List of commercial nuclear reactors

From Wikipedia, the free encyclopedia

This is a list of all the commercial nuclear reactors in the world, sorted by country, with operational status. The list only includes civilian nuclear power reactors used to generate electricity for a power grid. All commercial nuclear reactors use nuclear fission. As of April 2020, there are 440 operable power reactors in the world, with a combined electrical capacity of 390 GW. Additionally, there are 55 reactors under construction and 109 reactors planned, with a combined capacity of 63 GW and 118 GW, respectively,[1] while 329 more reactors are proposed.[1] For non-power reactors, see List of nuclear research reactors. Where not otherwise specified, all information is sourced from the Power Reactor Information System (PRIS) of the International Atomic Energy Agency (IAEA).[2]

In the following tables, the net capacity or reference unit power, expressed in megawatt (MW), is the maximum electricity output under reference ambient conditions, after deducting the losses within the system including the energy transformers.[3]

Argentina[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Atucha[4] 1 PHWR Siemens-KWU Operational 335 1 June 1968 24 June 1974
2 PHWR Siemens-KWU Operational 692 14 July 1981 (halted in 1994, restarted in 2007) 27 June 2014
3 PHWR CANDU-6 Planned[5] 800 (2025)
5th Plant[6] 1 PWR Hualong-1 Planned 1000 (2026)
Embalse[7] 1 PHWR CANDU-6 Operational 600 1 April 1974 20 January 1984 (2049)[8]
CAREM 1 PWR CAREM25 Under construction 25 8 February 2014

Armenia[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Metsamor 1 PWR VVER-440 V-270 Shut down 376 1 July 1969 6 October 1977 25 February 1989
2 PWR VVER-440 V-270 Operational 375 1 July 1975 3 May 1980 (2026)
3 PWR VVER-1200 V-392 Planned 1060 (2023)

Austria[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Zwentendorf 1 BWR BWR-69 (KWU) Finished; never entered service April 1972 5 November 1978

Bangladesh[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Ruppur 1 PWR VVER-1200/523 Under construction 1080 30 November 2017[9] (2023)
2 PWR VVER-1200/523 Under construction 1080 14 July 2018 (2024)

Belarus[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Ostrovets 1 PWR VVER-1200 V-491 Operational[10] 1109 6 November 2013 10 June 2021
2 PWR VVER-1200 V-491 Under construction 1109 24 April 2014 (2022)
1 PWR VVER-1000 Unfinished 1983 1987
2 PWR VVER-1000 Unfinished 1983 1987

Belgium[]

Name Unit
No.
Reactor Status[11] Net capacity (MW) Construction start Commercial operation Closure
Type Model
Mol 1 PWR Westinghouse (WH) BR-3 Decommissioned 10 1 November 1957 10 October 1962 30 June 1987
Doel 1 PWR WH, 2 loops Operational 433 1 July 1969 15 February 1975 (2025)
2 PWR WH, 2 loops Operational 433 1 September 1971 1 December 1975 (2025)
3 PWR Framatome, 3-loops Operational 1006 1 January 1975 1 October 1982 (2022)
4 PWR Belgian firms plus WH, 3 loops Operational 1039 1 December 1978 1 July 1985 (2025)
Tihange 1 PWR Framatome, 3 loops Operational 962 1 June 1970 1 October 1975 (2025)
2 PWR Framatome, 3-loops Operational 1008 1 April 1976 1 June 1983 (2023)
3 PWR Belgian firms plus WH, 3 loops Operational 1046 1 November 1978 1 September 1985 (2025)

Brazil[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Angra 1 PWR Westinghouse (WH) 2 loops Operational 609 1 May 1971 1 January 1985
2 PWR  [de] Operational 1275 1 January 1976 1 February 2001
3 PWR Pre-Konvoi Under construction 1245 1984 (halted in 1986, restarted on 1 June 2010)

Bulgaria[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Kozloduy 1 PWR VVER-440/V-230 Shut down 408 1 April 1970 28 October 1974 31 December 2002
2 PWR VVER-440/V-230 Shut down 408 1 April 1970 10 November 1975 31 December 2002
3 PWR VVER-440/V-230 Shut down 408 1 October 1973 20 January 1981 31 December 2006
4 PWR VVER-440/V-230 Shut down 408 1 October 1973 20 June 1982 31 December 2006
5 PWR VVER-1000/V-320 Operational 963 9 July 1980 23 December 1988
6 PWR VVER-1000/V-320 Operational 963 1 April 1982 30 December 1993
Belene 1 PWR VVER-1000/V-320
VVER-1000/V-446B
Unfinished
2 PWR VVER-1000/V-320
VVER-1000/V-446B
Unfinished

Canada[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Pickering 1 PHWR CANDU Operational 515 June 1966 29 July 1971 (2022)
2 PHWR CANDU Shut down 515 September 1966 30 December 1971 1997
3 PHWR CANDU Shut down 515 December 1967 1 June 1972 1997
4 PHWR CANDU Operational 515 May 1968 17 June 1973 (2022)
5 PHWR CANDU Operational 516 November 1974 10 May 1983 (2024)
6 PHWR CANDU Operational 516 October 1975 1 February 1984 (2024)
7 PHWR CANDU Operational 516 March 1976 1 January 1985 (2024)
8 PHWR CANDU Operational 516 September 1976 28 February 1986 (2024)
Darlington 1 PHWR CANDU Operational 878 April 1982 14 November 1992 (2052)
2 PHWR CANDU Operational 878 September 1981 9 October 1990 (2050)
3 PHWR CANDU Operational 878 September 1984 14 February 1993 (2053)
4 PHWR CANDU Operational 878 July 1985 14 June 1993 (2053)
5[12] BWR BWRX-300 Planned 300 (2023) (2028)
6[12] BWR BWRX-300 Planned 300 (2023) (2028)
Bruce 1 PHWR CANDU Operational 774 June 1971 1 September 1977 (2042)
2 PHWR CANDU Operational 777 December 1970 1 September 1977 (2043)
3 PHWR CANDU Operational 770 July 1972 1 February 1978 (2064)
4 PHWR CANDU Operational 769 September 1972 18 January 1979 (2064)
5 PHWR CANDU Operational 817 June 1978 1 March 1985 (2064)
6 PHWR CANDU Operational 817 January 1978 15 September 1984 (2064)
7 PHWR CANDU Operational 817 May 1979 10 April 1986 (2064)
8 PHWR CANDU Operational 817 August 1979 22 May 1987 (2064)
NPD 1 PHWR CANDU Shut down 19.5 January 1958 4 June 1962 1987
Douglas Point 1 PHWR CANDU Shut down 200 February 1960 26 September 1968 1984
Gentilly 1 BWR CANDU Shut down 250 September 1966 1 May 1972 1977
2 PHWR CANDU-6 Shut down 635 April 1974 1 October 1983 2012
Point Lepreau 1 PHWR CANDU Operational 635 May 1975 1 February 1983 (2041)

China[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Bailong 1 PWR CAP-1000 Planned 1100
2 PWR CAP-1000 Planned 1100
3 PWR CAP-1000 Planned 1100
4 PWR CAP-1000 Planned 1100
5 PWR CAP-1000 Planned 1100
6 PWR CAP-1000 Planned 1100
Changjiang I-1 PWR CNP-600 Operational 601 25 April 2010 25 December 2015
I-2 PWR CNP-600 Operational 601 21 November 2010 20 June 2016
I-3[13] PWR Hualong-1 Under construction 1200 31 March 2021[14]
I-4[13] PWR Hualong-1 Under construction 1200 31 March 2021[14]
II-1 PWR ACP-100 Under construction 100 13 July 2021
II-2 PWR ACP-100 Planned 100
Daya Bay (Guangdong) 1 PWR M-310 Operational 944 7 August 1987 1 February 1994
2 PWR M-310 Operational 944 7 April 1988 6 May 1994
Fangchenggang 1 PWR CPR-1000 Operational 1000 30 July 2010 25 October 2015
2 PWR CPR-1000 Operational 1000 23 December 2010 15 July 2016
3 PWR Hualong-1 Under construction 1000 24 December 2015 (2022)
4 PWR Hualong-1 Under construction 1000 23 December 2016
5 PWR Hualong-1 Planned 1117
6 PWR Hualong-1 Planned 1117
Fangjiashan 1 PWR CPR-1000 Operational 1012 26 December 2008 15 December 2014
2 PWR CPR-1000 Operational 1012 17 July 2009 12 February 2015
Fuqing 1 PWR CPR-1000 Operational 1000 21 November 2008 19 November 2014
2 PWR CPR-1000 Operational 1000 17 June 2009 15 October 2015
3 PWR CPR-1000 Operational 1000 31 December 2010 7 September 2016
4 PWR CPR-1000 Operational 1000 17 November 2012 31 July 2017
5 PWR Hualong-1 Operational 1000 15 April 2015 30 January 2021[15]
6 PWR Hualong-1 Under construction 1000 22 December 2015 (2021)
Haiyang 1 PWR AP-1000 Operational 1170 24 September 2009 23 October 2018[16]
2 PWR AP-1000 Operational 1170 20 June 2010 9 January 2019[17]
3 PWR CAP-1000 Planned 1100
4 PWR CAP-1000 Planned 1100
5 PWR CAP-1000 Planned 1100
6 PWR CAP-1000 Planned 1100
7 PWR CAP-1000 Planned 1100
8 PWR CAP-1000 Planned 1100
[18] 1 PWR CAP-1000 Planned 1100
2 PWR CAP-1000 Planned 1100
Hongyanhe I 1 PWR CPR-1000 Operational 1061 18 August 2007 6 June 2013
2 PWR CPR-1000 Operational 1061 28 March 2008 13 May 2014
3 PWR CPR-1000 Operational 1061 7 March 2009 23 March 2015
4 PWR CPR-1000 Operational 1061 15 August 2009 1 April 2016
5 PWR ACPR-1000 Operational 1061 29 March 2015 2 August 2021[19]
6 PWR ACPR-1000 Under construction 1061 24 July 2015 (2022)
[20] 1 PWR CAP-1000 Planned 1100
2 PWR CAP-1000 Planned 1100
3 PWR CAP-1000 Planned 1100
4 PWR CAP-1000 Planned 1100
5 PWR CAP-1000 Planned 1100
6 PWR CAP-1000 Planned 1100
Ling Ao I 1 PWR M-310 Operational 950 15 May 1997 28 May 2002
2 PWR M-310 Operational 950 28 November 1997 8 January 2003
3 PWR CPR-1000 Operational 1007 15 December 2005 15 September 2010
4 PWR CPR-1000 Operational 1007 15 June 2006 7 August 2011
1 PWR CAP-1000 Planned 1100
2 PWR CAP-1000 Planned 1100
3 PWR CAP-1000 Planned 1100
4 PWR CAP-1000 Planned 1100
5 PWR CAP-1000 Planned 1100
6 PWR CAP-1000 Planned 1100
Ningde I 1 PWR CPR-1000 Operational 1018 18 February 2008 15 April 2013
2 PWR CPR-1000 Operational 1018 12 November 2008 4 May 2014
3 PWR CPR-1000 Operational 1018 8 January 2010 10 June 2015
4 PWR CPR-1000 Operational 1018 29 September 2010 29 March 2016
5 PWR Hualong-1 Planned 1080
6 PWR Hualong-1 Planned 1080
1 PWR CAP-1000 Planned 1100
2 PWR CAP-1000 Planned 1100
3 PWR CAP-1000 Planned 1100
4 PWR CAP-1000 Planned 1100
Qinshan I-1 PWR CNP-300 Operational 308 20 March 1985 1 April 1994
II-1 PWR CNP-600 Operational 610 2 June 1996 15 April 2002
II-2 PWR CNP-600 Operational 610 1 April 1997 3 May 2004
II-3 PWR CNP-600 Operational 619 28 April 2006 5 October 2010
II-4 PWR CNP-600 Operational 619 28 January 2007 30 December 2011
III-1 PHWR CANDU-6 Operational 677 8 June 1998 31 December 2002
III-2 PHWR CANDU-6 Operational 677 25 September 1998 24 July 2003
[21] 1 PWR Hualong-1 Under construction[21] 1117 January 2021
2 PWR Hualong-1 Planned 1000
3 PWR Hualong-1 Planned 1000
4 PWR Hualong-1 Planned 1000
5 PWR Hualong-1 Planned 1000
6 PWR Hualong-1 Planned 1000
Sanmen 1 PWR AP-1000 Operational 1157 19 April 2009 21 September 2018[22]
2 PWR AP-1000 Operational 1157 15 December 2009 5 November 2018[23]
3 PWR CAP-1000 Planned 1100
4 PWR CAP-1000 Planned 1100
5 PWR CAP-1000 Planned 1100
6 PWR CAP-1000 Planned 1100
Shidaowan I-1 HTGR HTR-PM Operational 200 December 2012 20 December 2021[24]
II-1 PWR CAP-1400 Under construction 1400 19 June 2019
II-2 PWR CAP-1400 Under construction 1400 21 April 2020
II-3 PWR CAP-1000 Planned 1100
II-4 PWR CAP-1000 Planned 1100
II-5 PWR CAP-1000 Planned 1100
II-6 PWR CAP-1000 Planned 1100
Taipingling (Huizhou) 1 PWR Hualong-1 Under construction 1116 26 December 2019
2 PWR Hualong-1 Under construction 1116 2019[25]
3 PWR Hualong-1 Planned 1000
4 PWR Hualong-1 Planned 1000
5 PWR Hualong-1 Planned 1000
6 PWR Hualong-1 Planned 1000
Taishan 1 PWR EPR Operational 1660 18 November 2009 14 December 2018[26]
2 PWR EPR Operational 1660 15 April 2010 7 September 2019[27]
3 PWR EPR Planned 1660
4 PWR EPR Planned 1660
1 PWR CAP-1000 Planned 1100
2 PWR CAP-1000 Planned 1100
3 PWR CAP-1000 Planned 1100
4 PWR CAP-1000 Planned 1100
Tianwan 1 PWR VVER-1000 Operational 990 20 October 1999 17 May 2007
2 PWR VVER-1000 Operational 990 20 September 2000 16 August 2007
3 PWR VVER-1000 Operational 1045 27 December 2012 14 February 2018
4 PWR VVER-1000 Operational 1045 27 September 2013 22 December 2018[28]
5 PWR ACPR-1000 Operational 1000 27 December 2015 8 September 2020[29]
6 PWR ACPR-1000 Operational 1000 7 September 2016 3 June 2021
7 PWR VVER-1200 Under construction 1150 19 May 2021[30] (2027-2028)
8 PWR VVER-1200 Under construction 1150 19 May 2021 (2027-2028)
Xianning 1 PWR CAP-1000 Planned 1100
2 PWR CAP-1000 Planned 1100
3 PWR CAP-1000 Planned 1100
4 PWR CAP-1000 Planned 1100
5 PWR CAP-1000 Planned 1100
6 PWR CAP-1000 Planned 1100
Xiapu[31] I-1 SFR CFR-600 Under construction 642 2017 (2023)[32]
I-2 SFR CFR-600 Under construction[32] 642 27 December 2020[32]
II-1 PWR CAP-1000 Planned 1100
II-2 PWR CAP-1000 Planned 1100
II-3 PWR CAP-1000 Planned 1100
II-4 PWR CAP-1000 Planned 1100
II-5 PWR CAP-1000 Planned 1100
II-6 PWR CAP-1000 Planned 1100
Xudabao 1 PWR CAP-1000 Planned 1100
2 PWR CAP-1000 Planned 1100
3 PWR VVER V-491[20] Under construction 1150 19 May 2021[30] (2028)
4 PWR VVER V-491[20] Under construction 1150 19 May 2021 (2028)
5 PWR CAP-1000 Planned 1100
6 PWR CAP-1000 Planned 1100
Yangjiang 1 PWR CPR-1000 Operational 1000 16 December 2008 25 March 2014
2 PWR CPR-1000 Operational 1000 4 June 2009 8 June 2015
3 PWR CPR-1000+ Operational 1000 15 November 2010 1 January 2016
4 PWR CPR-1000+ Operational 1000 17 November 2012 15 March 2017
5 PWR ACPR-1000 Operational 1000 18 September 2013 12 July 2018[33]
6 PWR ACPR-1000 Operational 1000 23 December 2013 24 July 2019
Zhangzhou 1 PWR Hualong-1 Under construction 1126 16 October 2019[34]
2 PWR Hualong-1 Under construction 1126 2020[25]
3 PWR Hualong-1 Planned 1080
4 PWR Hualong-1 Planned 1080
5 PWR Hualong-1 Planned 1080
6 PWR Hualong-1 Planned 1080

