Artemis program

From Wikipedia, the free encyclopedia

Artemis program
An arrowhead combined with a depiction of a trans-lunar injection trajectory forms an "A", with an "Artemis" wordmark printed underneath
CountryUnited States
OrganizationNASA and partners
PurposeCrewed lunar exploration
StatusOngoing
Program history
CostUS$35 billion (2020–2024)[1]
Duration2017–present[2]
First flightArtemis 1 (NET 22 November 2021)
First crewed flightArtemis 2 (NET September 2023)[3]
Launch site(s)
  • Cape Canaveral Space Force Station
  • Kennedy Space Center
  • Starbase, Phobos, or Deimos (Starship HLS)
Vehicle information
Crewed vehicle(s)
  • Orion
  • Starship HLS
  • Lunar Gateway
Launch vehicle(s)
  • Space Launch System[4]
  • Starship
  • Commercial launch vehicles[5]

The Artemis Program is a United States-led international human spaceflight program. It was launched in 2017 under the Trump administration with the primary goal of returning humans to the Moon, specifically the lunar south pole, in the mid-2020s (first crew in 2024).[2][6] If successful, it will be the first crewed lunar mission since the end of the Apollo program in 1972.

The Artemis Program formally began in December 2017 as the culmination of successive efforts to revitalize the U.S. space program since 2009. Its stated short-term goal is landing the first woman on the Moon; mid-term objectives include establishing an international expedition team and a sustainable human presence on the Moon, long-term objectives are laying the foundations for private companies to build a lunar economy, and eventually, make sending humans to Mars and beyond feasible.[7]

The Artemis Program is carried out predominantly by NASA and U.S. commercial spaceflight contractors, in partnership with the space agencies of Europe, Luxembourg, Japan, Canada, Italy,[8] Australia, the United Kingdom, United Arab Emirates,[9][10] Ukraine, Brazil,[11] South Korea[12] and New Zealand.[13] Other nations are invited to join the program through signing the governing Artemis Accords, which remain open for signature since October 2020.

In February 2021, the succeeding Biden administration officially endorsed the Artemis Program.[14] In April 2021, NASA contracted with SpaceX to develop, manufacture, and operate two lunar missions with the Starship HLS lunar lander.[15]

History[]

Artistic rendering of the lunar module (left) and space capsule of the Constellation program
Artist’s impression of an early SLS launch

The current Artemis program incorporates several major components of previous canceled NASA programs and missions, such as the Constellation program and the Asteroid Redirect Mission. Originally legislated by the NASA Authorization Act of 2005, Constellation included the development of Ares I, Ares V, and the Orion Crew Exploration Vehicle. The program ran from the early 2000s until 2010.[16]

In May 2009, President Barack Obama established the Augustine Committee to take into account several objectives including support for the International Space Station, development of missions beyond low Earth orbit (including the Moon, Mars and Near-Earth objects) and utilization of the commercial space industry within defined budget limits.[17] The committee concluded that the Constellation program was massively underfunded and that a 2020 Moon landing was impossible. Constellation was subsequently put on hold.[18]

On 15 April 2010, President Obama spoke at the Kennedy Space Center, announcing the administration's plans for NASA and cancelling the non-Orion elements of Constellation on the premise that the program had become nonviable.[19] He instead proposed US$6 billion in additional funding and called for development of a new heavy lift rocket program to be ready for construction by 2015 with crewed missions to Mars orbit by the mid-2030s.[20]

On 11 October 2010, President Obama signed into law the NASA Authorization Act of 2010, which included requirements for the immediate development of the Space Launch System as a follow-on launch vehicle to the Space Shuttle and continued development of a Crew Exploration Vehicle to be capable of supporting missions beyond low Earth orbit starting in 2016, while maximizing, where possible, the use of the workforce, assets, and capabilities of the Space Shuttle, Constellation program and other NASA programs. The law also invested in space technologies and robotics capabilities tied to the overall space exploration framework, continued to support Commercial Orbital Transportation Services, Commercial Resupply Services and expanded the Commercial Crew Development program.[21]

On 30 June 2017, President Donald Trump signed an executive order to re-establish the National Space Council, chaired by Vice-President Mike Pence. The Trump administration's first budget request kept Obama-era human spaceflight programs in place: Commercial Resupply Services, Commercial Crew Development, the Space Launch System, and the Orion spacecraft for deep space missions, while reducing Earth science research and calling for the elimination of NASA's education office.[22]

