Page extended-protected

R211 (New York City Subway car)

From Wikipedia, the free encyclopedia

R211
First of New R211 Subway Cars Arrive for Testing (51282649362) (cropped).jpg
R211 train on the South Brooklyn Railway going to Coney Island Yard
MTA Celebrates 31st Anniversary of ADA (51336078507).jpg
Interior of an R211A car
In serviceest. 2022
ManufacturerKawasaki Heavy Industries
Built atLincoln, Nebraska, and Yonkers, New York[1]
Family nameNTT (New Technology Train)
ReplacedAll SIR operated R44s
All R46s
Constructed2019–present
Entered serviceR211A: 2022 (estimate)
R211T: TBA
R211S: TBA
Number under construction535
(1,612 with all options exercised)
Number built10[2]
Number in service0
FormationFive-car sets; four-car sets (if second option exercised)
Fleet numbers
  • R211A: 4060–4499[3]
Operator(s)
Specifications
Car body constructionStainless steel with fiberglass ends and rear bonnets[4]
Train length5-car train: 301.05 feet (91.76 m)
4-car train: 240.84 feet (73.41 m)
Car length60.21 feet (18.35 m)
Width10 feet (3,048 mm) max
Height12 feet (3,658 mm) max
Platform height3.76 ft (1.15 m)
Doors8 sets of 58 inches (150 cm) wide side doors per car
Maximum speed55 mph (89 km/h) (Service)
66 mph (106 km/h) (Design)
Weight82,000 pounds (37,000 kg)
Traction systemAlstom Optonix IGBT–VVVF[5]
Acceleration2.5 mph/s (1.1 m/s2)
Deceleration3.0 mph/s (1.3 m/s2)
(full service),
3.2 mph/s (1.4 m/s2)
(emergency)
Electric system(s)600 V DC Third rail
Current collection methodContact shoe
Braking system(s)Dynamic braking propulsion system; Pneumatic tread brake system
Safety system(s)CBTC, dead man's switch, train stop
Track gauge1,435 mm (4 ft 8+12 in) standard gauge

The R211 is a new technology (NTT) New York City Subway car being built by Kawasaki Heavy Industries for the B Division and the Staten Island Railway (SIR). They will replace all R44 cars on the Staten Island Railway and all R46 subway cars. The order is split into three parts: R211A and R211T cars for the subway and R211S cars for the SIR. The R211Ts employ open gangways between cars, a feature not present on current rolling stock. The base order consists of 535 cars, with options for up to 1,077 additional cars.

Planning for the R211 order started in 2011. The design process started in 2012, at which time the order was supposed to consist of 75-foot-long (23 m) cars. The cars' lengths were changed to 60 feet (18 m) by 2015, and the first request for proposals was solicited in July 2016. After several changes to the proposal, the Metropolitan Transportation Authority (MTA) awarded a contract to Kawasaki in January 2018. Delivery of the pilot cars began at the end of June 2021. They contain new features such as wider doors, information displays, Wi-Fi, LED-lit doorways, open gangways, and LED interior lighting.

Component orders

With all options exercised, the Metropolitan Transportation Authority (MTA) plans to spend $3.686 billion in the order.[6] The contract is split into three parts: R211A, R211S, and R211T. The majority of the 535-car base order will comprise 440 R211A cars that will partially replace the aging 748-car R46 fleet.[a] There will also be 20 R211T open gangway prototype cars, and 75 R211S cars which are expected to replace the remaining 61-car R44 fleet on the Staten Island Railway.[6][7]:73 The R44s and R46s are 75 feet (23 m) long, and the R211s are only 60 feet (18 m). As a result, the 752 R46s[a] would need to be replaced by 940 R211s.[b]

There will be two options for additional cars: the first for 640 cars and the second for 437 cars.[10] Both options are designed to accommodate either standard cars or open gangway cars, depending on the test results from the 20 pilot cars. If all options are exercised, the order would total 1,612 cars.[6] Any additional cars that do not replace existing rolling stock will be used to expand the system's fleet.[11][12] The R211 order would provide 1,015 new cars to replace existing fleet, as well as up to 597 cars for fleet expansions following the extension of the Second Avenue Subway and the automation of the New York City Subway.[7]:72 The R211Ts would also increase capacity and allow passengers to walk seamlessly from one car to the next.[11][13][14][15]

Features

Mock up of the proposed open gangway design (top) and the FIND system (bottom).