Cuba[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Juragua 1 PWR VVER-440 V-318 Unfinished 1983 5 September 1992
2 PWR VVER-440 V-318 Unfinished 1985 5 September 1992

Czech Republic[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Dukovany 1 PWR VVER-440 V-213 Operational 468 1 January 1979 3 May 1985
2 PWR VVER-440 V-213 Operational 471 1 January 1979 21 March 1986
3 PWR VVER-440 V-213 Operational 468 1 March 1979 20 December 1986
4 PWR VVER-440 V-213 Operational 471 1 March 1979 19 July 1987
5 PWR ? Planned
Temelín 1 PWR VVER-1000 Operational 1003 1 February 1987 10 June 2002
2 PWR VVER-1000 Operational 1003 1 February 1987 18 April 2003
3 PWR VVER or AP1000 Planned
4 PWR VVER or AP1000 Planned

Egypt[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
El Dabaa 1 PWR VVER-1200 Planned 1200 (2021)[35] (2026)
2 PWR VVER-1200 Planned 1200
3 PWR VVER-1200 Planned 1200
4 PWR VVER-1200 Planned 1200

Finland[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Hanhikivi 1 PWR VVER-1200/V-491 Planned 1200
Loviisa 1 PWR VVER-440/V-213 Operational 496 1 May 1971 9 May 1977
2 PWR VVER-440/V-213 Operational 496 1 August 1972 5 January 1981
Olkiluoto 1 BWR ASEA-III, BWR-2500 Operational 880 1 February 1974 10 October 1979
2 BWR ASEA-III, BWR-2500 Operational 880 1 November 1975 10 July 1982
3 PWR EPR Under construction 1600 12 August 2005 (January 2022[36])

France[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Belleville 1 PWR P4 REP 1300 Operational 1310 1 May 1980 1 June 1988
2 PWR P4 REP 1300 Operational 1310 1 August 1980 1 January 1989
Blayais 1 PWR CP1 Operational 910 1 January 1977 1 December 1981
2 PWR CP1 Operational 910 1 January 1977 1 February 1983
3 PWR CP1 Operational 910 1 April 1978 14 November 1983
4 PWR CP1 Operational 910 1 April 1978 1 October 1983
Brennilis 1 HWGCR Shut down/in decommissioning 70 1 July 1962 1 June 1968 31 July 1985
Bugey 1 GCR UNGG Shut down 540 1 December 1965 1 July 1972 27 May 1994
2 PWR CP0 Operational 910 1 November 1972 1 March 1979
3 PWR CP0 Operational 910 1 September 1973 1 March 1979
4 PWR CP0 Operational 880 1 June 1974 1 July 1979
5 PWR CP0 Operational 880 1 July 1974 3 January 1980
Cattenom 1 PWR P4 REP 1300 Operational 1300 29 October 1979 1 April 1987
2 PWR P4 REP 1300 Operational 1300 28 July 1980 1 February 1988
3 PWR P4 REP 1300 Operational 1300 15 June 1982 1 February 1991
4 PWR P4 REP 1300 Operational 1300 28 September 1983 1 January 1992
Chinon A-1 GCR UNGG Shut down 70 1 February 1957 1 February 1964 16 April 1973
A-2 GCR UNGG Shut down 180 1 August 1959 24 February 1965 14 June 1985
A-3 GCR UNGG Shut down 360 1 March 1961 4 August 1966 15 June 1990
B-1 PWR CP2 Operational 905 1 March 1977 1 February 1984
B-2 PWR CP2 Operational 905 1 March 1977 1 August 1984
B-3 PWR CP2 Operational 905 1 October 1980 4 March 1987
B-4 PWR CP2 Operational 905 1 February 1981 1 April 1988
Chooz A-1 PWR CHOOZ-A Shut down/dismantled 305 1 January 1962 15 April 1967 30 October 1991
B-1 PWR N4 REP 1450 Operational 1500 1 January 1984 15 May 2000
B-2 PWR N4 REP 1450 Operational 1500 1 January 1984 15 May 2000
Civaux 1 PWR N4 REP 1450 Operational 1495 15 October 1988 29 January 2002
2 PWR N4 REP 1450 Operational 1495 1 April 1991 23 April 2002
Cruas 1 PWR CP2 Operational 915 1 August 1978 2 April 1984
2 PWR CP2 Operational 915 15 November 1978 1 April 1985
3 PWR CP2 Operational 915 15 April 1979 10 September 1984
4 PWR CP2 Operational 915 1 October 1979 11 February 1985
Dampierre 1 PWR CP1 Operational 890 1 February 1975 10 September 1980
2 PWR CP1 Operational 890 1 April 1975 16 February 1981
3 PWR CP1 Operational 890 1 September 1975 27 May 1981
4 PWR CP1 Operational 890 1 December 1975 20 November 1981
Fessenheim 1 PWR CP0 Shut down 880 1 September 1971 1 January 1978 22 February 2020
2 PWR CP0 Shut down 880 1 February 1972 1 April 1978 30 June 2020
Flamanville 1 PWR P4 REP 1300 Operational 1330 1 December 1979 1 December 1986
2 PWR P4 REP 1300 Operational 1330 1 May 1980 9 March 1987
3 PWR EPR Under construction 1600 3 December 2007 (2023)[37]
Golfech 1 PWR P4 REP 1300 Operational 1310 17 November 1982 1 February 1991
2 PWR P4 REP 1300 Operational 1310 1 October 1984 4 March 1994
Gravelines 1 PWR CP1 Operational 910 1 February 1975 25 November 1980
2 PWR CP1 Operational 910 1 March 1975 1 December 1980
3 PWR CP1 Operational 910 1 December 1975 1 June 1981
4 PWR CP1 Operational 910 1 April 1976 1 October 1981
5 PWR CP1 Operational 910 1 October 1979 15 January 1985
6 PWR CP1 Operational 910 1 October 1979 25 October 1985
Phénix 1 FBR PH-250 Shut down 130 1 November 1968 14 July 1974 1 February 2010
Nogent 1 PWR P4 REP 1300 Operational 1310 26 May 1981 24 February 1988
2 PWR P4 REP 1300 Operational 1310 1 January 1982 1 May 1989
Paluel 1 PWR P4 REP 1300 Operational 1330 15 August 1977 1 December 1985
2 PWR P4 REP 1300 Operational 1330 1 January 1978 1 December 1985
3 PWR P4 REP 1300 Operational 1330 1 February 1979 1 February 1986
4 PWR P4 REP 1300 Operational 1330 1 February 1980 1 June 1986
Penly 1 PWR P4 REP 1300 Operational 1330 1 September 1982 1 December 1990
2 PWR P4 REP 1300 Operational 1330 1 August 1984 1 November 1992
Saint-Alban 1 PWR P4 REP 1300 Operational 1335 29 January 1979 1 May 1986
2 PWR P4 REP 1300 Operational 1335 31 July 1979 1 March 1987
Saint-Laurent A-1 GCR UNGG Shut down 390 1 October 1963 1 June 1969 18 April 1990
A-2 GCR UNGG Shut down 465 1 January 1966 1 November 1971 27 May 1992
B-1 PWR CP2 Operational 915 1 May 1976 1 August 1983
B-2 PWR CP2 Operational 915 1 July 1976 1 August 1983
Superphénix 1 FBR Na-1200 Shut down/in decommissioning 1200 13 December 1976 1 December 1986 31 December 1998
Tricastin 1 PWR CP1 Operational 915 1 November 1974 1 December 1980
2 PWR CP1 Operational 915 1 December 1974 1 December 1980
3 PWR CP1 Operational 915 1 April 1975 11 May 1981
4 PWR CP1 Operational 915 1 May 1975 1 November 1981