On 11 December 2017, President Trump signed Space Policy Directive 1, a change in national space policy that provides for a U.S.-led, integrated program with private sector partners for a human return to the Moon, followed by missions to Mars and beyond. The policy calls for the NASA administrator to "lead an innovative and sustainable program of exploration with commercial and international partners to enable human expansion across the Solar System and to bring back to Earth new knowledge and opportunities". The effort intends to more effectively organize government, private industry, and international efforts toward returning humans on the Moon and laying the foundation of eventual human exploration of Mars.[2] Space Policy Directive 1 authorized the lunar-focused campaign. Artemis draws upon legacy US spacecraft programs including the Orion space capsule, the Lunar Gateway space station, Commercial Lunar Payload Services, and also creates entirely new programs such as the Human Landing System. The in-development Space Launch System is expected to serve as the primary launch vehicle for Orion, while commercial launch vehicles will launch various other elements of the campaign.[23]

On 26 March 2019, Vice President Mike Pence announced that NASA's Moon landing goal would be accelerated by four years with a planned landing in 2024.[24] On 14 May 2019, NASA Administrator Jim Bridenstine announced that the new program would be named Artemis, who is both the twin sister of Apollo and the goddess of the Moon in Greek mythology.[25] Despite the immediate new goals, Mars missions by the 2030s were still intended as of May 2019.[2]

In mid-2019, NASA requested US$1.6 billion in additional funding for Artemis for fiscal year 2020,[26] while the Senate Appropriations Committee requested from NASA a five-year budget profile[27] which is needed for evaluation and approval by Congress.[28][29]

In February 2020, the White House requested a funding increase of 12% to cover the Artemis program as part of its fiscal year 2021 budget. The total budget would have been US$25.2 billion per year with US$3.7 billion dedicated towards a Human Landing System. NASA Chief Financial Officer Jeff DeWit said he thought the agency has "a very good shot" to get this budget through Congress despite Democratic concerns around the program.[1] However, in July 2020 the House Appropriations Committee rejected the White House's requested funding increase.[30] The bill proposed in the House dedicated only US$700 million towards the Human Landing System, US$3 billion short of the requested amount.[31]

Throughout February 2021, Acting Administrator of NASA Steve Jurczyk reiterated those budget concerns when asked about the project's schedule,[32][33] clarifying that "The 2024 lunar landing goal may no longer be a realistic target [...]".[34]

On 4 February 2021, the Biden Administration endorsed the Artemis program.[35] More specifically, White House Press Secretary Jen Psaki expressed the Biden administration's "support [for] this effort and endeavor".[36][37][38]

On April 16, 2021, NASA contracted SpaceX to develop, manufacture, and fly two lunar landing flights with the Starship HLS lunar lander.[15]

Supporting programs[]

Implementation of the Artemis program will require additional programs, projects, and commercial launchers to support the construction of the Gateway, launch resupply missions to the station, and deploy numerous robotic spacecraft and instruments to the lunar surface.[39] Several precursor robotic missions are being coordinated through the Commercial Lunar Payload Services (CLPS) program, which is dedicated to scouting and characterization of lunar resources as well as testing principles for in-situ resource utilization.[39][40]

Models of the first three commercial robotic landers selected for CLPS. From left: Peregrine by Astrobotic Technology, Nova-C by Intuitive Machines, and Z-01 by OrbitBeyond.

Commercial Lunar Payload Services[]

In March 2018, NASA established the Commercial Lunar Payload Services (CLPS) program with the aim of sending small robotic landers and rovers mostly to the lunar south pole region as a precursor to and in support of crewed missions.[40][41][42] The main goals include scouting of lunar resources, in situ resource utilization (ISRU) feasibility testing, and lunar science.[43] NASA is awarding commercial providers indefinite delivery/indefinite quantity contracts to develop and fly lunar landers with scientific payloads.[44] The first phase considered proposals capable of delivering at least 10 kg (22 lb) of payload by the end of 2021.[44] Proposals for mid-sized landers capable of delivering between 500 kg (1,100 lb) and 1,000 kg (2,200 lb) of cargo were planned to also be considered for launch beyond 2021.[45]

In November 2018, NASA announced the first nine companies that were qualified to bid on the CLPS transportation service contracts (see list below).[46] On 31 May 2019, three of those were awarded lander contracts: Astrobotic Technology, Intuitive Machines, OrbitBeyond.[47] On 29 July 2019, NASA announced that it had granted OrbitBeyond's request to be released from obligations under the contract citing "internal corporate challenges".[48]

