Railway platform height

From Wikipedia, the free encyclopedia

Typical commuter rail station in Boston, Massachusetts, with two platform heights: low-level for most cars and a full height platform to accommodate passengers in wheelchairs.

Railway platform height is the built height – above top of rail (ATR) – of passenger platforms at stations. A connected term is train floor height, which refers to the ATR height of the floor of rail vehicles. Worldwide, there are many, frequently incompatible, standards for platform heights and train floor heights. Where raised platforms are in use, train widths must also be compatible, in order to avoid both large gaps between platform and trains and mechanical interference liable to cause equipment damage.

Differences in platform height (and platform gap) can pose a risk for passenger safety. Differences between platform height and train floor height my also make boarding much more difficult, or impossible, for wheelchair using passengers and people with other mobility impairments, increasing station dwell time as platform or staff are required to deploy ramps to assist boarding. Platform ramps, steps, and platform gap fillers together with hazard warnings such as "mind the gap" are used to reduce risk and facilitate access. Platform height affects the loading gauge (the maximum size of train cars), and must conform to the structure gauge physical clearance specifications for the system. Tracks which are shared between freight and passenger service must have platforms which do not obstruct either type of railroad car.

To reduce construction costs, the platforms at stations on many railway systems are of low height, making it necessary for passenger cars to be equipped with external steps or internal stairs allowing passengers access to and from car floor levels. When railways were first introduced in the 19th century, low platforms were widely used from the 1880s, especially in rural areas, except in the United Kingdom. Over the years, raised platforms have become far more widespread, and are almost universal for high-speed express routes and universal in cities on commuter and rapid transit lines. Raised platforms on the narrow gauge railways can prevent track gauge conversion to standard gauge or broad gauge.

Height categories[]

Low floor tram platform in Cologne

Buses, trams, trolleys and railway passenger cars are divided into several typical categories.

  • Ultra Low Floor tram – 180 mm (7 in)
  • Low floor tram – 300 to 350 mm (12 to 14 in)
  • High floor tram – more than 600 mm (24 in)
  • Low floor train – 550 mm (22 in)
  • Train (in UK or narrow gauge) – 800 to 1,200 mm (31.5 to 47.2 in)
  • Standard North American passenger cars – 1,300 mm (51 in)
  • Train (standard gauge (except UK) or broad gauge) – 1,300 to 1,370 mm (51 to 54 in)

These are floor heights. The platforms can be much lower, overcome by onboard staircases.

Africa[]

Algeria[]

Typical Algerian platforms are 550 mm (21.7 in) above rail.

Kenya[]

The 1,435 mm (4 ft 8+12 in) SGR platforms are two standard heights of 300 mm (11.8 in) and 1,250 mm (49.2 in) above rail heads. The 1,000 mm (3 ft 3+38 in) meter gauge platforms are 1100mm.

Asia[]

China[]

A Platform at consists of both "low" and "high platform".

China Railway platforms are classified into the following categories of "low" 380 mm (15.0 in), "medium" 550 mm (21.7 in), "high" 760 mm (29.9 in) and "ultra high" 1,250 mm (49.2 in) (latter 2 for most new and rebuilt platforms). Areas adjacent to broad gauge countries/regions, such as Xinjiang and Inner-Mongolia, are still equipped with low platforms. Under the concession period since late 2016, platforms on the southeastern corridor from Shenzhen to Ruili to be 1,250 mm (49.2 in) ATR, whereas the northern-, central-, and western-Chinese platforms to be 380 mm (15.0 in) ATR, are recommended.

Most CRH platforms are 1,250 millimetres (49.2 in) above top of rail, with the remainders being 760 millimetres (29.9 in).

The proposed 1,524 mm (5 ft) Russian gauge [note 1] platforms will be 200 mm (7.9 in) above rails.

Hong Kong[]

MTR network[]

Platforms on the MTR are 1,250 mm (49.213 in) above the rail for the Tung Chung Line and Airport Express, collectively known as the Airport Railway.[1] The height of those on other lines (excluding Kowloon Southern Link and Sha Tin to Central Link) built by MTR is 1,100 mm (43.307 in) .