Germany[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
AVR 1 HTGR Pebble bed reactor prototype Shut down 13 1 August 1961 19 May 1969 31 December 1988
Biblis 1 PWR Type Siemens-KWU Shut downa/in decommissioning 1167 1 January 1970 26 February 1975 6 August 2011
2 PWR KWU Shut downa/in decommissioning 1240 1 February 1972 31 January 1977 6 August 2011
Brokdorf 1 PWR KWU Operational 1410 1 January 1976 22 December 1986 (31 December 2021)
Brunsbüttel 1 BWR BWR-69 Shut downa 771 15 April 1970 9 February 1977 6 August 2011
Emsland 1 PWR Konvoi (KWU) Operational 1329 10 August 1982 20 June 1988 (31 December 2022)
Grafenrheinfeld 1 PWR KWU Shut down 1275 1 January 1975 17 June 1982 27 June 2015
Greifswald 1 PWR VVER-440 V-230 Shut down/in decommissioning 408 1 March 1970 12 July 1974 14 February 1990
2 PWR VVER V-230 Shut down/in decommissioning 408 1 March 1970 16 April 1975 14 February 1990
3 PWR VVER V-230 Shut down/in decommissioning 408 1 April 1972 1 May 1978 28 February 1990
4 PWR VVER V-230 Shut down/in decommissioning 408 1 April 1972 1 November 1979 22 July 1990
5 PWR VVER V-213 Shut down/in decommissioning 408 1 December 1976 1 November 1989 24 November 1989
6 PWR VVER V-213 Finished; never entered service 408
Grohnde 1 PWR KWU Operational 1360 1 June 1976 1 February 1985 (31 December 2021)
Grosswelzheim 1 BWR Superheated steam reactor Shut down/dismantled 25 1 January 1965 2 August 1970 20 April 1971
Gundremmingen A BWR GE, BWR-1 Shut down/in decommissioning 237 12 December 1962 12 April 1967 13 January 1977
B BWR BWR-72 (KWU) Shut down[38] 1284 20 July 1976 19 July 1984 31 December 2017
3 BWR BWR-72 (KWU) Operational 1288 20 July 1976 18 January 1985 (31 December 2021)
Isar 1 BWR BWR-69 Shut downa 878 1 May 1972 21 March 1979 6 August 2011
2 PWR Konvoi (KWU) Operational 1410 15 September 1982 9 April 1988 (31 December 2022)
Kahl 1 BWR BWR Shut down/dismantled 15 1 July 1958 1 February 1962 25 November 1985
SNR-300 1 FBR Finished; never entered service 1972 1985
KNK II 1 FBR Shut down 17 1 September 1974 3 March 1979 23 August 1991
Krümmel 1 BWR BWR-69 (KWU) Shut downa 1346 5 April 1974 28 March 1984 6 August 2011
Lingen 1 BWR BWR with fossil fuel-fired superheater Shut down 183 1 October 1964 1 October 1968 5 January 1977
Mülheim-Kärlich 1 PWR B & W Shut down/in decommissioning 1219 15 January 1975 8 August 1987 9 September 1988
MZFR 1 PHWR Heavy water-cooled pressure vessel reactor Shut down 52 1 December 1961 19 December 1966 3 May 1984
Neckarwestheim 1 PWR KWU Shut downa 785 1 February 1972 1 December 1976 6 August 2011
2 PWR Konvoi (KWU) Operational 1310 9 November 1982 15 April 1989 (31 December 2022)
Niederaichbach 1 HWGCR Pressure tube reactor Shut down/decommissioned 100 1 June 1966 1 January 1973 31 July 1974
Obrigheim 1 PWR Siemens Shut down/in decommissioning 340 15 March 1965 31 March 1969 11 May 2005
Philippsburg 1 BWR BWR-69 Shut downa 890 1 October 1970 26 March 1980 6 August 2011
2 PWR KWU Shut down[39] 1402 7 July 1977 18 April 1985 31 December 2019
Rheinsberg 1 PWR VVER-70 Shut down/in decommissioning 62 1 January 1960 11 October 1966 1 June 1990
Stade 1 PWR Siemens Shut down/in decommissioning 640 1 December 1967 19 May 1972 4 November 2003
Stendal 1 PWR VVER-1000/320 Unfinished 1983 1990
2 PWR VVER-1000/320 Unfinished 1983 1990
3 PWR VVER-1000/320 Never built
4 PWR VVER-1000/320 Never built
THTR-300 1 HTGR Pebble bed reactor Shut down 296 3 May 1971 1 June 1987 29 September 1988
Unterweser 1 PWR KWU Shut downa/in decommissioning 1345 1 July 1972 6 September 1979 6 August 2011
1 BWR BWR-69 (AEG) Shut down/in decommissioning 640 26 January 1968 11 November 1975 26 August 1994
Notes:
^a Post-Fukushima shutdown of eight reactors. On 15 March 2011, the German Government decided to close seven nuclear power plants built before 1980 along with the Krümmel nuclear power plant for a duration of three months.[40] The temporary shutdown was changed into permanent shutdown by the German parliament on 30 June 2012. The remaining nine plants that stayed operational were given new decommissioning dates.[41]

Hungary[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Paks 1 PWR VVER-440 V-213 Operational 470 1 August 1974 10 August 1983
2 PWR VVER V-213 Operational 473 1 August 1974 14 November 1984
3 PWR VVER V-213 Operational 473 1 October 1979 1 December 1986
4 PWR VVER V-213 Operational 471 1 October 1979 1 November 1987
5 PWR VVER-1200 Planned 1114 (2023)[citation needed]
6 PWR VVER-1200 Planned 1114 (2025)

The modernization of the four reactors was finally ended at 2009, so the plant's total power generation reached 2000 MWe.

India[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
[42] 1 PHWR IPHWR-700 Planned 630
2 PHWR IPHWR-700 Planned 630
3 PHWR IPHWR-700 Planned 630
4 PHWR IPHWR-700 Planned 630
Chutka[43] 1 PHWR IPHWR-700 Planned 630
2 PHWR IPHWR-700 Planned 630
Gorakhpur 1 PHWR IPHWR-700 Under construction 630 (2019)[44]
2 PHWR IPHWR-700 Under construction 630
3 PHWR IPHWR-700 Planned 630
4 PHWR IPHWR-700 Planned 630
Jaitapur 1 PWR EPR Planned 1600
2 PWR EPR Planned 1600
3 PWR EPR Planned 1600
4 PWR EPR Planned 1600
5 PWR EPR Planned 1600
6 PWR EPR Planned 1600
Kaiga 1 PHWR IPHWR-220[45] Operational 202 1 September 1989 16 November 2000
2 PHWR IPHWR-220[45] Operational 202 1 December 1989 16 March 2000
3 PHWR IPHWR-220[45] Operational 202 30 March 2002 6 May 2007
4 PHWR IPHWR-220[45] Operational 202 10 May 2002 20 January 2011
5 PHWR IPHWR-700 Planned 630
6 PHWR IPHWR-700 Planned 630
Kakrapar 1 PHWR IPHWR-220[45] Operational 202 1 December 1984 6 May 1993
2 PHWR IPHWR-220[45] Operational 202 1 April 1985 1 September 1995
3 PHWR IPHWR-700[46] Operational 630 22 November 2010 5 May 2020
4 PHWR IPHWR-700[46] Under construction 630 22 November 2010
Kovvada 1 PWR AP-1000[47] Planned 1100
2 PWR AP-1000 Planned 1100
3 PWR AP-1000 Planned 1100
4 PWR AP-1000 Planned 1100
5 PWR AP-1000 Planned 1100
6 PWR AP-1000 Planned 1100
[48] 1 PWR VVER-1000 Planned 917
2 PWR VVER-1000 Planned 917
3 PWR VVER-1000 Planned 917
4 PWR VVER-1000 Planned 917
5 PWR VVER-1000 Planned 917
6 PWR VVER-1000 Planned 917
Kudankulam 1 PWR VVER-1000 Operational 932 31 March 2002 31 December 2014
2 PWR VVER-1000 Operational 932 4 July 2002 31 March 2017
3 PWR VVER-1000 Under construction 917 30 June 2017
4 PWR VVER-1000 Under construction 917 23 October 2017
5 PWR VVER-1000 Under construction 917 29 June 2021
6 PWR VVER-1000 Under construction 917 20 December 2021[49]
Madras 1 PHWR IPHWR-220[45] Operational 205 1 January 1971 27 January 1984
2 PHWR IPHWR-220[45] Operational 205 1 October 1972 21 March 1986
1 PHWR IPHWR-700 Planned 630
2 PHWR IPHWR-700 Planned 630
3 PHWR IPHWR-700 Planned 630
4 PHWR IPHWR-700 Planned 630
Narora 1 PHWR IPHWR-220[45] Operational 202 1 December 1976 1 January 1991
2 PHWR IPHWR-220[45] Operational 202 1 November 1977 1 July 1992
PFBR 1 FBR Prototype Under construction 470 23 October 2004
Rajasthan 1 PHWR CANDU[45] Shut down 90 1 August 1965 16 December 1973 October 2004[50]
2 PHWR CANDU[45] Operational 187 1 April 1968 1 April 1981
3 PHWR IPHWR-220[45] Operational 202 1 February 1990 1 June 2000
4 PHWR IPHWR-220[45] Operational 202 1 October 1990 23 December 2000
5 PHWR IPHWR-220[45] Operational 202 18 September 2002 4 February 2010
6 PHWR IPHWR-220[45] Operational 202 20 January 2003 31 March 2010
7 PHWR IPHWR-700[46] Under construction 630 18 July 2011
8 PHWR IPHWR-700[46] Under construction 630 30 September 2011
Tarapur 1 BWR BWR-1, Mark 1 Operational 150 1 October 1964 28 October 1969
2 BWR BWR-1, Mark 1 Operational 150 1 October 1964 28 October 1969
3 PHWR IPHWR-540 Operational 490 12 May 2000 18 August 2006
4 PHWR IPHWR-540 Operational 490 8 March 2000 12 September 2005

Indonesia[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Muria 1 PWR VVER-1200 Planned 1150 (2040)
2 PWR VVER-1200 Planned 1150 (2040)
3 PWR VVER-1200 Planned 1150 (2040)
4 PWR VVER-1200 Planned 1150 (2040)
Bangka Belitung 1 PWR VVER-1200 Planned 1150 (2040)
2 PWR VVER-1200 Planned 1150 (2040)

Iran[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Bushehr 1 PWR VVER-1000 Operational 915 1 May 1975 23 September 2013
2 PWR VVER-1000 Under construction 915 27 September 2019
3 PWR VVER-1000 Planned 915
4 PWR VVER-1000 Planned 915
5 PWR VVER-1000 Planned 915
Darkhovin 1 PWR Unfinished; restart planned 280

Italy[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Caorso 1 BWR BWR-4 Mark2 Shut down 860 1 January 1970 1 December 1981 1 July 1990
Enrico Fermi 1 PWR WH 4-loop Shut down/in decommissioning 260 1 July 1961 1 January 1965 1 July 1990
Garigliano 1 BWR BWR-1 Shut down/in decommissioning 150 1 November 1959 1 June 1964 1 March 1982
Latina 1 GCR MAGNOX Shut down/in decommissioning 153 1 November 1958 1 January 1964 1 December 1987
Alto Lazio 1 BWR Unfinished 982 1 July 1982 1 January 1988
2 BWR Unfinished 982 1 July 1982 1 July 1988