The first twelve payloads and experiments from NASA centers were announced on 21 February 2019.[49] On 1 July 2019, NASA announced the selection of twelve additional payloads, provided by universities and industry. Seven of these are scientific investigations while five are technology demonstrations.[50]

The Lunar Surface Instrument and Technology Payloads (LSITP) program was soliciting payloads in 2019 that do not require significant additional development. They will include technology demonstrators to advance lunar science or the commercial development of the Moon.[51][52]

In November 2019, NASA added five contractors to the group of companies who are eligible to bid to send large payloads to the surface of the moon with to the CLPS program: Blue Origin, Ceres Robotics, Sierra Nevada Corporation, SpaceX, and Tyvak Nano-Satellite Systems.[53][54]

In April 2020, NASA selected Masten Space Systems for a follow-on CLPS delivery of cargo to the Moon in 2022.[55][56]

In February 2021, NASA selected Firefly Aerospace for a CLPS launch to Mare Crisium in mid-2023.[57][58]

Commercial contractors selected for CLPS and HLS NASA-funded design work
Selection date Company Headquarters Element Proposed services Awarded contract
29 November 2018 Astrobotic Technology Pittsburgh, Pennsylvania CLPS Peregrine lander 31 May 2019
US$79.5 million[47]
Deep Space Systems Littleton, Colorado CLPS Rover; design and development services
Draper Laboratory Cambridge, Massachusetts CLPS Artemis-7 lander [46]
Firefly Aerospace Cedar Park, Texas CLPS Blue Ghost lander 4 February 2021
US$93.3 million[57]
Intuitive Machines Houston, Texas CLPS Nova-C lander 31 May 2019
US$77 million[47]
Lockheed Martin Space Littleton, Colorado CLPS McCandless Lunar Lander [46]
Masten Space Systems Mojave, California CLPS XL-1 lander 8 April 2020 [55][46]
US$75.9 million
Moon Express Cape Canaveral, Florida CLPS MX-1, MX-2, MX-5, MX-9 landers; sample return. [citation needed]
OrbitBeyond Edison, New Jersey CLPS Z-01 and Z-02 landers 31 May 2019
US$97 million [47][a]
18 November 2019 Blue Origin Kent, Washington CLPS / HLS Blue Moon lander [59]
Ceres Robotics Palo Alto, California CLPS [citation needed]
Sierra Nevada Corporation Louisville, Colorado CLPS [citation needed]
SpaceX Hawthorne, California CLPS / HLS Starship / Starship HLS [59]
Tyvak Nano-Satellite Systems Irvine, California CLPS [citation needed]
3 December 2020 Lunar outpost Golden, Colorado CLPS Rover [citation needed]

International contractors[]

Name Based Spacecraft
Ispace Tokyo,  Japan Hakuto-R
Ispace Europe  Luxembourg ?[60]
Toyota Toyota City,  Japan [61]
ArianeGroup Gironde,  France Space Launch System
ESAB Laxå Municipality,  Sweden Space Launch System
Augsburg,  Germany Space Launch System
Schweinfurt,  Germany Space Launch System
Magna Steyr Graz,  Austria Space Launch System
Airbus Ottobrunn  Germany Orion Service Module; Gateway Study; Study of Lunar ISRU Mission (ESA)
Fleet Space South Australia,  Australia 7 Sisters[clarification needed][62]
OZ Minerals Adelaide, South Australia,  Australia 7 Sisters
University of Adelaide Adelaide, South Australia,  Australia 7 Sisters
University of New South Wales Sydney, New South Wales,  Australia 7 Sisters
Unearthed Perth, Western Australia,  Australia 7 Sisters
MDA Brampton,  Canada Canadarm 3[63]

Artemis Accords[]

On 5 May 2020, Reuters reported that the Trump administration was drafting a new international agreement outlining the laws for mining on the Moon.[64] NASA Administrator Jim Bridenstine officially announced the Artemis Accords on 15 May 2020 will be a series of a bilateral agreements between the governments of participating nations in the Artemis program "grounded in the Outer Space Treaty of 1967".[65][7] The Artemis accords have been criticized by some American researchers as "a concerted, strategic effort to redirect international space cooperation in favor of short-term U.S. commercial interests".[66] The Accords were signed by the United States, Australia, Canada, Japan, Luxembourg, Italy, the United Kingdom, and the United Arab Emirates on 13 October 2020,[66] and later signed by Ukraine.[67][68] In May 2021, South Korea joined as 10th signatory state of the Artemis Accord,[69] with New Zealand following later the same month. Brazil became the 12th signatory country in June 2021.