The doors on the R211s are be 58 inches (150 cm) wide, wider than the current MTA standard of 50 inches (130 cm),[1] thereby projected to reduce station dwell time by 25 to 30 percent.[16][17] This design change partially incorporates a design feature of the R110A prototype subway cars, which had doors that are 63 inches (160 cm) wide.[18] The new cars have Wi-Fi installed, USB chargers, digital advertisements, digital customer information displays, illuminated door opening alerts, and security cameras,[19][20][1][21] unlike the current New Technology Trains, which lack these features.[22] Each car contains an on-board computer system that could detect breakdowns in critical systems such as braking and door-opening.[1]

It was announced in July 2016 that some of the cars would have open gangways that allowed passengers to move between cars during train movement.[1] To test out the curve radius and gangway flex in the existing 60-foot-long cars, an R143 test train was equipped with measuring gauges and was operated on most parts of the B Division.[c]

There will be a change in exterior appearance from previous New Technology Trains. The subway cars have a blue front with large windows, LED headlights, and a blue strip with gold accents on the sides, similar to the new MTA Regional Bus Operations livery released in 2016. To designate the route, a large LED screen with the route bullet is displayed at the ends of the train, a feature similar to trains with rollsigns (R40 to R68A). Also, the route's destination is displayed above the door on the front, similar to the overhead rollsign arrangement last used on the R38 order from 1966, which displayed both the route and destination. On the sides, there is a screen that displays both the route bullet and the route's destination, also similar to rollsign-equipped trains.

There are also several changes in interior appearance. Updated FIND displays are installed over doors. The seating on the inside is blue and gold, and flip seats are installed to allow for space for wheelchairs.[19][20] There are also looped stanchions, a feature found in some R46, R62A, and R160 cars, as well as on all R179 cars. As part of an action plan to fix the subway's state of emergency of 2017, many of the R211's features were implemented on several R160s assigned to the E, F, and L routes.[23][24][25]

In addition to various screens throughout the train, touch screen displays are present throughout the subway cars, allowing people to zoom in and out of the map.[26][27]

All R211A and R211T cars are equipped for communications-based train control (CBTC)[10][17] in conjunction with the ongoing automation of B Division lines.[3]:14 All R211S cars are equipped with cab signaling.[10]

History

Initial request for proposals

The R211 Design Master Plan was approved by the MTA in December 2011, and design planning began in December 2012.[13][28] An R211 solicitation was posted in the classified section of Metro Magazine's May 9, 2013, issue, stating the proposal to acquire these cars in the near future. At the time, the order was planned to be 75 feet (23 m) in length, the same length as the R46 cars. Open-gangways, which would allow passengers to seamlessly walk throughout the train or units, and other alternate configurations were also initially considered for the entire order.[29]

By the release of the MTA's 2015-2019 Capital Program in October 2015, the order specified 60-foot (18 m) cars, which has been the standard length of new B Division cars since the R143 order. As of March 2016, open-gangways will be tested on ten cars (now designated as the R211T).[14] Additionally, the order was broken up into a base order of 565 R211A cars and two option orders: the first for 375 R211A cars, and a second for up to 520 R211As.[14][11][12][29]