Japan[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Fugen 1 HWLWR ATR Shut down 148 10 May 1972 20 March 1979 29 March 2003
Fukushima Daiichi 1 BWR BWR-3 Inoperable 439 25 July 1967 26 March 1971 19 May 2011
2 BWR BWR-4 Inoperable 760 9 June 1969 18 July 1974 19 May 2011
3 BWR BWR-4 Inoperable 760 28 December 1970 27 March 1976 19 May 2011
4 BWR BWR-4 Shut down/Inoperable 760 12 February 1973 12 October 1978 19 May 2011
5 BWR BWR-4 Shut down 760 22 May 1972 18 April 1978 17 December 2013
6 BWR BWR-5 Shut down 1067 26 October 1973 24 October 1979 17 December 2013
Fukushima Daini 1 BWR BWR-5 Shut down 16 March 1976 20 April 1982 30 September 2019
2 BWR BWR-5 Shut down 1067 25 May 1979 3 February 1984 30 September 2019
3 BWR BWR-5 Shut down 1067 23 March 1981 21 June 1985 30 September 2019
4 BWR BWR-5 Shut down 1067 28 May 1981 25 August 1987 30 September 2019
Genkai 1 PWR Mitsubishi (2-loop) Shut down 529 15 September 1971 15 October 1975 27 April 2015
2 PWR Mitsubishi (2-loop) Shut down 529 1 February 1977 30 March 1981 9 April 2019
3 PWR Mitsubishi (4-loop) Operational 1127 1 June 1988 18 March 1994
4 PWR Mitsubishi (4-loop) Operational[51] 1127 15 July 1992 25 July 1997
Hamaoka 1 BWR BWR-4 Shut down 515 10 June 1971 17 March 1976 30 January 2009
2 BWR BWR-4 Shut down 806 14 June 1974 29 November 1978 30 January 2009
3 BWR BWR-5 Operation suspended
(under review)[52]
1056 18 April 1983 28 August 1987
4 BWR BWR-5 Operation suspended
(under review)[52]
1092 13 October 1989 3 September 1993
5 BWR ABWR Operation suspended 1325 12 July 2000 18 January 2005
Higashidōri 1 BWR BWR-5 Operation suspended
(under review)[52]
1067 7 November 2000 8 December 2005
2 BWR ABWR Planned
3 BWR ABWR Planned
Ikata 1 PWR Mitsubishi (2-loop) Shut down 538 1 September 1973 30 September 1977 25 March 2016
2 PWR Mitsubishi (2-loop) Shut down 538 1 August 1978 19 March 1982 27 March 2018
3 PWR Mitsubishi (3-loop) Operational 846 1 October 1990 15 December 1994
Kaminoseki 1 BWR ABWR Planned
2 BWR ABWR Planned
Kashiwazaki-Kariwa 1 BWR BWR-5 Operation suspended 1067 5 June 1980 18 September 1985
2 BWR BWR-5 Operation suspended 1067 18 November 1985 28 September 1990
3 BWR BWR-5 Operation suspended 1067 7 March 1989 11 August 1993
4 BWR BWR-5 Operation suspended 1067 5 March 1990 11 August 1994
5 BWR BWR-5 Operation suspended 1067 20 June 1985 10 April 1990
6 BWR ABWR Operation suspended
(restart approved)[53]
1315 3 November 1992 7 November 1996
7 BWR ABWR Operation suspended
(restart approved)[53]
1315 1 July 1993 2 July 1997
Mihama 1 PWR Mitsubishi (2-loop) Shut down 320 1 February 1967 28 November 1970 March 2015
2 PWR Mitsubishi (2-loop) Shut down 470 29 May 1968 25 July 1972 March 2015
3 PWR Mitsubishi (3-loop) Operational[54] 780 7 August 1972 1 December 1976
Monju 1 FBR - Shut down 246 10 May 1986 29 August 1995 5 December 2017
Ōi 1 PWR W (4-loop) Shut down 1120 26 October 1972 27 March 1979 December 2017
2 PWR Westinghouse (4-loop) Shut down 1120 8 December 1972 5 December 1979 December 2017
3 PWR Mitsubishi (4-loop) Operational 1127 3 October 1987 18 December 1991
4 PWR Mitsubishi (4-loop) Operational[55] 1127 13 June 1988 2 February 1993
Ōma 1 BWR ABWR Under construction 1325 7 May 2010
Onagawa 1 BWR BWR-4 Shut down 498 8 July 1980 1 June 1984 21 December 2018
2 BWR BWR-5 Operation suspended
(restart approved)[56]
796 12 April 1991 28 July 1995
3 BWR BWR-5 Operation suspended 796 23 January 1998 30 January 2002
Sendai 1 PWR M (3-loop) Operational 846 15 December 1979 4 July 1984
2 PWR Mitsubishi (3-loop) Operational 846 12 October 1981 28 November 1985
3 PWR Mitsubishi APWR Planned
Shika 1 BWR BWR-5 Operation suspended 505 1 July 1989 30 July 1993
2 BWR ABWR Operation suspended
(under review)[52]
1108 20 August 2001 15 March 2006
Shimane 1 BWR BWR-3 Shut down 439 2 July 1970 29 March 1974 March 2015
2 BWR BWR-5 Operation suspended
(restart approved)[52]
789 2 February 1985 10 February 1989
3 BWR ABWR Under construction 1325 12 October 2007
Takahama 1 PWR Mitsubishi (3-loop) Operation suspended
(restart approved)[53]
780 25 April 1970 14 November 1974
2 PWR Mitsubishi (3-loop) Operation suspended
(restart approved)[53]
780 9 March 1971 14 November 1975
3 PWR Mitsubishi (3-loop) Operational 830 12 December 1980 17 January 1985
4 PWR Mitsubishi (3-loop) Operational 830 19 March 1981 5 June 1985
Tōkai 1 GCR MAGNOX Shut down 137 1 March 1961 25 July 1966 31 March 1998
2 BWR BWR-5 Operation suspended
(restart approved)[57]
1060 3 October 1973 28 November 1978
Tomari 1 PWR Mitsubishi (2-loop) Operation suspended
(under review)[52]
550 18 April 1985 22 June 1989
2 PWR Mitsubishi (2-loop) Operation suspended
(under review)[52]
550 13 June 1985 12 April 1991
3 PWR Mitsubishi (3-loop) Operation suspended
(under review)[52]
866 18 November 2004 22 December 2009
Tsuruga 1 BWR BWR-2 Shut down 340 24 November 1966 14 March 1970 March 2015
2 PWR Mitsubishi (4-loop) Operation suspended
(under review)[52]
1108 6 November 1982 17 February 1987
3 PWR Mitsubishi APWR Planned
4 PWR Mitsubishi APWR Planned

Kazakhstan[]

Name Unit
No.
Reactor Status Capacity in MW Construction start Commercial operation Closure
Type Model Net Gross
1 SFR BN-350 Shut down 135 1964 1973 1999

Lithuania[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Ignalina 1 LWGR RBMK-1500 Shut down/in decommissioning 1185 1 May 1977 1 May 1985 31 December 2004
2 LWGR RBMK-1500 Shut down/in decommissioning 1185 1 January 1978 1 December 1987 31 December 2009
3 LWGR RBMK-1500 Unfinished 1185
4 LWGR RBMK-1500 Never built 1185

Mexico[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Laguna Verde 1 BWR BWR-5 Operational 665 1 October 1976 29 July 1990
2 BWR BWR-5 Operational 665 1 June 1977 10 April 1995

Netherlands[]

Name Unit
No.
Reactor Status Capacity in MW Construction start Commercial operation Closure
Type Model Net Gross
Borssele 1 PWR KWU - PWR Operational 482 515 1 July 1969 26 October 1973 (26 October 2033)
Dodewaard 1 BWR BWR-2 Shut down 55 60 1 May 1965 26 March 1969 26 March 1997

North Korea[]

Name Unit
No.
Reactor Status Capacity in MW Construction start Commercial operation Closure
Type Model Net Gross
Yongbyon 1 GCR Magnox (Pu-production) Shut down[citation needed] 5[citation needed] 1994
2 LWR[58] Planned[58] 30
Taechon 1 Unfinished 200 1994
Kumho 1 PWR Unfinished 1,000 2003
2 PWR Unfinished 1,000 2003

Pakistan[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Chashma 1 PWR CNP-300 Operational 300 1 August 1993 15 September 2000
2 PWR CNP-300 Operational 300 28 December 2005 18 May 2011
3 PWR CNP-300 Operational 315 28 May 2011 15 October 2016
4 PWR CNP-300 Operational 315 18 December 2011 1 July 2017
5 PWR Hualong-1 Planned 1080
Karachi 1 PHWR CANDU-137 MW Shut Down 90 1 August 1966 7 December 1972 1 August 2021
2 PWR Hualong-1 Operational 1080 23 May 2013 19 March 2021[59]
3 PWR Hualong-1 Under construction 1080 21 August 2015 (2022)

Philippines[]

Name Unit
No.
Reactor Status Capacity in MW Construction start Commercial operation Closure
Type Model Net Gross
Bataan 1 PWR Westinghouse Finished; never entered service 621 1976 1986

Poland[]

Name Unit
No.
Reactor Status Capacity in MW Construction start Commercial operation Closure
Type Model Net Gross
Żarnowiec 1 PWR VVER-440 Unfinished 440 31 March 1982 4 September 1990
2 PWR VVER-440 Unfinished 440 31 March 1982 4 September 1990
3 PWR VVER-440 Never built 440 4 September 1990
4 PWR VVER-440 Never built 440 4 September 1990
Choczewo[60] 1 ? ? Planned 1500 (2026) (2033)[61]
2 ? ? Planned 1500 (2033-2040)[61]
3 ? ? Planned 1500 (2033-2040)[61]
4 ? ? Planned 1500 (2033-2040)[61]
5 ? ? Planned 1500 (2033-2040)[61]
6 ? ? Planned 1500 (2040)[61]
Synthos Oświęcim 1 SMR GE Hitachi Planned 1500 (2027)[61]

Romania[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Cernavodă 1 PHWR CANDU-6 Operational 650 1 July 1982 2 December 1996
2 PHWR CANDU-6 Operational 650 1 July 1983 31 October 2007
3 PHWR CANDU-6 Unfinished; restart planned 650
4 PHWR CANDU-6 Unfinished; restart planned 650
5 PHWR CANDU-6 Unfinished 650

Russia[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Akademik Lomonosov 1 PWR KLT-40S Operational 32 15 April 2007 19 December 2019[62]
2 PWR KLT-40S Operational 32 15 April 2007 19 December 2019
Balakovo 1 PWR VVER-1000 Operational 950 1 December 1980 23 May 1986
2 PWR VVER-1000 Operational 950 1 August 1981 18 January 1988
3 PWR VVER-1000 Operational 950 1 November 1982 8 April 1989
4 PWR VVER-1000 Operational 950 1 April 1984 22 December 1993
5 PWR VVER-1000 Unfinished 950 28 December 1992
6 PWR VVER-1000 Unfinished 950 28 December 1992
1 PWR VVER-1000 Unfinished 1980 1991
2 PWR VVER-1000 Unfinished 1980 1991
3 PWR VVER-1000 Unfinished 1980 1991
4 PWR VVER-1000 Unfinished 1980 1991
Beloyarsk 1 LWGR AMB-100 Shut down 102 1 June 1958 26 April 1964 1 January 1983
2 LWGR AMB-200 Shut down 146 1 January 1962 1 December 1969 1 January 1990
3 SFR BN-600 Operational 560 1 January 1969 1 November 1981
4 SFR BN-800 Operational 789 18 July 2006 10 December 2015
5 SFR BN-1200 Planned 1100
Bilibino 1 LWGR EGP-6 Shut down 11 1 January 1970 1 April 1974 14 January 2019
2 LWGR EGP-6 Operational 11 1 January 1970 1 February 1975
3 LWGR EGP-6 Operational 11 1 January 1970 1 February 1976
4 LWGR EGP-6 Operational 11 1 January 1970 1 January 1977
1 FBR SVBR-100 Planned 90
1 PWR AST-500 Unfinished 1982 1993
2 PWR AST-500 Unfinished 1982 1993
Kalinin 1 PWR VVER-1000 Operational 950 1 February 1977 12 June 1985
2 PWR VVER-1000 Operational 950 1 February 1982 3 March 1987
3 PWR VVER-1000 Operational 950 1 October 1985 8 November 2005
4 PWR VVER-1000 Operational 950 1 August 1986 25 December 2012
Kaliningrad 1 PWR VVER-1200 Under construction
(suspended)[63]
1109 22 February 2012
2 PWR VVER-1200 Planned 1109
Kola 1 PWR VVER-440 V-230 Operational 441 1 May 1970 28 December 1973
2 PWR VVER-440 V-230 Operational 441 1 May 1970 21 February 1975
3 PWR VVER-440 V-213 Operational 441 1 April 1977 3 December 1982
4 PWR VVER-440 V-213 Operational 441 1 August 1976 6 December 1984
[63][64] 1 PWR VVER-S-600 Planned (600) (2028) (2034)
2 PWR VVER-S-600 Planned (600) (2028) (2034)
[63][65] 1 PWR VVER-1200 Unfinished; restart planned 1300 1979 1990
2 PWR VVER-1200 Unfinished; restart planned 1300 1979 1990
3 PWR VVER-1200 Unfinished; restart planned 1300 1979 1990
4 PWR VVER-1200 Unfinished; restart planned 1300 1979 1990
5 LWGR RBMKP-2400 Unfinished 1986 1986
6 LWGR RBMKP-2400 Unfinished 1986 1986
Kursk 1 LWGR RBMK-1000 Shut down 925 1 June 1972 12 October 1977 19 December 2021
2 LWGR RBMK-1000 Operational 925 1 January 1973 17 August 1979
3 LWGR RBMK-1000 Operational 925 1 April 1978 30 March 1984
4 LWGR RBMK-1000 Operational 925 1 May 1981 5 February 1986
5 LWGR RBMK-1000 Unfinished/In state of conservation 925 1 December 1985 2012
6 LWGR RBMK-1000 Unfinished 925 1 August 1986
Kursk II 1 PWR VVER-TOI Under construction 1115 29 April 2018
2 PWR VVER-TOI Under construction 1115 15 April 2019[66]
3 PWR VVER-TOI Planned 1115
4 PWR VVER-TOI Planned 1115
Leningrad 1 LWGR RBMK-1000 Shut down 925 1 March 1970 1 November 1974 21 December 2018[67]
2 LWGR RBMK-1000 Shut down 925 1 June 1970 11 February 1976 10 November 2020
3 LWGR RBMK-1000 Operational 925 1 December 1973 29 June 1980
4 LWGR RBMK-1000 Operational 925 1 February 1975 29 August 1981
Leningrad II 1 PWR VVER-1200 Operational 1085 25 October 2008 29 October 2018
2 PWR VVER-1200 Operational 1085 15 April 2010 22 March 2021[68]
3 PWR VVER-1200[69] Planned 1085
4 PWR VVER-1200[69] Planned 1085
MPEB #1[70][71] 1 PWR RITM-200S Planned 53 (2027)
2 PWR RITM-200S Planned 53 (2027)
MPEB #2[70][71] 1 PWR RITM-200S Planned 53 (2027)
2 PWR RITM-200S Planned 53 (2027)
MPEB #3[70][71] 1 PWR RITM-200S Planned 53 (2028)
2 PWR RITM-200S Planned 53 (2028)
MPEB #4[70][71] 1 PWR RITM-200S Planned 53 (2031)
2 PWR RITM-200S Planned 53 (2031)
1 PWR VVER-1200 Planned 1300
2 PWR VVER-1200 Planned 1300
3 PWR VVER-1200 Planned 1300
4 PWR VVER-1200 Planned 1300
Novovoronezh 1 PWR VVER-440 V-120 Shut down 197 1 July 1957 31 December 1964 16 February 1988
2 PWR VVER-440 V-120 Shut down 336 1 June 1964 14 April 1970 29 August 1990
3 PWR VVER-440 V-179 Shut down 385 1 July 1967 29 June 1972 25 December 2016
4 PWR VVER 440 V-179 Operational 385 1 July 1967 24 March 1973
5 PWR VVER-1000 Operational 950 1 March 1974 20 February 1981
Novovoronezh II 1 PWR VVER-1200 Operational 1114 24 June 2008 27 February 2017
2 PWR VVER-1200 Operational 1114 12 July 2009 6 November 2019
3 PWR VVER-1200 Planned 1175
4 PWR VVER-1200 Planned 1175
Obninsk 1 LWGR AM-1 Shut down 5 1 January 1951 1 December 1954 29 April 2002
Rostov 1 PWR VVER-1000 Operational 950 1 September 1981 25 December 2001
2 PWR VVER-1000 Operational 950 1 May 1983 10 December 2010
3 PWR VVER-1000 Operational 950 15 September 2009 27 December 2014
4 PWR VVER-1000 Operational 1011 16 June 2010 28 September 2018
1 PWR RITM-200N Planned 45 (2024)[72] (2028)
2 PWR RITM-200N Planned 45 (2024) (2028)
1 FBR BREST-300 Under construction 280 8 June 2021[73] (2026)
1 FBR BN-1200 Unfinished; restart planned 1100 1982 1993
2 FBR BN-1200 Unfinished; restart planned 1100 1982 1993
3 FBR BN-1200 Unfinished; restart planned 1100 1982 1993
Smolensk 1 LWGR RBMK-1000 Operational 925 1 October 1975 30 September 1983
2 LWGR RBMK-1000 Operational 925 1 June 1976 2 July 1985
3 LWGR RBMK-1000 Operational 925 1 May 1984 12 October 1990
4 LWGR RBMK-1000 Unfinished 925
5 LWGR RBMK-1000 Unfinished 925
6 LWGR RBMK-1000 Unfinished 925
1 PWR VVER-TOI[69] Planned 1300
2 PWR VVER-TOI Planned 1300
3 PWR VVER-TOI Planned 1300
4 PWR VVER-TOI Planned 1300
1 PWR VVER-1200 Unfinished; restart planned 1300 1980 1990
2 PWR VVER-1200 Unfinished; restart planned 1300 1980 1990
3 PWR Unfinished 1980 1990
4 PWR Unfinished 1980 1990
1 PWR AST-500 Unfinished 9 January 1983 5 July 1990
2 PWR AST-500 Unfinished 9 January 1983 5 July 1990