Exploration Ground Systems (EGS)[]

Name Based
Knight Optical (USA) North Kingstown, Rhode Island
Sensing Systems Corporation New Bedford, Massachusetts
Altova Beverly, Massachusetts
Engility Andover, Massachusetts
Turbonomic Boston, Massachusetts
Mathworks Natick, Massachusetts
Dell EMC Hopkinton, Massachusetts
Alutiiq Fusion Joint Venture Anchorage, Alaska
Envirolux Energy Systems Vancouver, Washington
XPO Logistics Portland, Oregon
Gyro-Stabilized Systems Nevada City, California
Livermore Software Technology Corporation Livermore, California
New Tech Solutions Fremont, California
San Jose State University Research San Jose, California
Intel Santa Clara, California
Troian Industries Mountain View, California
Real Time Innovations Sunnyvale, California
New Directions Technology Ridgecrest, California
NIT Americans Simi Valley, California

Launch vehicles[]

As of the early mission concepts outlined by NASA in May 2020, launch vehicles planned to be used will include the NASA Space Launch System as well as commercial launch systems chosen and contracted for by the various commercial suppliers of the Human Landing System (HLS) elements: Blue Origin New Glenn, United Launch Alliance Vulcan Centaur, and SpaceX Starship[59] and Falcon 9,[70] as well as launch vehicles that are contracted for the various CLPS cargo providers. The European Ariane 6 was also proposed to be part of the program in July 2019.[71]

The Power and Propulsion Element (PPE) module and the Habitation and Logistics Outpost (HALO) of the Gateway, which were previously planned for the SLS Block 1B,[72] will now fly together on a Falcon Heavy in November 2024.[73][74] The Gateway will be supported and resupplied by approximately 28 commercial cargo missions launched by undetermined commercial launch vehicles.[75] The Gateway Logistics Services (GLS) will be in charge of the resupply missions,[75] as well for contracting the construction of a resupply vehicle capable to remain docked to the Gateway for one year of operations, provide and generate its own power while docked, and be capable of autonomous disposal at the end of its mission.[75][76]

In May 2019, the plan was for components of a crewed lunar lander to be deployed to the station on commercial launchers before the arrival of the first crewed mission, Artemis 3.[77] An alternative approach where the HLS and Orion dock together directly has been discussed and may still allow a 2024 crewed landing on the moon, but it is not completely clear NASA has committed to such a change.[78][79]

Although the Delta IV Heavy and Falcon Heavy were considered by NASA[when?] to launch a crewed Orion, the agency ultimately decided in 2019 to use only the SLS to launch astronauts.[5]

Launch Vehicles
Launch Vehicle Missions
Space Launch System Crew transportation and supplementary logistics
Falcon Heavy Dragon XL launches and the first two Gateway modules
Vulcan Centaur Parts of the Integrated Landing Vehicle and the Dynetics HLS along with CLPS missions
Falcon 9 CLPS missions
Electron CAPSTONE
New Glenn Modules of the Integrated Landing Vehicle
New Shepard Testing of SPLICE sensor suite to support future lunar landers.
Starship Starship HLS and heavy surface payloads
Ariane 6 ESPRIT and Heracles

Space Launch System[]

Diagram of four versions of the Space Launch System rocket
Planned evolution of the Space Launch System, the primary launch vehicle for Orion

The Space Launch System (SLS) is a United States super heavy-lift expendable launch vehicle, which has been under development since its announcement in 2011. The SLS is the main launch vehicle of the Artemis lunar program, as of March 2021. NASA is required to utilize SLS Block 1 by the U.S. Congress to lift a payload of 95 t (209,000 lb) to low Earth orbit (LEO), and will launch Artemis 1, 2, and 3.[citation needed] The later Block 1B is intended to debut the Exploration Upper Stage (EUS) and launch the notional Artemis 4-7.[80][full citation needed] Block 2 is planned to replace the initial Shuttle-derived boosters with advanced boosters and would have a LEO capability of more than 150 t (150 long tons; 170 short tons), again as required by Congress.[81] Block 2 is intended to enable crewed launches to Mars.[4] The SLS will launch the Orion spacecraft and use the ground operations capabilities and launch facilities at NASA's Kennedy Space Center in Florida. Some variations of the SLS launch manifest has all the blocks being active at the same time rather than one block replacing the last as is common with launchers.[citation needed]

SLS Core Stage rolling out from the Michoud Assembly Facility on 8 January 2020, ahead of the Artemis 1 Mission.