Pre-KCR network[]

East Rail line platforms are 42 in (1,066.8 mm) high.[2] Since all the former KCR lines excluding light rail are built to the same specs, the platform height on the West Rail line, Ma On Shan line, as well as the MTR-built Kowloon Southern Link and Sha Tin to Central Link is also 3 feet 6 inches (1066.8 mm) high.

XRL network[]

Platforms at Hong Kong West Kowloon railway station are 1,250 mm (49.213 in) above the rail, to adopt the standard of High-speed rail in China.

India[]

There are two standard heights of the platforms, 200 mm (7.9 in) and 760 mm (29.9 in) above rail heads.

Indonesia[]

There are three standard heights of the platforms, 180 mm (7.1 in) (low), 430 mm (16.9 in) (medium), and 1,000 mm (39.4 in) (high) above rail heads.[3] Most railway stations in Indonesia use low platforms.[4]

Iran[]

Iranian platforms are 380 mm (15.0 in), 550 mm (21.7 in) and 760 mm (29.9 in). Like in China, areas adjacent to broad gauge countries/regions such as the eastern regions such as around Mashhad and Zahedan, still equipped low platforms.

Israel[]

Israel Railways platforms fall in the range between 760 mm (29.9 in) to 1,060 mm (41.7 in) above top of rail.[5]

Japan[]

The Japanese National Railways (JNR) for many years used a triple-standard for its conventional (Cape gauge) lines:

  • 760 mm (29.9 in) for long-distance trains (originally step-fitted passenger cars pulled by steam engines);
  • 1,100 mm (43.3 in) for commuter trains (step-less electric multiple units at a time when long-distance trains were not); and
  • 920 mm (36.2 in) shared platforms that could serve both with relatively little discomfort (roughly level with the step on passenger carriages but not too low to board commuter trains).

However, increasing electrification and the phasing-out of locomotive traction in favor of multiple units has made the distinction a matter of historical, rather than practical relevance. Recently, at Japan Railways Group stations in urban centers such as Tokyo and Osaka, whose lines were the earliest to be electrified, 1,100 mm (43.3 in) is the norm and lower-level platforms are generally raised to this height during station improvements or refurbishment. Elsewhere, such as Hokkaido and the Tohoku/Hokuriku region of Honshu, 920 mm (36.2 in) – and even 760 mm (29.9 in) platforms are still commonplace. As this represents a potential obstacle when boarding modern commuter trains, workarounds such as a step built into the floor of area-specific trainsets are often employed. Nevertheless, with accessibility becoming a greater concern as Japan's population ages, raising the level of the platform itself (in tandem with other improvements such as elevators and escalators) is seen as the most practical solution.

In at least one case, with the E721 series EMU used on JR East lines in the Tohoku region, the floor of the train itself is lowered to be nearly level to existing 920 mm (36.2 in) platforms. This makes level boarding feasible at many stations (and boarding less of a hassle at stations with the lowest 760 mm (29.9 in) platforms). However, this (along with a different standard of electrification) also makes through service southward to Tokyo impossible, and prevents them from running on certain through lines, such as the Senseki-Tohoku Line, since the Senseki Line portion uses the higher 1,100 mm (43.3 in) platforms (and DC electrification).

In contrast to the above standards, the standard gauge Shinkansen (Bullet Train) has, since its original inception, used only 1,250 mm (49.2 in) platforms. However, exceptions from this include the "Mini-Shinkansen" Yamagata Shinkansen and Akita Shinkansen lines, which use 1,100 mm (43.3 in) platforms to maintain compatibility with conventional JR trainsets.

Most standard gauge non-JR commuter railways, such as Kintetsu Nara Line and Keisei Line, use 1,250 mm (49.2 in) platforms.

North Korea[]

North Korean platforms are standardized at 1,250 mm (49.2 in) only. In there, 1,250 mm (49.2 in) is the norm, lower-level platforms are already raised to this height.

South Korea[]

Korail adopted 550 mm (21.7 in) high platforms to operate KTX. Typically, older platforms are lower than 500 mm. For metro trains, higher platforms which height after 1,135 mm (44.7 in)[6] are used. Nuriro trains are using mechanical steps to allow both type of platforms. Korail has a long-term plan to change platform standards to higher platforms; both KTX-Eum and EMU-320 are designed to use higher platforms.