Slovakia[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Bohunice A-1[74] HWGCR KS 150 Shut down/decommissioned 93 1 August 1958 25 December 1972 22 February 1977
1[75] PWR VVER-440 V-230 Shut down 408 24 April 1972 1 April 1980 31 December 2006
2 PWR VVER-440 V-230 Shut down 408 24 April 1972 1 January 1981 31 December 2008
3 PWR VVER-440 V-213 Operational 472 1 December 1976 14 February 1985 2045
4 PWR VVER-440 V-213 Operational 471 1 December 1976 18 December 1985 2045
Mochovce 1 PWR VVER-440 V-213 Operational 436 13 October 1983 29 October 1998 2058
2 PWR VVER-440 V-213 Operational 436 13 October 1983 11 April 2000 2060
3 PWR VVER-440 V-213+ Under construction 440 27 January 1987, restarted in 2009
4 PWR VVER-440 V-213+ Under construction 440 27 January 1987, restarted in 2009

Slovenia[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Krško 1 PWR Westinghouse (WH) 212 Operational 688 30 March 1975 1 January 1983 2043
2 PWR WH AP-1000, APR-1400 or EPR Planned 2027[76]

South Africa[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Koeberg 1 PWR CP-1 (France) Operational 930 1 July 1976 21 July 1984
2 PWR CP-1 (France) Operational 930 1 July 1976 9 November 1985
Thyspunt
or
Duynefontein
1 PWR VVER-1200 or CAP1400 Planned 1300
2 PWR VVER-1200 or CAP1400 Planned 1300
3 PWR VVER-1200 or CAP1400 Planned 1300
4 PWR VVER-1200 or CAP1400 Planned 1300
5 PWR VVER-1200 or CAP1400 Planned 1300
6 PWR VVER-1200 or CAP1400 Planned 1300
7 PWR VVER-1200 or CAP1400 Planned 1300
8 PWR VVER-1200 or CAP1400 Planned 1300
TBA 1 TBA TBA Bidding (Oct 2021) 2500

South Korea[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Hanbit 1 PWR Westinghouse F Operational 960 4 June 1981 25 August 1986
2 PWR WH F Operational 958 10 December 1981 10 June 1987
3 PWR OPR-1000 Operational 997 23 December 1989 31 March 1995
4 PWR OPR-1000 Operational 997 26 May 1990 1 January 1996
5 PWR OPR-1000 Operational 997 29 June 1997 21 May 2002
6 PWR OPR-1000 Operational 995 20 November 1997 24 December 2002
Hanul 1 PWR France CPI Operational 960 26 January 1983 10 September 1988
2 PWR France CPI Operational 962 5 July 1983 30 September 1989
3 PWR OPR-1000 Operational 994 21 July 1993 11 August 1998
4 PWR OPR-1000 Operational 998 1 November 1993 31 December 1999
5 PWR OPR-1000 Operational 996 1 October 1999 29 July 2004
6 PWR OPR-1000 Operational 996 29 September 2000 22 April 2005
Shin-Hanul 1 PWR APR-1400 Under construction 1340 10 July 2012
2 PWR APR-1400 Under construction 1340 19 July 2012
Kori 1 PWR WH 60 Shut down 576 27 April 1972 29 April 1978 18 June 2017
2 PWR WH F Operational 640 4 December 1977 25 July 1983
3 PWR WH F Operational 1011 1 October 1979 30 September 1985
4 PWR WH F Operational 1012 1 April 1980 29 April 1986
Shin-Kori 1 PWR OPR-1000 Operational 996 16 June 2006 28 February 2011
2 PWR OPR-1000 Operational 996 5 June 2007 20 July 2012
3 PWR APR-1400 Operational 1416 16 October 2008 15 January 2016
4 PWR APR-1400 Operational 1418 19 August 2009 29 August 2019[77]
5 PWR APR-1400 Under construction 1340 1 April 2017
6 PWR APR-1400 Under construction 1340 20 September 2018
Wolsong 1 PHWR CANDU-6 Shut down 657 30 October 1977 22 April 1983 24 December 2019
2 PHWR CANDU-6 Operational 655 22 June 1992 1 July 1997
3 PHWR CANDU-6 Operational 684 17 March 1994 1 July 1998
4 PHWR CANDU-6 Operational 688 22 July 1994 1 October 1999
Shin-Wolsong 1 PWR OPR-1000 Operational 991 20 November 2007 31 July 2012
2 PWR OPR-1000 Operational 960 23 September 2008 26 February 2015

Spain[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Almaraz 1 PWR Westinghouse 3 loops Operational 1011 3 July 1973 1 September 1983
2 PWR WH 3 loops Operational 1006 3 July 1973 1 July 1984
Ascó 1 PWR WH 3 loops Operational 995 16 May 1974 10 December 1984
2 PWR WH-3 loops Operational 997 7 March 1975 31 March 1986
Cofrentes 1 BWR BWR-6 Operational 1064 9 September 1975 11 March 1985
José Cabrera 1 PWR WH 1 loop Shut down/in decommissioning 141 24 June 1964 13 August 1969 30 April 2006
Lemoniz 1 PWR Unfinished 1972 1984
2 PWR Unfinished 1972 1984
Santa María de Garoña 1 BWR BWR-3 Shut down/in decommissioning 446 11 May 1971 15 February 1975 6 July 2013
Trillo 1 PWR KWU 3 loops Operational 1003 17 August 1979 6 August 1988
Valdecaballeros 1 BWR Unfinished 1975 1984
2 BWR Unfinished 1975 1984
Vandellòs 1 GCR Shut down/in decommissioning 480 1967 2 August 1972 31 July 1990
2 PWR WH 3 loops Operational 1045 29 December 1980 8 March 1988

Sweden[]


Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Ågesta 1 PHWR R3 Shut down/dismantled 10 1 December 1957 1 May 1964 2 June 1974
Barsebäck 1 BWR ASEA-II Shut down/in decommissioning 600 1 February 1971 1 July 1975 30 November 1999
2 BWR ASEA-II Shut down/in decommissioning 600 1 January 1973 1 July 1977 31 May 2005
Forsmark 1 BWR ASEA-III, BWR-2500 Operational 986 1 June 1973 10 December 1980
2 BWR ASEA-III, BWR-2500 Operational 1116 1 January 1975 7 July 1981
3 BWR ASEA-IV, BWR-3000 Operational 1167 1 January 1979 18 August 1985
Oskarshamn 1 BWR ASEA-I Shut down/in decommissioning 473 1 August 1966 6 February 1972 19 June 2017
2 BWR ASEA-II Shut down/in decommissioning 638 1 September 1969 1 January 1975 22 December 2016
3 BWR ASEA-III, BWR-3000 Operational 1400 1 May 1980 15 August 1985
R4 1 Unfinished
Ringhals 1 BWR ASEA-I Shut down 881 1 February 1969 1 January 1976 31 December 2020[78]
2 PWR WH 3-loops Shut down 904 1 October 1970 1 May 1975 30 December 2019
3 PWR WH 3-loops Operational 1062 1 September 1972 9 September 1981
4 PWR WH 3-loops Operational 1104 1 November 1973 21 November 1983

Switzerland[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction
Start Date
Commercial
Operation Date
Closure[79]
Type Model
Beznau 1 PWR WH 2-loops Operational 365 1 September 1965 1 September 1969 2029
2 PWR WH 2-loops Operational 365 1 January 1968 1 December 1971 2031
Gösgen 1 PWR KWU 3-loops Operational 1010 1 December 1973 1 November 1979 not defined
Leibstadt 1 BWR BWR-6 Operational 1220 1 January 1974 15 December 1984 not defined
Lucens 1 HWGCR HWGCR Shut down/dismantled 6 1 April 1962 29 December 1966 21 January 1969
Mühleberg 1 BWR BWR-4 Shut down/in decommissioning 373 1 March 1967 6 November 1972 20 December 2019

Taiwan[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Jinshan 1 BWR BWR-4 Shut down 636 2 June 1972 10 December 1978 3 October 2018
2 BWR BWR-4 Shut down 636 7 December 1973 15 July 1979 3 October 2018
Kuosheng 1 BWR BWR-6 Shut down[80] 985 19 November 1975 28 December 1981 1 July 2021
2 BWR BWR-6 Operational 985 15 March 1976 16 March 1983
Lungmen 1 BWR ABWR Unfinished[81] 1,350 31 March 1999
2 BWR ABWR Unfinished 1,350 30 August 1999
Maanshan 1 PWR WH 312 3-loop Operational 951 21 August 1978 27 July 1984
2 PWR WH 312 3-loop Operational 951 21 February 1979 18 May 1985