The Request for Proposal (RFP) was issued on July 22, 2016, and the contract was to be put out for bidding.[13][14][19] With the RFP, the breakup of the order was changed. The base order consisted of 285 cars, with 10 R211T cars, 75 R211S cars, and 200 R211A cars. There were still two option orders; the first option order contained 740 cars (either R211As or R211Ts, depending on the success of the R211Ts in the base order), and the second base order contained 520 cars. The RFP closed in December 2016,[30] and the contract was expected to be awarded in early 2017,[13] at which time the existing R46 fleet would be 42 years old, making the oldest cars 46 years old, in 2021. However, in January 2017, the contract was pushed back to mid-2017.[30]

On April 24, 2017, at the New York City Transit Board Meeting, the breakdown of the order was changed once again. The base order now includes 535 cars (an increase of 250 cars), with 10 R211T cars, 75 R211S cars, and 450 R211A cars. The option order now consisted of between 490 and 640 R211T cars. This change was made to allow for faster deliveries of the R211 cars. The R211As, with their standard configuration, would be delivered in 2021, earlier than the open-gangway R211T cars, which would not be delivered until at least 2023.[6]

Contract

Creation of mockup and contract award

Full-size mock-up of the proposed exterior of an R211 car at 34th Street–Hudson Yards station
R211T mockup at Kawasaki's plant in Kobe, Japan

In May 2017,[30] the MTA quietly built a mockup of the R211 in a sparsely-used section of the 34th Street–Hudson Yards station's mezzanine, hidden behind a construction wall. The New York Daily News first reported on the mockup's existence in September of that year. The mockup contains features such as the open-gangway designs, digital screens showing next stops and their station layouts, multicolor lights next to the doors to indicate which set of doors will open, and a blue-and-gold-stripe paint design on its exterior.[31] The model was completed and was made publicly accessible from November 30 to December 6, 2017, so riders could review it.[32][33]

In August 2017, Bombardier Transportation, who was manufacturing the R179s at the time, was banned from bidding on the R211 contract due to various delays and problems associated with the R179 contract.[34][35] Shortly afterward, it was reported that CRRC had also opted out of contention for the R211 contract, leaving Kawasaki Heavy Industries and Alstom Transport as two of the likely bidders for the contract.[35]

On January 19, 2018, the MTA Board suggested that Kawasaki Rail Car, Inc, a subsidiary of Kawasaki Heavy Industries of Kobe, Japan, be awarded the $1.4 billion base order for the first 535 new R211 cars.[6][21] The cars are anticipated to be delivered from 2020 to 2023, with the option orders to be delivered by 2025. The R211 base order includes 20 R211T cars with open gangways; 75 R211S cars for the Staten Island Railway, to be delivered near the end of the base order; and 440 cars similar to the R143/R160 series, operating in five-car units.[6][1] The cars are being assembled at Kawasaki's factories in Lincoln, Nebraska, and Yonkers, New York.[1] The first test train was then expected to be delivered in July 2020, with the production cars being delivered between 2021 and 2023.[36] At the same time it was announced that there would be two option orders, with the first consisting of 640 cars, and the second consisting of 437 cars in 89 sets.[37][d] In October 2018, it was confirmed that the second option order would consist of 89 sets, and in September 2019, it was confirmed that the 89 sets would be formed from 437 cars.[38][10][e] The entire order will consist of 1,612 cars with both options exercised.[10][39]:12 The delivery of the base order is scheduled to be completed by August 2023, with option 1 and option 2 completed by December 2024 and October 2025 respectively.[36]

Delays in delivery

By January 2019, the first R211A train was scheduled to be delivered in July 2020, but was delayed to January 2021. Thereafter, new R211 cars would have been produced and delivered at a rate of 30 to 40 cars per month.[39]:29 The first two test trains of ten R211T open-gangway cars would have been delivered in May 2021, followed by the first 5-car set of R211S cars for the Staten Island Railway in December 2021.[39]:12 Under the schedule outlined in January 2019, the base order of R211 cars would begin delivery in October 2021[7]:74 and continue to be delivered through mid-2023.[39]:12 If the two option orders of 1,077 cars were exercised, deliveries would have continued through late 2025. A decision on whether to make the first option order as open-gangway or standard trainsets would have needed to be decided by late 2022.[39]:13 It was also announced in January 2019 that Kawasaki had made a full-car mock-up of the R211 fleet.[39]:15–17