Taiwan[]

Taiwan high-speed rail platforms are 1,250 mm (49.2 in) above rail.

Example of a platform whose height was raised.

Initially, Taiwan Railways Administration platforms were 760 mm (29.9 in) tall and passengers must take two stair steps to enter the train. In 2001, the platforms were raised to 960 mm (37.8 in), cutting the steps needed to one. Between 2016 and 2020, platforms were again raised to 1,150 mm (45.3 in), and the unnecessary gap on trains were filled in.[7]

Thailand[]

Old railway platforms are usually less than 500mm (20 in) in height. New platforms along double tracking projects, red line projects, and metro stations are built at 1,100 mm (43.3 in) height, with the exception of the new Southern line doubling project, which will be built to roughly 550-760mm height. Bang Bamru station is built with both high and low platforms.

Eurasia[]

Russia[]

There are two standard heights of platforms in Russia; they are 200 and 1,100 mm (7.9 and 43.3 in) above rail heads. 1,100 mm (43.3 in) high platforms are gradually changing to 550 mm (21.7 in) platform height.[8] 200 mm (7.9 in) platforms are used primarily on lines with either small passenger flow or using double-decker trains.[citation needed]

In late 2015, there are three standard heights of platforms, which include:

  • 200 mm (7.9 in) for long-distance trains (originally locomotive-hauled step-fitted passenger carriages);
  • 1,100 mm (43.3 in) for direct-current only commuter trains (step-less direct current commuter electric multiple units at a time when long-distance trains were not); and
  • 550 mm (21.7 in) for shared platforms that could serve both with relatively little discomfort (roughly level with the steps on passenger carriages but not too low to board commuter trains).

In some urban areas, such as Moscow and St Petersburg, served only by local traffic, use 1,100 mm (43.3 in) platforms for direct-current electric multiple units. Elsewhere, 550 mm (21.7 in) - and even 200 mm (7.9 in) platforms are almost commonplace. In some cases, such as VR Sm4 of Finland, the floor of the train itself lowered to be nearly level to 550 mm (21.7 in) platforms. This makes level boarding feasible at some stations (and boarding less of a hassle at stations with the lowest 200 mm (7.9 in) platforms).

The proposed 1,676 mm (5 ft 6 in) Indian gauge [note 2] platforms will be 200 mm (7.9 in) above rails.

Turkey[]

In Turkey, the standard platform height for commuter railways is 1,050 mm (41.3 in) and for mainline & high-speed railways it's 550 mm (21.7 in). But most of the platforms throughout the network are old and thus out of standard.

Kazakhstan[]

In Kazakhstan, only Astana Nurly Jol station and Russian Railway's Petropavlovsk station have 550 mm (21.7 in) platforms. Almost everywhere else, the platforms are 200 mm (7.9 in) above the rails.

Europe[]

Multi-country[]

European Union[]

Application of the EU standard heights for new construction; Green = 550 mm, Blue = 760 mm, Turquoise = both, dark gray = New builds in other heights than the EU standards

The European Union Commission issued a TSI (Technical Specifications for Interoperability) on 30 May 2002 (2002/735/EC) that sets out standard platform heights for passenger steps on high-speed rail. These standard heights are 550 and 760 mm (21.7 and 29.9 in) .[9][note 3] The 550 mm (21.7 in) for most member states, 760 mm (29.9 in) for Great Britain / Netherlands / Spain / Portugal, and 915 mm (36.0 in) for Ireland / Northern Ireland.

Broad-gauge railways[]

The proposed 1,520 mm (4 ft 11+2732 in) (Russian gauge) railways (e.g. Arctic Railway and Kosice-Vienna broad gauge line) and the proposed 7 ft 14 in (2,140 mm) (Brunel gauge) railways will be 200 mm (7.9 in) for Sweden and Norway, 200 mm (7.9 in) and 550 mm (21.7 in) for Poland and Slovakia, and 380 mm (15.0 in) for Germany and Austria.

Channel Tunnel[]

Platforms for Eurotunnel Shuttle are 1,100 mm (43.3 in) above rails.