In March 2019, the Trump Administration released its Fiscal Year 2020 Budget Request for NASA. This budget did not initially include any money for the Block 1B and Block 2 variants of SLS but later a request for a budget increase of US1.6 billion dollars towards SLS, Orion, and crewed landers was made. Block 1B is currently intended to debut on Artemis 4 and will be used mainly for co-manifested crew transfers and logistics rather than constructing the Gateway as initially planned. An uncrewed Block was planned to launch the Lunar Surface Asset in 2028, the first lunar outpost of the Artemis program, but now that launch has been moved to a commercial launcher.[82] Block 2 development will most likely start in the late 2020s after NASA is regularly visiting the lunar surface and shifts focus towards Mars.[83]

In October 2019, it was announced NASA had authorized Boeing to purchase materials in bulk for more SLS rockets ahead of the announcement of a new contract. This contract is expected to support up to ten core stages and eight Exploration Upper Stages for the SLS 1B to transfer heavy payloads, up to 40 metric tons, on a lunar trajectory.[84]

Spacecraft[]

Orion[]

NASA's Orion spacecraft undergoing final tests.

Orion is a class of partially reusable space capsules to be used in NASA's human spaceflight programs. The spacecraft consists of a Crew Module (CM) designed by Lockheed Martin and the European Service Module (ESM) manufactured by Airbus Defence and Space. Capable of supporting a crew of six beyond low Earth orbit, Orion is equipped with solar panels, an automated docking system, and glass cockpit interfaces modeled after those used in the Boeing 787 Dreamliner. It has a single AJ10 engine for primary propulsion, and others including reaction control system engines. Although compatible with other launch vehicles, Orion is primarily designed to launch atop a Space Launch System (SLS) rocket, with a tower launch escape system.

Orion was originally conceived by Lockheed Martin as a proposal for the Crew Exploration Vehicle (CEV) to be used in NASA's Constellation program. Lockheed Martin's proposal defeated a competing proposal by Northrop Grumman, and was selected by NASA in 2006 to be the CEV. Originally designed with a service module featuring a new "Orion Main Engine" and a pair of circular solar panels, the spacecraft was to be launched atop the Ares I rocket. Following the cancellation of the Constellation program in 2010, Orion was heavily redesigned for use in NASA's Journey to Mars initiative; later named Moon to Mars. The SLS replaced the Ares I as Orion's primary launch vehicle, and the service module was replaced with a design based on the European Space Agency's Automated Transfer Vehicle. A development version of Orion's CM was launched in 2014 during Exploration Flight Test-1, while at least four test articles have been produced. As of 2020, three flight-worthy Orion spacecraft are under construction, with an additional one ordered, for use in NASA's Artemis program; the first of these is due to be launched in 2021 on Artemis 1. On 30 November 2020, it was reported that NASA and Lockheed Martin had found a failure with a component in one of the Orion spacecraft's power data units but NASA later clarified that it does not expect the issue to affect the Artemis 1 launch date.

A conceptual advanced Gateway depicting what Gateway could look like in the late 2020s.

Gateway[]

NASA's Gateway is an in-development mini-space station in lunar orbit intended to serve as a solar-powered communication hub, science laboratory, short-term habitation module, and holding area for rovers and other robots.[85] While the project is led by NASA, the Gateway is meant to be developed, serviced, and utilized in collaboration with commercial and international partners: Canada (Canadian Space Agency) (CSA), Europe (European Space Agency) (ESA), and Japan (JAXA).

Phase 1 early Gateway with Power and Propulsion Element (left), Habitation and Logistics Outpost (center foreground), and cargo spacecraft (center background) depicted

The Power and Propulsion Element (PPE) started development at the Jet Propulsion Laboratory during the now canceled Asteroid Redirect Mission (ARM). The original concept was a robotic, high performance solar electric spacecraft that would retrieve a multi-ton boulder from an asteroid and bring it to lunar orbit for study.[86] When ARM was canceled, the solar electric propulsion was repurposed for the Gateway.[87][88] The PPE will allow access to the entire lunar surface and act as a space tug for visiting craft.[89] It will also serve as the command and communications center of the Gateway.[90][91] The PPE is intended to have a mass of 8-9 tonnes and the capability to generate 50 kW[92] of solar electric power for its ion thrusters, which can be supplemented by chemical propulsion.[93]