In late November 2020, the MTA announced that delivery of the first cars was delayed to the first quarter of 2021.[40] The onset of the COVID-19 pandemic had impacted global supply chains and the delivery of the first cars was delayed by between 9 and 14 months.[3]:16 By January 2021, the first cars were scheduled to arrive in April. The R211T open-gangway test trains were delayed to April 2022, while the R211S Staten Island Railway test train was delayed to August 2022. Deliveries of the base order of R211As were scheduled for September 2022 to September 2024, while deliveries of the R211S cars were scheduled for October 2023 to June 2024.[3]:17 Kawasaki planned to deliver 22 cars per month, a rate that an independent engineering consultant for the MTA described as "aggressive".[3]:26

In late March 2021, TV station NY1 reported that delivery of the first cars had slipped further, with the arrival of the first cars delayed to June 2021.[41] At its June 2021 meeting, the MTA's Capital Program Oversight Committee announced the R211A pilot had been delayed to July 2021 and the R211T test train had been delayed to June 2022. The production of the R211A base order, the R211S test train, and the rest of the R211S order had the same timeline as was outlined in January 2021.[42]:12 Some of the other issues with the test train, such as cracks in the HVAC frame, had been identified in previous months and fixed.[42]:19 The base order of R211As had to be underway by November 2023 so there would be enough cars to test a communications-based train control (CBTC) system being installed on the IND Eighth Avenue Line.[42]:21

Delivery

R211A 4064 being delivered on June 29, 2021

Starting on June 29, 2021,[43] the first set of R211As (4060–4064) was delivered to the New York City Transit Authority.[16][44] The next five cars (4065–4069) were delivered starting on July 12, 2021, forming a complete pilot ten-car train for acceptance testing and evaluation.[citation needed] The test train was delivered despite a lack of staff in Nebraska and a shortage of important parts, which prompted an independent engineering consultant to predict that delivery of the test train could be delayed past July 2021.[42]:21 The pilot train was to be prepared at Coney Island Yard for three weeks before being tested without passengers.[45]

Notes

  1. ^ Jump up to: a b The R211 order is slated to replace 752 R46 cars.[6][7]:73 Four of these cars were scrapped after separate incidents in 2017 and 2020, leaving only 748 cars in revenue service.[8][9]
  2. ^ Both quantities represent 94 full-length trainsets, each of which is 600 ft (180 m) long. Each 600-foot trainset of R46s would require 8 cars, while each 600-foot trainset of sixty-foot-long cars would require 10 such cars. As such, 752 R46 cars could be arranged to make 94 full-length trainsets, and 940 sixty-foot-long cars could be arranged to make 94 such trainsets.
  3. ^ See also:
    • Tech And Transit (April 4, 2017), R211 Open Gangway Measurement Test Train (R143 8269-8272), retrieved April 5, 2017
  4. ^ If the second option had 333 cars, there would 88 cars in 22 sets of four cars each, and 245 cars in 49 sets of five cars each.
    • If the second option had 437 cars, there would be 32 cars in 8 sets of four cars each, and 405 cars in 81 sets of five cars each.
  5. ^ An option order with 333 cars would only result in 83.25 train sets of four cars, but an MTA board meeting document from October 2018 mentions 89 four- and five-car trainsets in the second option order, all of which would be equipped with communications-based train control. Assuming all 437 cars will be equipped with CBTC, the order would have to be divided into 81 five-car sets, totaling 405 cars, plus 8 four-car sets, totaling 32 cars.