Turkey[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Akkuyu 1 PWR VVER-1200 V-509 Under construction 1114 3 April 2018 (2023)
2 PWR VVER-1200 V-513 Under construction 1114 8 April 2020 (2024)
3 PWR VVER-1200 V-513 Under construction 1114 11 March 2021 (2025)
4 PWR VVER-1200 V-513 Planned 1114 2021 (2026)
Sinop[82] 1 PWR Atmea-1 Never built 1100 (2020) (2025)
2 PWR Atmea-1 Never built 1100 (2021) (2026)
3 PWR Atmea-1 Never built 1100 (2022) (2027)
4 PWR Atmea-1 Never built 1100 (2023) (2028)
1 PWR AP1000 Planned 1000
2 PWR AP1000 Planned 1000
3 PWR CAP1400 Planned 1400
4 PWR CAP1400 Planned 1400

Ukraine[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Chernobyl 1 LWGR RBMK-1000 Shut down/in decommissioning 740 1 March 1970 27 May 1978 30 November 1996
2 LWGR RBMK-1000 Shut down/in decommissioning 925 1 February 1973 28 May 1979 11 October 1991
3 LWGR RBMK-1000 Shut down/in decommissioning 925 1 March 1976 8 June 1982 15 December 2000
4 LWGR RBMK-1000 Destroyed 925 1 April 1979 26 March 1984 26 April 1986
5 LWGR RBMK-1000 Unfinished 925
6 LWGR RBMK-1000 Unfinished 925
Chyhyryn 1 PWR VVER-1000 Unfinished 1977 19 May 1989
2 PWR VVER-1000 Unfinished 1977 19 May 1989
3 PWR VVER-1000 Unfinished 1977 19 May 1989
4 PWR VVER-1000 Unfinished 1977 19 May 1989
Crimean 1 PWR VVER-1000 Unfinished 26 January 1984 1987
2 PWR VVER-1000 Unfinished 26 January 1984 1987
3 PWR VVER-1000 Never built
4 PWR VVER-1000 Never built
Kharkiv 1 PWR VVER-1000 Unfinished 900 1988 1990
2 PWR VVER-1000 Unfinished 900 1988 1990
3 PWR VVER-1000 Never built 900
4 PWR VVER-1000 Never built 900
Khmelnytskyi 1 PWR VVER-1000 Operational 950 1 November 1981 13 August 1988
2 PWR VVER-1000 Operational 950 1 February 1985 15 December 2005
3 PWR VVER-1000 Unfinished 950 1 March 1986
4 PWR VVER-1000 Unfinished 950 1 February 1987
5 PWR VVER V-320 Never built
6 PWR VVER V-320 Never built
Odesa 1 PWR VVER-1000 Unfinished 900 1989
2 PWR VVER-1000 Unfinished 900 1989
Rivne 1 PWR VVER-440 V-213 Operational 381 1 August 1973 22 September 1981
2 PWR VVER-440 V-213 Operational 376 1 October 1973 29 July 1982
3 PWR VVER-1000 Operational 950 1 February 1980 16 May 1987
4 PWR VVER-1000 Operational 950 1 August 1986 6 April 2006
5 PWR VVER-1000 Never built
6 PWR VVER-1000 Never built
South Ukraine 1 PWR VVER-1000 Operational 950 1 August 1976 2 December 1983
2 PWR VVER-1000 Operational 950 1 July 1981 6 April 1985
3 PWR VVER-1000 Operational 950 1 November 1984 29 December 1989
4 PWR VVER-1000 Unfinished 950
Zaporizhzhia 1 PWR VVER-1000 Operational 950 1 April 1980 25 December 1985
2 PWR VVER-1000 Operational 950 1 January 1981 15 February 1986
3 PWR VVER-1000 Operational 950 1 April 1982 5 March 1987
4 PWR VVER-1000 Operational 950 1 April 1983 14 April 1988
5 PWR VVER-1000 Operational 950 1 November 1985 27 October 1989
6 PWR VVER-1000 Operational 950 1 June 1986 17 September 1996

United Arab Emirates[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Barakah 1 PWR APR-1400 Operational 1345 19 July 2012 6 April 2021[83]
2 PWR APR-1400 Operational 1345 16 April 2013 14 September 2021[84]
3 PWR APR-1400 Under construction 1345 24 September 2014 (2021)
4 PWR APR-1400 Under construction 1345 30 July 2015 (2021)

United Kingdom[]

Name Unit
No.
Reactor Status Net capacity (MW) Construction start Commercial operation Closure
Type Model
Berkeley 1 GCR Magnox Shut down 138 1 January 1957 12 June 1962 31 March 1989
2 GCR Magnox Shut down 138 1 January 1957 20 October 1962 26 October 1988
Bradwell 1 GCR Magnox Shut down 123 1 January 1957 1 July 1962 31 March 2002
2 GCR Magnox Shut down 123 1 January 1957 12 November 1962 30 March 2002
Bradwell B 1 PWR Hualong-1 Planned 1117
2 PWR Hualong-1 Planned 1117
Calder Hall 1 GCR Magnox Shut down 49 1 August 1953 1 October 1956 31 March 2003
2 GCR Magnox Shut down 49 1 August 1953 1 February 1957 31 March 2003
3 GCR Magnox Shut down 49 1 August 1955 1 May 1958 31 March 2003
4 GCR Magnox Shut down 49 1 August 1955 1 April 1959 31 March 2003
Chapelcross 1 GCR Magnox Shut down 48 1 October 1955 1 March 1959 29 June 2004
2 GCR Magnox Shut down 48 1 October 1955 1 August 1959 29 June 2004
3 GCR Magnox Shut down 48 1 October 1955 1 December 1959 29 June 2004
4 GCR Magnox Shut down 48 1 October 1955 1 March 1960 29 June 2004
Dounreay 1 SFR DFR Shut down 11 1 March 1955 1 October 1962 1 March 1977
2 SFR PFR Shut down 234 1 January 1966 1 July 1976 31 March 1994
Dungeness A-1 GCR Magnox Shut down 225 1 July 1960 28 October 1965 31 December 2006
A-2 GCR Magnox Shut down 225 1 July 1960 30 December 1965 31 December 2006
B-1 GCR AGR Shut down 520 1 October 1965 1 April 1985 7 June 2021
B-2 GCR AGR Shut down 520 1 October 1965 1 April 1989 7 June 2021
Hartlepool 1 GCR AGR Operational 595 1 October 1968 1 April 1989 (2024)
2 GCR AGR Operational 585 1 October 1968 1 April 1989 (2024)
Heysham A-1 GCR AGR Operational 585 1 December 1970 1 April 1989 (2024)
A-2 GCR AGR Operational 575 1 December 1970 1 April 1989 (2024)
B-1 GCR AGR Operational 610 1 August 1980 1 April 1989 (2030)
B-2 GCR AGR Operational 610 1 August 1980 1 April 1989 (2030)
Hinkley Point A 1 GCR Magnox Shut down 235 1 November 1957 30 March 1965 23 May 2000
2 GCR Magnox Shut down 235 1 November 1957 5 May 1965 23 May 2000
Hinkley Point B 1 GCR AGR Operational 435 1 September 1967 2 October 1978 (2022)
2 GCR AGR Operational 435 1 September 1967 27 September 1976 (2022)
Hinkley Point C 1 PWR EPR Under construction 1600 11 December 2018
2 PWR EPR Under construction 1600 12 December 2019
Hunterston A 1 GCR Magnox Shut down 150 1 October 1957 5 February 1964 30 March 1990
2 GCR Magnox Shut down 150 1 October 1957 1 July 1964 31 December 1989
Hunterston B 1 GCR AGR Shut down 460 1 November 1967 6 February 1976 26 November 2021
2 GCR AGR Operational 460 1 November 1967 31 March 1977 (2022)
Moorside[85] 1 PWR AP1000 Cancelled 1000
2 PWR AP1000 Cancelled 1000
3 PWR AP1000 Cancelled 1000
Moorside 1 PWR EPR Planned 1600
2 PWR EPR Planned 1600
Oldbury 1 GCR Magnox Shut down 217 1 May 1962 31 December 1967 29 February 2012
2 GCR Magnox Shut down 217 1 May 1962 30 September 1968 30 June 2011
Oldbury B 1 BWR ABWR Cancelled 1300
2 BWR ABWR Cancelled 1300
Sizewell A 1 GCR Magnox Shut down 210 1 April 1961 25 March 1966 31 December 2006
2 GCR Magnox Shut down 210 1 April 1961 15 September 1966 31 December 2006
Sizewell B 1 PWR WH SNUPPS Operational 1191 18 July 1988 22 September 1995 (2035)
Sizewell C 1 PWR EPR Planned 1600
2 PWR EPR Planned 1600
Torness 1 GCR AGR Operational 595 1 August 1980 25 May 1988 (2030)
2 GCR AGR Operational 595 1 August 1980 3 February 1989 (2030)
Trawsfynydd 1 GCR Magnox Shut down 195 1 July 1959 24 March 1965 6 February 1991
2 GCR Magnox Shut down 195 1 July 1959 24 March 1965 4 February 1991
Winfrith[86] 1 SGHWR SGHWR Shut down 92 1 May 1963 1 January 1968 11 September 1990
Wylfa 1 GCR Magnox Shut down 490 1 September 1963 1 November 1971 30 December 2015
2 GCR Magnox Shut down 490 1 September 1963 3 January 1972 25 April 2012
Wylfa Newydd 1 BWR ABWR Cancelled 1300
2 BWR ABWR Cancelled 1300

United States[]