Rail Baltica[]

The 1,435 mm (4 ft 8+12 in) European standard gauge Rail Baltica II platforms will be 550 mm (21.7 in)[11] above rails.

Belgium[]

Belgium has been using mixed type of platform heights (due to the age of the network, and the different companies running it before 1923). As of 2017 the most common platform heights for small stop places and stations are low platform heights of 280 mm (11.0 in).[12]

There is nevertheless a plan to comply with the European TSI by raising all low platform heights to one of the European Standard Heights. Most stations will by then be equipped with 550 mm platforms, and direct current EMUs dedicated platforms will be upgraded in their final version to 760 mm. Some stations, or stopping points, already having 760 mm platform heights will keep the platforms at these heights.

Finland[]

In Finland, the current standard platform height is 550 mm (21.7 in). Platforms that have not been upgraded to enable level entry are built to the older standard of 265 mm (10.4 in) above top of rail.[13]

The sole exception on the national railway network is the Nikkilä halt which has a platform height of 400 mm (15.8 in).[13]

Germany[]

Triple gauntlet track at Kaufungen, Germany. Wider mainline trains go down the centre; narrower trams switch either to the left, or right, to be closer to the relevant platform. Beyond the station, the rails return to single track.

Germany's EBO standard (Ordinance on the Construction and Operation of Railways) specifies an allowable range of 380 mm (15.0 in) to maximal 960 mm (37.8 in) .[14] This would not include light rail systems that follow the BOStrab standard (Ordinance on the Construction and Operation of Tramways) with newer metro lines to use low-floor trams which have a usual floor height of 300 to 350 mm (11.8 to 13.8 in) so that platforms are constructed as low as 300 mm in accordance with BOStrab that requires the platform height not to be higher than the floor height.[15]

The traditional platforms had a very diverse height as the nationwide railway network is a union of earlier railway operators. Prior to followed by the European TSI standard the EBO standard requires that new platform construction be at a regular height of 760 mm (29.9 in) .[14][clarification needed] The TSI standard of 550 mm (21.7 in) height, historically common in the East, is widely used on regional lines. Only the S-Bahn suburban rail systems had a higher platform height and these are standardized on 960 mm (37.8 in).[14]

Ireland[]

While older platforms on the Dublin and Kingstown Railway were at lower levels, all platforms are now 915mm above rail and all new platforms are being built at that level. Amongst other work, there is an ongoing program of platform renewal. Both Irish railway companies (Irish Rail in the Republic of Ireland and Northern Ireland Railways in Northern Ireland) have had some derogations from EU standards as their mainline rail systems, while connected to each other, are not connected to any other system.

The electric DART fleet has carriage floors at 1,067 mm (42.0 in) above top of rail creating a step of 152 mm (6.0 in) , while the diesel fleet is typically one step (150 to 200 mm or 5.9 to 7.9 in) higher than the platform.

On Dublin's Luas tram system, platforms are approximately 280 mm (11 in) above rail. Tram floors are at the same height, but have internal steps over the bogies.

Luxembourg[]

The 760 mm (29.9 in) platforms for the Namur-Luxembourg line (with 3kV DC electrification). The remainder of the network, the platforms are 380 mm (15.0 in) above rails.

Netherlands[]

European Commission decision 2002/735/EC which concerns trans-European interoperability for high-speed rail specifies that rolling stock be built for operational suitability platform height of 840 mm (33.1 in) .[9] Dutch infrastructure maintainer ProRail has committed to upgrading all stations to 760 mm (29.9 in) platform height.[16][17]

Poland[]

Typical Polish platform is 760 mm (29.9 in) high. In some rural or urban/suburban areas (e.g. around Warsaw) platforms used by local traffic are lower or higher (550 to 1,060 mm or 21.7 to 41.7 in). All newly built platforms are 760 mm (29.9 in) high.

Spain[]

While older Spanish platforms are lower than the rest of Europe, many platforms are now 680 mm above rail. Following track gauge conversion from Iberian gauge to standard gauge, platforms to be raised to 1,250 mm (49.2 in) for new regional trainsets.