References

  1. ^ Jump up to: a b c d e f g Maslin Nir, Sarah (January 19, 2018). "New York Set to Acquire the Next Generation of Subway Cars". The New York Times. Retrieved January 20, 2018.
  2. ^ "MTA reveals first look at new R211 subway cars". www.radio.com. January 21, 2020. Retrieved January 17, 2021.
  3. ^ Jump up to: a b c d e "Capital Program Oversight Committee Meeting January 2021". web.mta.info. Metropolitan Transportation Authority. January 2021. Retrieved January 19, 2021.
  4. ^ "New York City Transit to Award Contract for New Generation Subway Cars". Kawasaki Heavy Industries, Ltd. Retrieved January 17, 2021.
  5. ^ https://www.youtube.com/watch?v=fd-XmUIIc8M MTA Board Meeting Stream, 5:38:46
  6. ^ Jump up to: a b c d e f g "New York City Transit and Bus Committee Meeting 1/22/2018" (PDF). mta.info. Metropolitan Transportation Authority. January 22, 2018. pp. 134–136. Archived from the original (PDF) on January 27, 2018. Retrieved October 20, 2018.
  7. ^ Jump up to: a b c d "Capital Program Oversight Committee Meeting January 2020". web.mta.info. Metropolitan Transportation Authority. January 2020. Retrieved January 19, 2018.
  8. ^ "New York City Subway Car Update" (PDF). The Bulletin. Electric Railroaders' Association. 61 (2): 6–7. February 2018.
  9. ^ "New York City Subway Car Update" (PDF). The Bulletin. Electric Railroaders' Association. 63 (11): 20. November 2020.
  10. ^ Jump up to: a b c d e "New York City Transit and Bus Committee Meeting October 2018" (PDF). mta.info. Metropolitan Transportation Authority. October 19, 2018. pp. 188–189. Retrieved October 20, 2018.
  11. ^ Jump up to: a b c "Review of the A and C Lines" (PDF). Metropolitan Transportation Authority. December 11, 2015. Retrieved January 19, 2016.
  12. ^ Jump up to: a b "MTA Twenty-Year Capital Needs Assessment 2015-2034" (PDF). Metropolitan Transportation Authority. October 2013. Retrieved August 11, 2015.
  13. ^ Jump up to: a b c d "MTA Capital Program Oversight Committee Meeting: January 2016" (PDF). mta.info. Metropolitan Transportation Authority. January 2016. Archived from the original (PDF) on January 29, 2016. Retrieved January 23, 2016.
  14. ^ Jump up to: a b c d "Transit & Bus Committee Meeting - March 2016" (PDF). Metropolitan Transportation Authority. Metropolitan Transportation Authority. March 21, 2016. Retrieved March 19, 2016.
  15. ^ Rivoli, Dan (August 13, 2015). "Ancient subway trains on C and J/Z lines won't be replaced until 2022, documents say". Daily News (New York). Retrieved November 25, 2015.
  16. ^ Jump up to: a b Duggan, Kevin (July 1, 2021). "MTA moves forward with new R211 train cars after yearlong delay". amNewYork. Retrieved July 2, 2021.
  17. ^ Jump up to: a b "MTA unveils new fleet of subway cars". ABC7 New York. July 1, 2021. Retrieved July 2, 2021.
  18. ^ "R-110 New Technology Test Program". www.nycsubway.org. Retrieved July 19, 2016.
  19. ^ Jump up to: a b c "Governor Cuomo Unveils Design of Reimagined MTA Subway Cars and Details Ambitious Plan to Enhance Subway Stations". July 18, 2016. Retrieved July 19, 2016.
  20. ^ Jump up to: a b "MTA renderings" (PDF). www.governor.ny.gov. July 18, 2016. Retrieved July 18, 2016.
  21. ^ Jump up to: a b "kawasakirc.com NYCT Awards R211 Contract". Kawasaki Rail Car, Inc. January 27, 2018. Retrieved August 5, 2018.
  22. ^ "NYC, meet your (possible) subway cars of the future". am New York. Retrieved April 25, 2016.
