
  152. ^ Jump up to: a b c Pagliaro, Jennifer (November 29, 2017). "Mayor John Tory and Councillor Josh Matlow square off on Scarborough transit". Toronto Star. Retrieved November 30, 2017.
  153. ^ "Eglinton East Corridor Wish Mapping". Eglinton East LRT. Retrieved January 26, 2019.
  154. ^ "Implementation of priority bus-only lanes to be accelerated across the city; Eglinton East identified as first priority". Toronto Transit Commission. July 8, 2020. Archived from the original on August 19, 2020. Retrieved August 19, 2020.
  155. ^ "Attachment 1 Eglinton East Light Rail Transit and the Waterfront Transit Network" (PDF). Retrieved December 3, 2020.
  156. ^ Pagliaro, Jennifer (February 11, 2021). "Mayor's executive committee approves almost $14B in spending — but nothing for supportive housing proposal for Toronto's homeless". Toronto Star. Retrieved February 15, 2021.

External links[]

Retrieved from ""