Sweden[]

Sweden has generally 380 to 580 mm (15.0 to 22.8 in) platforms for mainline trains. Stockholm Commuter Rail has almost always its own platforms at 730 mm (28.7 in) height which allows stepless trains of type X60. The Arlanda Express service has 1,150 mm (45.3 in) platform height with floor at platform level. They have their own platforms and trains, which are incompatible with mainline platforms and trains, even if the Arlanda Express goes on a mainline. The stations Sundbyberg and Knivsta have one platform each used by both commuter trains and regional mainline trains, which can cause uncomfortable steps, but is accepted. Sundbyberg has 730 mm and Knivsta has around 500 mm. Stockholm Central station has after the commuter trains moved to the "City" station, two high 730 mm platforms, now used for mainline trains. The Stockholm Metro and Saltsjöbanan have 1,125 mm (44.3 in),[18] while tramways in general have a very low platform, often also used by buses which must allow boarding from places without platform.

United Kingdom[]

The standard height for platforms is 915 mm with a margin of +0,-25 mm.[9][19] On the Heathrow Express the platform height is specified at 1,100 mm (43.3 in) .[20]

High Speed 2 is being built with a platform height of 1,115 mm, which does not conform to the European Union technical standards for interoperability for high-speed rail (EU Directive 96/48/EC).[21] This is to provide true step free access to trains at the new HS2 stations, which is not possible using European Standards or UK standard heights. HS2 trains will operate outside of the HS2 line using existing infrastructure, which will not be step free.[22] High Speed 1 has a platform height of 760 mm (29.9 in) on its international platforms.[23] The Great Western Main Line, North London Line, Gospel Oak to Barking Line and Great Eastern Main Line platforms will be mixture of 760 mm (29.9 in) (for intercity trains) and 1,100 mm (43.3 in) (for London commuter trains).

France[]

The standard height for all platforms is 550 mm (21.7 in), following the european guidelines. However, this rule is not respected for parts of the RER and Transilien network.

North America[]

Canada[]

Intercity and commuter rail[]

Via Rail intercity trains have level boarding with platforms 48 inches (1,219 mm) above the top of rail at Montreal Central Station, Quebec City Gare du Palais and Ottawa station.[citation needed] The remainder of stations in the Via Rail network have low platforms 5 inches (127 mm) to 8 inches (203 mm) above the rail.[citation needed]

GO Transit regional trains have a floor height of 610 millimetres (24 in) above the top of rail, and GO Transit plans to raise platforms to provide level boarding at that height.[24] Currently, platforms are 127 millimetres (5 in) above the top of rail, with a raised "mini-platform" which provides level boarding from one door of the train.[24]

Exo commuter trains have level boarding with platforms 48 inches (1,219 mm), 50 inches (1,270 mm), or 51 inches (1,295 mm) above the top of rail at Montreal Central, Côte-de-Liesse, Repentigny, Terrebonne, and Mascouche stations. [25] The remainder of stations in the Exo network have low platforms 5 inches (127 mm) or 8 inches (203 mm) above the top of rail.[25]

All UP Express stations have level boarding with platforms 48 inches (1,219 mm) above the top of rail.[citation needed]

Metro and light rail[]

All rapid transit and light rail systems, except for the Toronto streetcar system, provide level boarding between trains and platforms. The platform heights vary per line, as per the table below.

City Network/Line Platform Height
Calgary C-Train LRT 890 millimetres (35 in)
Edmonton High-Floor LRT 890 millimetres (35 in)[26]
Low-Floor LRT 329 millimetres (13 in)
Kitchener-Waterloo Ion LRT 329 millimetres (13 in)[27]
Montreal Metro Unknown
REM Unknown
Ottawa Electric LRT (Lines 1,3) unknown
Diesel LRT (Lines 2,4) 553 millimetres (22 in)[28]
Toronto Subway (Lines 1,2,4) 1,105 millimetres (44 in)[29]
RT (Line 3) Unknown
LRT (Lines 5,6) 329 millimetres (13 in)
Vancouver Skytrain Unknown

On the Toronto streetcar system, most stops are in mixed traffic accessed from the road surface, without raised platforms. Where raised platforms do exist, they are at sidewalk curb height and not at the height of the vehicle floor. As a result, people using wheeled mobility aids need to use the wheelchair ramp even at stops where a raised platform exists.