  23. ^ Chung, Jen (October 3, 2017). "Photos: Step Inside The MTA's New Subway Cars, Now With Less Seating". Gothamist. Archived from the original on October 4, 2017. Retrieved October 4, 2017.
  24. ^ Furfaro, Danielle (October 3, 2017). "MTA removes seats from E train cars". New York Post. Retrieved October 4, 2017.
  25. ^ "news - Subway Action Plan Update: New Subway Cars on E Line". MTA. October 3, 2017. Retrieved January 20, 2018.
  26. ^ Miller, Seth (December 1, 2017). "Taking the new NYC Subway R211 cars for a test drive". Medium. Retrieved February 23, 2021.
  27. ^ "Here's Your Chance to Test 'Ride' the Next Subway Car | WNYC | New York Public Radio, Podcasts, Live Streaming Radio, News". WNYC. Retrieved February 23, 2021.
  28. ^ "Capital Program Oversight Committee Meeting: October 2012" (PDF). Metropolitan Transportation Authority. October 2012. Archived from the original (PDF) on November 2, 2013. Retrieved January 24, 2016.
  29. ^ Jump up to: a b "New York City Transit: R211 - New Generation of Subway Cars". Metro Magazine, MTA New York City Transit. May 2013. Retrieved November 25, 2015.
  30. ^ Jump up to: a b c "Capital Program Oversight Committee Meeting" (PDF). Metropolitan Transportation Authority. January 23, 2017. p. 37. Retrieved September 5, 2017.
  31. ^ Rivoli, Dan (September 5, 2017). "New subway train prototype up but hidden at Hudson Yards station". NY Daily News. Retrieved September 5, 2017.
  32. ^ Rivoli, Dan (November 30, 2017). "MTA unveils models of future subway cars available for viewing". NY Daily News. Retrieved December 1, 2017.
  33. ^ Barone, Vin (November 30, 2017). "Tour the MTA's potential new subway cars". am New York. Retrieved December 1, 2017.
  34. ^ "Bombardier shut out of N.Y. subway contract because of 'poor performance'". Montreal Gazette. August 30, 2017. Retrieved August 31, 2017.
  35. ^ Jump up to: a b "Kawasaki vying for $3.2 billion New York subway order". 1330 & 101.5 WHBL. Midwest Communications. August 31, 2017. Retrieved September 1, 2017.
  36. ^ Jump up to: a b "Capital Program Oversight Committee Meeting January 2018" (PDF). web.mta.info. Metropolitan Transportation Authority. Retrieved January 19, 2018.
  37. ^ https://new.mta.info/sites/default/files/2019-09/MTA%202020-2024%20Capital%20Program%20-%20Full%20Report.pdf page 185/PDF page 187
  38. ^ "S-48013 R179/R211 Carborne Equipment for the CBTC 8th Avenue Line" (PDF). mta.info. Metropolitan Transportation Authority. December 14, 2018. Retrieved January 20, 2019.
  39. ^ Jump up to: a b c d e f "Capital Program Oversight Committee Meeting" (PDF). Metropolitan Transportation Authority. January 2019. Retrieved January 18, 2019.
  40. ^ Martinez, Jose (November 29, 2020). "Subway Slowdown: Sleek New Train Cars Running Late in Pandemic". THE CITY. Retrieved November 30, 2020.
  41. ^ "Newest MTA Train Model Continues to Face Delays Amid COVID-19". www.ny1.com. Retrieved April 2, 2021.
  42. ^ Jump up to: a b c d "Capital Program Oversight Committee Meeting". Metropolitan Transportation Authority. June 23, 2021. Retrieved January 18, 2019.
  43. ^ "Next generation MTA subway car arrives in NYC for testing". PIX11. June 30, 2021. Retrieved July 1, 2021.
  44. ^ "First Kawasaki R211 Subway cars arrive in New York". Railway Gazette International. July 2, 2021. Retrieved July 8, 2021.
  45. ^ Guse, Clayton (July 1, 2021). "MTA's newest subway cars arrive in NYC — more than a year late". New York Daily News. Retrieved July 2, 2021.

External links

Retrieved from ""