The Habitation and Logistics Outpost (HALO),[94][95] also called the Minimal Habitation Module (MHM) and formerly known as the Utilization Module,[96] will be built by Northrop Grumman Innovation Systems (NGIS).[97][98] A single Falcon Heavy equipped with an extended fairing[99] will launch the PPE together with the HALO in November 2024.[73] The HALO is based on a Cygnus Cargo resupply module[97] to the outside of which radial docking ports, body mounted radiators (BMRs), batteries and communications antennae will be added. The HALO will be a scaled-down habitation module,[100] yet, it will feature a functional pressurized volume providing sufficient command, control and data handling capabilities, energy storage and power distribution, thermal control, communications and tracking capabilities, two axial and up to two radial docking ports, stowage volume, environmental control and life support systems to augment the Orion spacecraft and support a crew of four for at least 30 days.[98]

Gateway as of October 2020 which includes European, Japanese, and Russian modules

In March 2020, Doug Loverro, NASA's associate administrator for human exploration and operations at that time, removed the Gateway construction from the 2024 critical path to clear up funding for the HLS. He stated that the PPE could face delays and that moving it back to 2026 would allow for a more refined vehicle. It is also worth noting that the international partners on the Gateway would not have their modules ready until 2026. It was made a requirement that all Human Landing System proposals would be capable of free flight without the Gateway.[101]

On 30 April 2020, a key to NASA's vision for a "sustainable" crew presence on or near the Moon, the Gateway station, was announced to be optional, rather than required, in mission planning. NASA officials originally hoped the Gateway would be in position near the Moon in time for the Artemis 3 mission in 2024, allowing elements of the lunar lander to be assembled, or aggregated, at the Gateway before the arrival of astronauts on an Orion crew capsule. Jim Bridenstine told Spaceflight Now, the Artemis 3 mission will no longer go through the Gateway, but NASA is not backing away from the program.[79]

In late October 2020, NASA and European Space Agency (ESA) finalized their agreement to collaborate in the Gateway program. ESA will provide a habitat module in partnership with JAXA (iHab) and a refueling module (ESPRIT). In return Europe will have three flight opportunities to launch crew aboard the Orion crew capsule, which they will provide the service module for.[102][103]

Dragon XL[]

On 27 March 2020, SpaceX revealed the Dragon XL resupply spacecraft designed to carry pressurized and unpressurized cargo, experiments and other supplies to NASA's planned Gateway under a NASA Gateway Logistics Services (GLS) contract. The equipment delivered by Dragon XL missions could include sample collection materials, spacesuits and other items astronauts may need on the Gateway and the surface of the Moon, according to NASA. It will launch on SpaceX's Falcon Heavy launch vehicle from pad LC-39A at the Kennedy Space Center in Florida. The Dragon XL is planned to stay at the Gateway for six to 12 months at a time when research payloads inside and outside the cargo vessel could be operated remotely, even when crews are not present. Its payload capacity is expected to be more than 5,000 kg (11,000 lb) to lunar orbit. Unlike previous Dragon variants, the spacecraft will not be reusable and will instead be built solely for transporting cargo. It will act as the United States' logistics vehicle.[104]

Landers[]

Human Landing System[]

The Human Landing System, if fully funded and supported over the next several years, could result in crewed missions to the lunar surface beginning with the Artemis 3 mission as early as the mid-2020s.[105][106]

In April 2020, NASA awarded US$967 million in design development funding to Blue Origin, Dynetics, and SpaceX to begin a 10-month-long design process.[107][108][105] The companies/teams selected in the 2020 design awards were the "National Team" — led by Blue Origin and partners Lockheed Martin, Northrop Grumman, and Draper, with US$579 million in NASA design funding; Dynetics, including SNC and other unspecified companies, with US$253 million in NASA funding; and SpaceX with a modified Starship second stage design called Starship HLS, with US$135 million in NASA design funding.[107][109]

Although the HLS initial design phase had at first been planned to be a ten-month program, ending in February 2021,[108][105] NASA delayed the selection process and announcement by two months.[110] NASA planned to select up to two contractors at the end of the 12-month design development program.[110]