United States[]

Gauntlet track on Conrail Shared Assets Operation Lehigh Line at New Jersey Transit's Raritan Valley Line Union station. Freight trains run on the outer track so as to clear the platform

New and substantially renovated stations in the United States must comply with Americans with Disabilities Act (ADA), which requires level boarding. Most intercity and commuter rail systems use either 48-inch (1,219 mm) high platforms level with car floors or 8-inch (203 mm) low platforms, while metro and light rail systems use a range of platform heights.

Intercity and commuter rail[]

Most commuter rail systems in the northeastern United States have standardized on 48-inch (1,219 mm) high platforms. This height was introduced in the 1960s on the Long Island Rail Road with the M1 railcars.[30]: 212 MBTA Commuter Rail, CTrail (Hartford Line and Shore Line East), Long Island Rail Road, Metro-North Railroad, NJ Transit, and SEPTA Regional Rail all use this height for new and renovated stations, though low platforms remain at some older stations. Outside the Northeast, Metra Electric District, RTD, WES Commuter Rail, and SMART also use 48-inch platforms.[31] MARC has high-level platforms at most Penn Line stations; low platforms are used on the Camden Line and Brunswick Line due to freight clearances, except at stations with passing tracks (Greenbelt) or off freight routes (Baltimore-Camden, and Monocacy).

Amtrak intercity service uses high-level platforms on the Northeast Corridor, Keystone Corridor, Empire Corridor, and New Haven–Springfield Line; some stations on the lines have not been retrofitted with high platforms. High-level platforms are also present at a small number of stations on other lines, including Worcester, Roanoke, Raleigh, and several Downeaster stations. Brightline service in Florida also uses high level platforms.

At some stations, a desired high-level platform is impractical due to wide freight trains or other practicalities. (Gauntlet tracks, which permit wide freights to pass full-length high-level platforms, have practical issue of their own.) At these locations, mini-high platforms are often used for accessibility. Mini-high platforms have a short length of high platform (long enough for one or two doors), with an accessible ramp to the longer low platform. The platform edge is usually hinged so that it can be flipped out of the way of passing freights.

Most other US commuter rail systems and other Amtrak stations have 8-inch (203 mm) low-level platforms to accommodate freight service, with mini-high platforms or portable lifts to reach the 25-inch (640 mm)-high floors of bilevel railcars. Coaster uses 22-inch (559 mm) platforms.[31] Once electrified, new Caltrain trains will be equipped for both 22-and-50.5-inch (559 and 1,283 mm) platform heights in anticipation of sharing facilities with California High-Speed Rail trains.[32]

Metro and light rail[]

Platform heights of metro systems vary by system and even by line: on the MBTA subway system, the Blue Line platforms are at 41.5 inches (1,054 mm) above top of rail (ATR), Orange Line platforms at 45 inches (1,143 mm) and Red Line platforms at 49 inches (1,245 mm).[33] Bay Area Rapid Transit stations have platform heights of 39 inches (991 mm).[34]

Most light rail systems have platforms around 12–14 inches (300–360 mm) ATR, allowing level boarding on low-floor light rail vehicles. Most new systems are built to this standard, and some older systems like VTA light rail have been converted. Several systems including MetroLink use higher platforms with level boarding. Several older light rail systems have high-floor vehicles but low platforms, with mini-high platforms or lifts for accessibility. Some like the MBTA Green Line are being converted to low-floor rolling stock, while some like Baltimore Light Rail have permanent mini-high platforms. Muni Metro has 34-inch (864 mm) high platforms in the subway and some surface stops, and mini-high platforms at other surface stops; the vehicles have movable steps to serve both high and low platforms.[35]

Oceania[]

Australia[]

The majority of railway systems in Australia use high level platforms with a platform height a small distance below the train floor level. Exception to this include Queensland who have narrow gauge trains and lower platforms, and South Australia who have trains fitted with low level steps to enable the use of low level platforms.[citation needed]

In New South Wales, by 2000, the platform step (the difference between the platform height and the train floor height) had been allowed to grow to a maximum of about 300 mm (11.8 in), which was uncomfortably large. For Sydney's 2000 Olympics, new and altered platforms were designed to match the Tangara trains, which are 3,000 mm (9 ft 10+18 in) wide, leaving a platform gap of about 80 mm (3+18 in) and a step height close to zero. This has become the standard for all subsequent platforms and trains in NSW.