Name Unit Reactor Status Capacity in MW Construction start Commercial operation Closure
Type Model Net Gross
Arkansas Nuclear One 1 PWR B & W (DRY-Cont.) Operational 846 1 October 1968 21 May 1974
2 PWR CE (DRY) Operational 930 6 December 1968 1 September 1978
Beaver Valley 1 PWR WH 3-loop (DRY) Operational 970 26 June 1970 2 July 1976
2 PWR WH 3-loop (DRY) Operational 920 3 May 1974 14 August 1987
Bellefonte 1 PWR B & W (DRY-Cont.) Unfinished 1,100 1975
2 PWR B & W (DRY-Cont.) Unfinished 1,100 1975
Big Rock Point[87] 1 BWR BWR-1 Shut down/dismantled 67 1 May 1960 29 March 1963 29 August 1997
Blue Castle Project[88] 1 Planned 1,500 (2023) (2028)
2 Planned 1,500 (2023) (2028)
Braidwood 1[89] PWR WH 4-loop (DRY) Operational 1,194 1,270 1 August 1975 29 July 1988
2[90] PWR WH 4-loop (DRY) Operational 1,121 1 August 1975 17 October 1988
Browns Ferry 1 BWR BWR-4 (WET) Operational 1,310 1 May 1967 1 August 1974
2 BWR BWR-4 (WET) Operational 1,310 1 May 1967 1 March 1975
3 BWR BWR-4 (WET) Operational 1,310 1 July 1968 1 March 1977
Brunswick 1 BWR BWR-4 (WET) Operational 938 7 February 1970 18 March 1977[91]
2 BWR BWR-4 (WET) Operational 920 7 February 1970 3 November 1975[92]
Byron 1 PWR WH 4-loop (DRY) Operational 1,168 1 April 1975 16 September 1985
2 PWR WH 4-loop (DRY) Operational 1,168 1 April 1975 2 August 1987
Callaway 1 PWR WH 4-loop (DRY) Operational 1,300 1 September 1975 19 December 1984
Calvert Cliffs 1 PWR CE 2-loop (DRY) Operational 873 1 June 1968 8 May 1977
2 PWR CE 2-loop (DRY) Operational 863 1 June 1968 1 April 1977
Catawba 1 PWR WH 4-loop (ICECOND.) Operational 1,129 1 May 1974 29 June 1985
2 PWR WH 4-loop (ICECOND.) Operational 1,129 1 May 1974 19 August 1986
Clinton 1 BWR BWR-6 (WET) Operational 1,043 1 October 1975 24 November 1987
Columbia 1 BWR BWR-5 (WET) Operational 1,170 1 August 1972 13 December 1984
Comanche Peak 1 PWR WH 4-loop (DRY) Operational 1,084 19 December 1974 13 August 1990
2 PWR WH 4-loop (DRY) Operational 1,124 19 December 1974 3 August 1993
Connecticut Yankee 1 PWR WH DRY Shut down/dismantled 582 1 May 1964 1 January 1968 5 December 1996
Cooper 1 BWR BWR-4 (WET) Operational 770 1 June 1968 1 July 1974
Crystal River 3 1 PWR B & W (DRY) Shut down 860 25 September 1968 13 March 1977 5 February 2013
Davis-Besse 1 PWR B & W (DRY) Operational 965 1 September 1970 31 July 1978
Diablo Canyon 1 PWR WH DRY Operational 1,122 23 April 1968 7 May 1985
2 PWR WH DRY Operational 1,118 9 December 1970 13 March 1986
Donald C. Cook 1 PWR WH (ICECOND.) Operational 1,020 25 March 1969 27 August 1975
2 PWR WH (ICECOND.) Operational 1,090 25 March 1969 1 July 1978
Dresden 1 BWR BWR-1 Shut down 210 1 May 1956 4 July 1960 31 October 1978
2 BWR BWR-3 (WET) Operational 867 10 January 1966 9 June 1970
3 BWR BWR-3 (WET) Operational 867 14 October 1966 16 November 1971
Duane Arnold 1 BWR BWR-4 (WET) Shut down 581 22 May 1970 1 February 1975 10 August 2020
Edwin I. Hatch 1 BWR BWR-4 (WET) Operational 924 30 September 1968 31 December 1975
2 BWR BWR-4 (WET) Operational 924 1 February 1972 5 September 1979
Elk River 1 BWR Shut down/dismantled 22 1 July 1964 1 February 1968
Fermi 1 FBR Prototype Shut down 69 8 August 1956 7 August 1966 29 November 1972
2 BWR BWR-4 (WET) Operational 1,098 26 September 1972 23 January 1988
Fort Calhoun 1 PWR CE 2-loop (WET) Shut down 476 1966 9 August 1973 24 October 2016
Fort St. Vrain 1 HTGR General Atomics Shut down 330 1 July 1979 29 August 1989
Ginna 1 PWR WH 2-loop (DRY) Operational 610 25 April 1966 1 June 1970
Grand Gulf 1 BWR BWR-6 (WET) Operational 1,500 1 July 1985
H. B. Robinson 1 PWR WH 3-loop (DRY) Operational 735 7 March 1971
Hallam 1 Sodium-cooled graphite-moderated Atomics International Shut down/dismantled 75 1963 1969
Hope Creek 1 BWR BWR-4 (WET) Operational 1,059 20 December 1986
Humboldt Bay 1 BWR BWR-1 Shut down/dismantled 63 August 1963 July 1976
Indian Point 1 PWR Shut down 275 1 May 1956 1 October 1962 31 October 1974
2 PWR WH 4-loop (DRY) Shut down 1,032 14 October 1966 1 August 1974 30 April 2020[93]
3 PWR WH 4-loop (DRY) Shut down 1,051 1 November 1968 30 August 1976 30 April 2021[93]
James A. FitzPatrick 1 BWR BWR-4 (WET) Operational 838 July 1975
Joseph M. Farley 1 PWR WH (DRY) Operational 900 1 December 1977
2 PWR WH (DRY) Operational 920 30 July 1981
Kewaunee 1 PWR WH 2-loop (DRY) Shut down 556 16 June 1974 7 May 2013
La Crosse 1 BWR BWR-1 Shut down/dismantled 50 7 November 1969 30 April 1987
LaSalle County 1 BWR BWR-5 (WET) Operational 1,200 1 January 1984
2 BWR BWR-5 (WET) Operational 1,200 19 October 1984
Limerick 1 BWR BWR-5 (WET) Operational 1,134 1 February 1986
2 BWR BWR-5 (WET) Operational 1,134 8 January 1990
Maine Yankee 1 PWR WH (DRY) Shut down/dismantled 860 1 October 1968 28 December 1972[94] 1 August 1997[94]
McGuire 1 PWR WH (ICECOND.) Operational 1,100 1 December 1981
2 PWR WH (ICECOND.) Operational 1,100 1 March 1984
Millstone 1 BWR BWR-3 (WET) Shut down 1 May 1966 28 December 1970 21 July 1998
2 PWR CE 2-loop (DRY) Operational 882 1 November 1969 26 December 1975
3 PWR WH (DRY) Operational 1,155 9 August 1974 23 April 1986
Monticello 1 BWR BWR-3 (WET) Operational 647 30 June 1971
N-Reactor 1 LWGR United States Atomic Energy Commission Shut down 800 1964 December 1986
Nine Mile Point 1 BWR BWR-2 (WET) Operational 621 12 April 1965 1 December 1969
2 BWR BWR-5 (WET) Operational 1,140 1 August 1975 11 March 1988
North Anna 1 PWR WH (DRY) Operational 903 6 June 1978
2 PWR WH (DRY) Operational 972 14 December 1980
North Anna 3 ESBWR WET Planned 1,500
Oconee 1 PWR B & W (DRY) Operational 846 15 July 1973
2 PWR B & W (DRY) Operational 846 9 September 1974
3 PWR B & W (DRY) Operational 846 16 December 1974
Oyster Creek 1 BWR BWR-2 (WET) Shut down 636 15 December 1964 23 December 1969 17 September 2018
Palisades 1 PWR CE 2-loop (DRY) Operational 800 14 March 1967 31 December 1971 (2022)[95]
Palo Verde 1 PWR CE80 2-loop (DRY) Operational 1,447 25 May 1976 28 January 1986
2 PWR CE80 2-loop (DRY) Operational 1,447 1 June 1976 19 September 1986
3 PWR CE80 2-loop (DRY) Operational 1,447 1 June 1976 8 January 1988
Parr 1 PHWR CVTR Shut down/dismantled 17 18 December 1963 10 January 1967
Pathfinder 1 BWR BWR-1 Shut down/dismantled 59 July 1966 October 1967
Peach Bottom 1 GCR Prototype Shut down 1 February 1962 1966 1974
2 BWR BWR-4 (WET) Operational 1,382 31 January 1968 5 July 1974
3 BWR BWR-4 (WET) Operational 1,382 31 January 1968 23 December 1974
Perry 1 BWR BWR-6 (WET) Operational 1,231 18 November 1987
Pilgrim 1 BWR BWR-3 (WET) Shut down 677 711 26 August 1968 9 December 1972 31 May 2019
Piqua 1 Organic nuclear reactor Atomics International Shut down/decommissioned 12.5 1963 1966
Point Beach 1 PWR WH 2-loop (DRY) Operational 510 21 December 1970
2 PWR WH 2-loop (DRY) Operational 516 1 October 1972
Prairie Island 1 PWR WH 2-loop (DRY) Operational 548 16 December 1973
2 PWR WH 2-loop (DRY) Operational 548 21 December 1974
Quad Cities 1 BWR BWR-4 (WET) Operational 912 18 February 1973
2 BWR BWR-4 (WET) Operational 912 10 March 1973
Rancho Seco 1 PWR WH (DRY) Shut down/dismantled 913 17 April 1975 23 October 2009
River Bend 1 BWR BWR-6 (WET) Operational 978 16 June 1986
Salem 1 PWR WH 4-loop (DRY) Operational 1,174 30 June 1977
2 PWR WH 4-loop (DRY) Operational 1,130 31 October 1981
San Onofre 1 PWR WH (DRY) Shut down/dismantled 436 456 1964 1 January 1968 30 November 1992
2 PWR CE (DRY) Shut down 1,172 8 August 1983 7 June 2013
3 PWR CE (DRY) Shut down 1,178 1 April 1984 7 June 2013
Saxton 1 PWR Shut down/dismantled November 1961 May 1972
Seabrook Station 1 PWR WH (DRY) Operational 1,194 15 March 1990
Sequoyah 1 PWR WH 4-Loop (ICECOND.) Operational 1,148 1 July 1981
2 PWR WH 4-Loop (ICECOND.) Operational 1,126 1 June 1982
Shearon Harris 1 PWR WH 3-Loop (DRY) Operational 900 960 28 January 1978 2 May 1987
Shippingport 1 PWR WH Shut down/dismantled 60 6 September 1954 26 May 1958 December 1989
Shoreham 1 BWR GE Shut down 820 1 November 1972 1 August 1986 1 May 1989
Sodium Reactor Experiment 1 FBR Shut down/dismantled 6.5 1954 12 July 1957 15 February 1964
South Texas 1 PWR WH 4-loop (DRY) Operational 1,250 22 December 1975 25 August 1988
2 PWR WH 4-loop (DRY) Operational 1,250 22 December 1975 19 June 1989
St. Lucie 1 PWR CE (DRY) Operational 1,002 1 July 1970 1 March 1976
2 PWR CE (DRY) Operational 1,002 2 June 1977 10 June 1983
Surry 1 PWR WH 3-loop (DRY) Operational 799 25 June 1968 22 December 1972
2 PWR WH 3-loop (DRY) Operational 799 1 May 1973
Susquehanna 1 BWR BWR-5 (WET) Operational 1,350 2 November 1973 12 November 1982
2 BWR BWR-5 (WET) Operational 1,350 27 June 1984
Three Mile Island 1 PWR B & W (DRY) Shut down 852 18 May 1968 2 September 1974 20 September 2019
2 PWR B & W (DRY) Shut down/Core melt 906 1 November 1969 30 December 1978 1979
Trojan 1 PWR WH (DRY) Shut down/dismantled 1,130 1 February 1970 20 May 1976 1992
Turkey Point 1 PWR WH 3-loop (DRY) Operational 900 27 April 1967 14 December 1972
2 PWR WH 3-loop (DRY) Operational 900 27 April 1967 7 September 1973
3 PWR AP1000 Planned 1000 1135
4 PWR AP1000 Planned 1000 1135
(SMR)[96] 1 PWR NuScale Planned 77 (2029-2030)
2 PWR NuScale Planned 77 (2029-2030)
3 PWR NuScale Planned 77 (2029-2030)
4 PWR NuScale Planned 77 (2029-2030)
5 PWR NuScale Planned 77 (2029-2030)
6 PWR NuScale Planned 77 (2029-2030)
Vallecitos 1 BWR BWR-1 Shut down 25 October 1957 December 1963
Vermont Yankee 1 BWR BWR-4 (WET) Shut down 514[97] 30 November 1972 29 December 2014[98]
Virgil C. Summer 1 PWR WH 3-Loop (DRY) Operational 1,000 21 March 1973 1 January 1984
Vogtle 1 PWR WH (DRY) Operational 1,215 1 August 1976 1 June 1987
2 PWR WH (DRY) Operational 1,215 1 August 1976 20 May 1989
3 PWR AP1000 (DRY) Under construction 1,250 12 March 2013 (2021)[99]
4 PWR AP1000 (DRY) Under construction 1,250 19 November 2013 (2022)[99]
Waterford 1 PWR CE 2-loop (DRY) Operational 1,218 14 November 1974 24 September 1985
Watts Bar 1 PWR WH (ICECOND.) Operational 1,167 20 July 1973 27 May 1996
2 PWR WH (ICECOND.) Operational 1,165 1 September 1973 4 June 2016
Wolf Creek 1 PWR WH (DRY) Operational 1,250 31 May 1977 3 September 1985
Yankee Rowe 1 PWR WH (DRY) Shut down/dismantled 185 1956 1960 26 February 1992
Zion 1 PWR WH (DRY) Shut down/dismantled 1,040 1 December 1968 June 1973 13 February 1998
2 PWR WH (DRY) Shut down/dismantled 1,040 1 December 1968 December 1973 13 February 1998

See also[]

Notes and references[]