In the end, NASA selected only one lander — Starship HLS.[111] On 16 April 2021, SpaceX was awarded a contract, valued at US$2.89 billion, to develop the Starship HLS lander and to provide two operational lunar missions — one uncrewed demonstration mission, and one crewed lunar landing — as early as 2025.[15][112][113] The Blue Origin bid to NASA had been US$5.99 billion for the Integrated Lander Vehicle development plus two lunar flights.[114]

On 26 April 2021, both Blue Origin and Dynetics filed formal protests with the US Government Accountability Office claiming that NASA had improperly evaluated aspects of the proposals.[115][114] On 30 April 2021, NASA suspended the Starship HLS contract and funding until such time as the GAO could issue a ruling on the protests.[116][117] In May 2021, Sen. Cantwell, from Blue Origin's state of Washington, introduced an amendment to the "Endless Frontier Act" that directed NASA to reopen the HLS competition and select a second lander proposal, authorized spending of an additional US$10 billion. This funding would require a separate appropriations act. Sen. Sanders criticized the amendment as a "multibillion dollar Bezos bailout", as the money would likely go to Blue Origin, which was founded by Jeff Bezos.[118][119][120][121] The act, including this amendment, was passed by the Senate on 8 June 2021.[122][123][needs update]

On 30 July 2021, the GAO rejected the protests and found that "NASA did not violate procurement law" in awarding the contract to SpaceX, who bid a much lower cost and more capable human and cargo lunar landing capability for NASA Artemis.[124][125] Nevertheless, CNBC reported on 4 August that "Jeff Bezos’ space company remains on the offensive in criticizing NASA’s decision to award Elon Musk’s SpaceX with the sole contract to build a vehicle to land astronauts on the moon" and the company had produced an infographic highlighting several Starship deficiencies compared to the Blue Origin proposal, but noted the infographic avoided showing the Blue Origin bid price as roughly double the SpaceX bid price.[126] Soon after the appeal was rejected, NASA made the contracted initial payment of $300m to SpaceX.[127]

On 13 August 2021, Blue Origin filed a lawsuit in the US Court of Federal Claims challenging "NASA’s unlawful and improper evaluation of proposals."[128][129] Blue Origin has asked the court for an injunction to halt further spending by NASA on the existing contract with SpaceX.[130] Reaction to the lawsuit has been mostly negative in the space community, at NASA, and among Blue Origin employees according to space journalist Eric Berger.[131]

Company Vehicles Participation Status
SpaceX Starship HLS, a fully integrated lander that would use a Lunar design variation of the upper stage of the SpaceX Starship, would launch using the Super Heavy booster and then serve as its own second stage to complete the ascent to low-Earth orbit (LEO). On orbit, it would be refueled before climbing out to lunar orbit to meet the Gateway and Orion crew capsule. It was chosen to transport two NASA Artemis 3 astronauts along with cargo to and from the lunar surface working as a lunar SSTO, each time it lands on the moon. Proposal
Design Award
Option A
Finalist
Selected
"National Team"
Blue Origin (lead),
Lockheed Martin, Northrop Grumman
The Integrated Lander Vehicle (ILV), a three-element lunar lander (transfer, descent, and ascent elements) that is intended to be launched via either New Glenn and ULA Vulcan Centaur launch vehicles, would be assembled in lunar orbit. Proposal
Design Award
Selected for design phase; Not selected for development funding
Dynetics The Dynetics Human Landing System (DHLS), a single structure providing both lunar ascent and descent capabilities, would launch on either the ULA Vulcan Centaur or NASA's Space Launch System.[132] Proposal
Design Award
Selected for design phase; Not selected for development funding
Boeing The Boeing Lunar Lander was a HLS proposal submitted by Boeing in November 2019. The lander consisted of a descent and ascent stage. The lander was intended to be launched on an SLS Block 1B rather than assembled in multiple launches. Proposal Not selected
Vivace The Vivace HLS proposal was a two stage lunar landing vehicle that could transport astronauts to and from the lunar surface. It had an appearance similar[according to whom?] to the Altair LSAM.[133] Proposal Not selected

Starship HLS[]

Artist's concept of Starship HLS, selected by NASA to land humans on the Moon

The Starship Human Landing System (Starship HLS) was the winner selected by NASA for potential use for long-duration crewed lunar landings as part of NASA's Artemis program.[15][113]

The Starship HLS is a modified configuration of SpaceX's Starship spacecraft, optimized to operate on and around the Moon. As a result, the heat shield and air-brakes — integral parts of the main Starship design — are not included in Starship HLS. The variant will use high-thrust methalox RCS thrusters located mid-body on Starship HLS during the final "tens of meters" of the terminal lunar descent and landing, and will be powered by a solar array located on its nose below the docking port. Elon Musk stated that Starship HLS would be able to deliver "potentially up to 200 tons" to the lunar surface.