Metro and light rail[]

The tramway network in Melbourne have some low level platforms and low floor vehicles, but most trams have steps and are boarded from the road. The Adelaide Tram line has low platforms at almost all stops and operates almost entirely with low-floor trams which also have retractable ramps for street boarding where required by persons unable to step up.[citation needed] The Gold Coast and Sydney light rail networks have low floor trams and platforms at all stops.

South America[]

Argentina[]

Platforms for long-distance trains are 200 mm (7.9 in) above rail, and platforms for Buenos Aires commuter trains are 1,100 mm (43.3 in).

See also[]

Notes[]

  1. ^ The proposed 1,524 mm (5 ft) Russian gauge railways for northern China which will seamless link with Russia, Mongolia and Kazakhstan.
  2. ^ The proposed 1,676 mm (5 ft 6 in) Indian gauge railways which will seamless link from the Indian subcontinent to the Russian Far East and the Russian Arctic, through Central Asia.
  3. ^ In reference to EU documentation on interoperability of trans-national high-speed rail (see EU Directive 96/48/EC) platform height is measured from the top of the running surface of the rail.[10]

References[]

  1. ^ Redevelopment of Kowloon Station, 1995, HKU Scholars Hub
  2. ^ Under the Wires to Lo Wu, The Railway Magazine, November 1983
  3. ^ "Peraturan Menteri Perhubungan Nomor PM. 29 Tahun 2011 tentang Persyaratan Teknis Bangunan Stasiun Kereta Api" [Regulation of the Minister of Transportation Number PM. 29 of 2011 concerning Technical Requirements for Railway Station Buildings] (PDF) (in Indonesian). Ministry of Transportation. Retrieved 11 January 2021.
  4. ^ Syamsudin, M. (5 August 2011). "Aspek Yuridis Pembangunan Peron Tinggi di Stasiun Kereta Api sebagai Sarana Perlindungan Hukum Konsumen" [Juridical Aspects of Construction of High Platforms at Railway Stations as a Means of Protection of Consumer Laws]. Prosiding SNaPP: Sosial, Ekonomi dan Humaniora (in Indonesian). 2 (1): 345–352. ISSN 2303-2472. Retrieved 11 January 2021.
  5. ^ "TENDER No. 51403 for the Supply and Maintenance of Electric Multiple Units: Technical Specifications" (PDF). www.rail.co.il. Retrieved 19 November 2020.
  6. ^ "Info". www.law.go.kr. Retrieved 8 September 2019.
  7. ^ "台鐵車廂無階化 2020年全達標". China Times. Retrieved 14 September 2020.
  8. ^ "ГОСТ 9238-2013". 1 July 2014.
  9. ^ Jump up to: a b c 2002/735/EC, sections 7.3.4 and 4.2.5
  10. ^ "Commission Recommendation of 21 March 2001 on the basic parameters of the trans-European high-speed rail system referred to in Article 5(3)(b) of Directive 96/48/EC". eur-lex.europa.eu. European Union. 21 March 2001. section 6.1. Retrieved 7 March 2013. Platform height is measured between the track running surface and the platform surface along the perpendicular
  11. ^ "Technical Standards and Specifications Manual of Rail Baltica" (PDF).
  12. ^ "De Belgische Kamer van volksvertegenwoordigers". www.dekamer.be.
  13. ^ Jump up to: a b Finnish Transport Infrastructure Agency (2019). Railway Network Statement 2021 (PDF). Helsinki: Finnish Transport Infrastructure Agency. pp. Appendix 3B 13–24. ISBN 978-952-317-744-4.