  1. ^ a b "World Nuclear Power Reactors & Uranium Requirements". world-nuclear.org. World Nuclear Association. Retrieved 5 May 2020.
  2. ^ "PRIS - Home". pris.iaea.org.
  3. ^ Reference Unit Power at IAEA
  4. ^ "Nuclear Power in Argentina | Argentinian Nuclear Energy - World Nuclear Association". world-nuclear.org. Retrieved 4 August 2019.
  5. ^ "Atucha 3 contract signed". Retrieved 20 August 2015.
  6. ^ "Macri acordó en China que la construcción de Atucha III comenzará en enero". Télam. Retrieved 30 May 2017.
  7. ^ Yulia Kosarenko. "NASA fact sheet". Archived from the original on 8 July 2007. Retrieved 20 August 2015.
  8. ^ "BNamericas - The Embalse Nuclear Power Plant returns to s..." BNamericas.com.
  9. ^ "Nuclear Power in Bangladesh - World Nuclear Association". world-nuclear.org. Retrieved 17 July 2018.
  10. ^ "Росатом Госкорпорация "Росатом" ядерные технологии атомная энергетика АЭС ядерная медицина". rosatom.ru.
  11. ^ "RTBF Info of 21 December 2018". RTBF Info. 21 December 2018. Retrieved 28 December 2018.
  12. ^ a b Patel, Sonal (2 December 2021). "Darlington Nuclear Plant Will Get a BWRX-300 SMR as GE Hitachi Bags Lucrative OPG Selection". POWER Magazine. Retrieved 5 December 2021.
  13. ^ a b "China / Construction Begins of Two Hualong One Reactors at Changjiang". The Independent Global Nuclear News Agency. Retrieved 28 November 2019.
  14. ^ a b "我国自主三代核电华龙一号在海南正式开工建设". CNNC. Retrieved 2 April 2021.
  15. ^ "China's first Hualong One nuclear reactor starts commercial operation". Reuters. Reuters. 30 January 2021. Retrieved 30 January 2021.
  16. ^ "Second AP1000 enters commercial operation". World Nuclear News. World Nuclear Association. Retrieved 24 October 2018.
  17. ^ "Fourth Chinese AP1000 enters commercial operation". World Nuclear News. World Nuclear Association. Retrieved 13 January 2019.
  18. ^ "China Nuclear Power | Chinese Nuclear Energy - World Nuclear Association". world-nuclear.org. Retrieved 16 July 2018.
  19. ^ "Fifth Hongyanhe unit enters commercial operation". World Nuclear News. World Nuclear Association. Retrieved 2 August 2021.
  20. ^ a b c "China Nuclear Power | Chinese Nuclear Energy - World Nuclear Association". world-nuclear.org. Retrieved 15 June 2018.
  21. ^ a b "Construction of new Chinese power plant begins : New Nuclear - World Nuclear News". world-nuclear-news.org. Retrieved 5 January 2021.
  22. ^ "First AP1000 reactor enters commercial operation". World Nuclear News. World Nuclear Association. Retrieved 24 October 2018.
  23. ^ "Sanmen 2 AP1000 enters commercial operation - World Nuclear News". world-nuclear-news.org. Retrieved 7 November 2018.
  24. ^ "HTR-PM: Demonstration HTR-PM grid connected - World Nuclear News". Retrieved 21 December 2021.
  25. ^ a b "China approves first new nuclear reactors in 3-plus years". Nikkei Asian Review. Retrieved 2 August 2019.
  26. ^ "EDF : le premier des 2 EPR de la centrale de Taishan (Chine) entre en exploitation commerciale". Capital.fr (in French). 14 December 2018. Retrieved 14 December 2018.
  27. ^ "World's second EPR starts operations". Retrieved 10 September 2019.
  28. ^ "Fourth Tianwan unit enters commercial operation". World Nuclear News. World Nuclear Association. Retrieved 27 December 2018.
  29. ^ "Fifth Tianwan unit starts commercial operation". World Nuclear News. World Nuclear Association. Retrieved 9 September 2020.
  30. ^ a b "Дан старт сооружению новых блоков российского дизайна атомных станций "Тяньвань" и "Сюйдапу" (Китай)". ruscable.ru.
  31. ^ "Fast nuclear reactor to start construction in Fujian in 2017". 16 August 2015. Archived from the original on 17 August 2015. Retrieved 16 August 2015.
  32. ^ a b c "China starts building second CFR-600 fast reactor : New Nuclear - World Nuclear News". world-nuclear-news.org. Retrieved 30 December 2020.
  33. ^ "Yangjiang 5 enters commercial operation". world-nuclear-news.org. Retrieved 16 July 2018.
  34. ^ "Construction starts on first Zhangzhou unit - World Nuclear News". world-nuclear-news.org. Retrieved 18 October 2019.
  35. ^ "El Dabaa Nuclear Power Project- Egypt's First NPP".
  36. ^ "The Olkiluoto 3 plant unit has been granted permission for startup".
  37. ^ "https://world-nuclear-news.org/Articles/Decree-delays-deadline-for-start-up-of-Flamanville". World Nuclear News. 31 March 2020. Retrieved 21 December 2020. External link in |title= (help)
  38. ^ "German reactor permanently shut down". world-nuclear-news.org. Retrieved 10 May 2018.
  39. ^ "Germany shuts down Philippsburg 2". energycentral.com. Retrieved 8 January 2020.
  40. ^ "Bundesregierung | Kernkraftwerke kommen auf den Prüfstand" (in German). Bundesregierung.de. Archived from the original on 4 May 2011. Retrieved 8 August 2012.
  41. ^ "13. Gesetz zur Änderung des Atomgesetzes" (PDF).
  42. ^ "Government Approves 10 Sites for New Nuclear Power Projects". The New Indian Express.
  43. ^ Indian Nuclear Power Program Archived 1 July 2012 at the Wayback Machine
  44. ^ "Annual Report 2018-19 DAE" (PDF). Department of Atomic Energy. Retrieved 13 February 2020.
  45. ^ a b c d e f g h i j k l m n o p (PDF) https://aris.iaea.org/PDF/IPHWR-220.pdf. Missing or empty |title= (help)
  46. ^ a b c d (PDF) https://aris.iaea.org/PDF/IPHWR-700.pdf. Missing or empty |title= (help)
  47. ^ "India, USA document their commitment to new build".
  48. ^ "Andhra Pradesh to get another nuclear plant". Deccan Chronicle. 22 September 2018. Retrieved 1 October 2018.
  49. ^ "В Индии началось сооружение блока № 6 АЭС «Куданкулам»". ase-ec.ru (in Russian). Retrieved 21 December 2021.
  50. ^ "Rajya Sabha unstarred question No. 466" (PDF). Department of Atomic Energy. Retrieved 20 March 2021.
  51. ^ "Genkai unit 4 supplying power again". world-nuclear-news.org. Retrieved 22 June 2018.
  52. ^ a b c d e f g h i "Licensing status for the Japanese nuclear facilities - Japan Nuclear Safety Institute". genanshin.jp. Retrieved 3 October 2021.
  53. ^ a b c d "Nuclear Power Plants in Japan - The Federation of Electric Power Companies of Japan(FEPC)". fepc.or.jp. Retrieved 8 May 2018.
  54. ^ "40年超の美浜原発3号機が再稼働 原発事故後 全国初". NHK. Retrieved 23 June 2021.
  55. ^ "Ohi No.4 reactor restarted- News - NHK WORLD - English". NHK WORLD. Archived from the original on 10 May 2018. Retrieved 10 May 2018.
  56. ^ "Japan clears restart at nuclear reactor closest to epicenter of 2011 quake - Reuters". reuters.com. Retrieved 27 November 2019.
  57. ^ "Japan approves extension for reactor similar to Fukushima units that melted down - Reuters". reuters.com. Retrieved 29 December 2019.
  58. ^ a b "North Korea's Yongbyon Nuclear Facility: Slow Progress at the Experimental Light Water Reactor". 38 North. U.S.-Korea Institute, Johns Hopkins University School of Advanced International Studies. 14 January 2016. Archived from the original on 9 April 2016. Retrieved 4 April 2016.
  59. ^ "Pakistan's China-Built Nuclear Reactor Starts Operation | Voice of America - English". voanews.com.
  60. ^ "Preferred site of the first Polish nuclear power plant indicated by investor". 22 December 2021.
  61. ^ a b c d e f g Wilczek, Maria (16 June 2020). "Construction of Poland's first nuclear power plant to begin in 2026".
  62. ^ "Rosatom State Atomic Energy Cooperation | ROSATOM's first of a kind floating power unit connects to isolated electricity grid in Pevek, Russia's Far East". rosatom.ru. Retrieved 1 January 2020.
  63. ^ a b c "Nuclear Power in Russia | Russian Nuclear Energy - World Nuclear Association". world-nuclear.org. Retrieved 14 May 2018.
  64. ^ "Кольскую АЭС-2 начнут строить в 2028 году".
  65. ^ Dollezhal N.A. At the origins of the man-made world: Notes of the designer - M .: Knowledge, 1989 - Academician's Tribune - 256s.(Доллежаль Н. А. У истоков рукотворного мира: Записки конструктора — М.: Знание, 1989 — Трибуна академика — 256с.)
  66. ^ "The construction of the 2nd innovative VVER-TOI power block at the Kursk NPP-2 site has started ahead of schedule". rosenergoatom.ru. Retrieved 16 April 2019.
  67. ^ "Russia retires Leningrad unit 1". World Nuclear News. World Nuclear Association. Retrieved 27 December 2018.
  68. ^ "Unit 6 of Leningrad NPP commissioned for commercial operation". rosatom.ru. Retrieved 23 March 2021.
  69. ^ a b c "Four new npp units will be built in russia". rosatom-europe.com. Retrieved 26 June 2020.
  70. ^ a b c d "Russia commits to further floating NPPs : New Nuclear - World Nuclear News". world-nuclear-news.org. Retrieved 28 July 2021.
  71. ^ a b c d ""Росатом" и Kaz Minerals предварительно договорились о поставках электроэнергии для Баимского ГОКа". Interfax.ru (in Russian). Retrieved 3 September 2021.
  72. ^ "В Якутии собираются строить АЭС мощностью не менее 55 МВт". Sakhapress.ru.
  73. ^ Сурикова, Маргарита (8 June 2021). "Росатом» начал строительство реактора Брест-300 в Северске". Известия.
  74. ^ Shut down after a 1977 refuelling incident; decommission in progress since 1979
  75. ^ "Tlačová agentúra Slovenskej republiky - TASR.sk". tasr.sk. Archived from the original on 20 January 2009.
  76. ^ "Slovenian decision on second unit by 2027: minister : Nuclear Policies - World Nuclear News". world-nuclear-news.org.
  77. ^ "Second APR-1400 unit starts commercial operation". world-nuclear-news.org. Retrieved 3 September 2019.
  78. ^ "Ringhals 1 inne på slutspurten". SVT (in Swedish). 26 October 2020. Retrieved 29 December 2020.
  79. ^ admin.ch, The Federal Authorities, Federal Council decides to gradually phase out nuclear energy as part of its new energy strategy Archived 20 June 2013 at the Wayback Machine, 25 May 2011
  80. ^ "Early shutdown for Taiwanese reactor : Corporate - World Nuclear News". world-nuclear-news.org. Retrieved 1 August 2021.
  81. ^ "Sputnik News - World News, Breaking News & Top Stories".
  82. ^ "Turkey, Japan scrap partnership in Sinop nuclear plant in Turkey's north - Turkey News". Hürriyet Daily News.
  83. ^ "UAE's first nuclear power plant begins commercial operations". Reuters. 6 April 2021. Retrieved 6 April 2021.
  84. ^ https://www.world-nuclear-news.org/Articles/Second-Barakah-unit-connected-to-the-grid
  85. ^ "Nuclear Power in the United Kingdom |UK Nuclear Energy - World Nuclear Association". world-nuclear.org. Retrieved 14 May 2018.
  86. ^ "PRIS - Reactor Details". pris.iaea.org. Retrieved 24 January 2019.
  87. ^ "PRIS - Reactor Details". iaea.org. Retrieved 11 May 2018.
  88. ^ Kern, Penelope (30 October 2007). "Nuclear Plant in Works for Utah; Coal Developer Joins Effort". Energy Prospects West.
  89. ^ "PRIS - Reactor Details". iaea.org. Retrieved 11 May 2018.
  90. ^ "PRIS - Reactor Details". iaea.org. Retrieved 11 May 2018.
  91. ^ "BRUNSWICK-1". IAEA. Retrieved 14 April 2013.
  92. ^ "BRUNSWICK-2". IAEA. Retrieved 14 April 2013.
  93. ^ a b "Entergy's Indian Point Unit 2 to Shut Down Permanently". Indian Point Energy Center. 29 April 2020. Retrieved 30 April 2020.
  94. ^ a b "MAINE YANKEE". IAEA. Retrieved 14 April 2013.
  95. ^ AP, John Madill/The Herald-Palladium via; File (28 September 2017). "Palisades nuclear plant in Michigan to shut down in 2022". Energy News Network. Retrieved 7 December 2019.
  96. ^ "Scaled down SMR pilot project remains on course : New Nuclear - World Nuclear News". world-nuclear-news.org. Retrieved 24 July 2021.
  97. ^ "VERMONT YANKEE". IAEA. 13 April 2013. Retrieved 14 April 2013.
  98. ^ StarTribune.com, WILSON RING Vermont Yankee nuclear power plant ends operations after 42 years of producing electricity Archived 29 December 2014 at the Wayback Machine, 29 December 2014
  99. ^ a b Walton, Rod (9 August 2018). "Vogtle Cost Upgrade Causes Rethinking of $25B Nuclear Plant's Future". Power Engineering.

External links[]

Retrieved from ""