  14. ^ Jump up to: a b c "Eisenbahn-Bau- und Betriebsordnung (EBO)" (PDF) (in German). Bundesministeriums der Justiz / juris GmbH. Section 13: Bahnsteige, Rampen. Retrieved 7 March 2013. 13.1 : Bei Neubauten oder umfassenden Umbauten von Personenbahnsteigen sollen in der Regel die Bahnsteigkanten auf eine Höhe von 0,76 m über Schienenoberkante gelegt werden; Höhen von unter 0,38 m und über 0,96 m sind unzulässig. Bahnsteige, an denen ausschließlich Stadtschnellbahnen halten, sollen auf eine Höhe von 0,96 m über Schienenoberkante gelegt werden. In Gleisbogen ist auf die Überhöhung Rücksicht zu nehmen
  15. ^ BOStrab § 31 (1) "Haltestellen sollen Bahnsteige besitzen (...)."; § 31 (8) "Die Bahnsteigoberfläche soll nicht höher liegen als der Fahrzeugfußboden in seiner tiefsten Lage (...)."
  16. ^ "Network Statement 2010 Combined Network based on the Railways Act" (PDF). www.prorail.nl. Prorail. 12 December 2008 (22 January 2009). Archived from the original (PDF) on 21 October 2012. Retrieved 7 March 2013. Check date values in: |date= (help)[failed verification]
  17. ^ "ProRail invests 450 million euros in accessibility". www.prorail.nl (Press release). Prorail. 13 October 2009. Archived from the original on 28 November 2010.
  18. ^ "Lokaliseringsutredning Sofia-Gullmarsplan/söderort" (PDF).
  19. ^ Ellis' British Railway Engineering Encyclopaedia. Iain Ellis. 2006. ISBN 9781847286437. Retrieved 7 March 2013.
  20. ^ Institution of Mechanical Engineers (Great Britain). Railway Division, Institution of Civil Engineers (Great Britain) (2001). Railway infrastructure, Issue 3. John Wiley and Sons. 3.1.2 Specification of the System, p.19. ISBN 9781860583506.
  21. ^ Department for Transport (11 March 2010). High Speed Rail – Command Paper (PDF). The Stationery Office. section 8.4, p.127. ISBN 978-0-10-178272-2.
  22. ^ https://www.railengineer.co.uk/2019/03/01/buying-hs2s-high-speed-trains/
  23. ^ "HS1 Network Statement" (PDF). www.highspeed1.com. 17 August 2009. section 3.3.1.2 "Track Gauge & Structure Gauge", page 14. Archived from the original (PDF) on 14 April 2014. Retrieved 7 March 2013.
  24. ^ Jump up to: a b "Level Boarding: Passive Protection" (PDF). GO Transit. Retrieved 10 May 2021.
  25. ^ Jump up to: a b "Plan de développement accessibilité - AMT". Agence Métropolitaine du Transport. Retrieved 11 May 2021.
  26. ^ "LRT Design Guidelines" (PDF). City of Edmonton. Retrieved 10 May 2021.
  27. ^ "Design and construction performance output specifications" (PDF). Region of Waterloo. Retrieved 10 May 2021.
  28. ^ "Ottawa LRT Schedule 15-2" (PDF). Retrieved 10 May 2021.
  29. ^ "T1 Series Cars". TransitToronto. Retrieved 11 May 2021.
  30. ^ Cudahy, Brian J. (2003). A Century of Subways: Celebrating 100 Years of New York's Underground Railways. New York: Fordham University Press. ISBN 0-8232-2292-6.
  31. ^ Jump up to: a b SMA Rail Consulting (April 2016). "California Passenger Rail Network Schematics" (PDF). California Department of Transportation.
  32. ^ "KISS Double-Decker Electric Multiple Unit EMU for Peninsula Corridor Joint Powers Board (CALTRAIN), California, USA" (PDF). Retrieved 16 October 2016.
  33. ^ Robin Washington (25 February 2015). "On the T, One Sized Doesn't Fit All". Boston Globe. Retrieved 21 January 2019.
  34. ^ "BART-San Francisco Airport Extension Final Environmental Impact Report/Final Environmental Impact Statement". Federal Transit Administration. June 1996. pp. 3–501 – via Internet Archive.
  35. ^ "S200 SF Light Rail Vehicle" (PDF). Siemens. Retrieved 18 May 2016.

Sources[]

External links[]

Retrieved from ""