Starship HLS would be launched to Earth orbit using the SpaceX Super Heavy booster, and would use a series of tanker spacecraft to refuel the Starship HLS vehicle for lunar transit and lunar landing operations. In the mission concept, a NASA Orion spacecraft would carry a NASA crew to the lander where they would depart and descend to the surface of the Moon. After lunar surface operations, Starship HLS would liftoff from the lunar surface acting as a SSTO and return the crew to Orion.

NASA did highlight two weaknesses with SpaceX’s proposal. Starship’s propulsion systems were described as “notably complex,” and the report referred to prior delays under the Commercial Crew program and Falcon Heavy launch vehicle development as evidence for potential threats to their development schedule.[107]

Unselected proposals[]

Integrated Lander Vehicle[]

The Integrated Lander Vehicle (ILV) or National Human Landing System (NHLS) was a lunar lander design concept proposed by the "National Team" which is led by Blue Origin, along with Lockheed Martin, Northrop Grumman, and Draper Laboratory as major partners.

The main selling point[according to whom?] of the lander was that all the components have been in development in one form or another for some time.[citation needed] The transfer stage is based on the Cygnus spacecraft, the Blue Moon will be used as the descent stage, and the ascent stage will be based on the Orion spacecraft..[citation needed] It was to be launched in three parts on either the New Glenn and Vulcan Centaur but could also be launched on a single SLS Block 1B.[citation needed]

In the 28 April 2020 HLS source selection statement, NASA stated that the vehicle passes all requirements but faces risks with its power, propulsion, and communications systems which pose a significant risk to the developmental timeline.[107][105]

Dynetics ALPACA HLS[]

The Dynetics ALPACA (Autonomous Logistics Platform for All-Moon Cargo Access) Human Landing System design concept was proposed by Dynetics and Sierra Nevada Corporation as well as a number of subcontractors. The vehicle design consists of a single-stage lander powered by methalox engines, although a previous design used drop tanks. ALPACA was proposed to launch on a Vulcan Centaur or SLS Block 1B rocket, and be refueled by up to three Vulcan Centaur tanker flights. Ultimately, NASA did not select the proposal, citing negative mass margins and an experimental thrust structure, which could pose threat to development time.[134][135]

Boeing HLS[]

The Boeing Human Landing System proposal was submitted to NASA in early November 2019. The two-stage lander was designed to launch on a single SLS Block 1B. Boeing had partnered with Intuitive Machines to provide engines,[136] and also planned to reuse technologies from their Starliner spacecraft.[137] An alternative plan for launching the lander was also detailed: In the event the SLS Block 1B was not ready by 2024, the descent stage could launch on an SLS Block 1 while the ascent stage would be launched by a commercial launcher and assembled in lunar orbit.[138] The Boeing proposal was not selected for design funding by NASA in the April 2020 design funding announcements.[59]

Vivace HLS[]

The Vivace Human Landing System was a lunar landing concept by aerospace firm Vivace. Little is known about the vehicle other than its resemblance to NASA's Altair lunar lander from the Constellation program. Only one image of the lander can be found on their website's gallery page Vivace's concept was not selected for design funding.[133]

Commissioned HLS studies[]

In May 2019, NASA announced 11 contracts worth US$45.5 million in total for studies on transfer vehicles, descent elements, descent element prototypes, refueling element studies and prototypes. One of the requirements is that selected companies will have to contribute at least 20% of the total cost of the project "to reduce costs to taxpayers and encourage early private investments in the lunar economy.[139]

Company Contract
Aerojet Rocketdyne One transfer vehicle study
Blue Origin One descent element study, one transfer vehicle study, and one transfer vehicle prototype
Boeing One descent element study, two descent element prototypes, one transfer vehicle study, one transfer vehicle prototype, one refueling element study, and one refueling element prototype
Dynetics One descent element study and five descent element prototypes
Lockheed Martin Space Systems One descent element study, four descent element prototypes, one transfer vehicle study, and one refueling element study
Masten Space Systems One descent element prototype
Maxar (formerly SSL) One refueling element study and one refueling element prototype
Northrop Grumman Innovation Systems One descent element study, four descent element prototypes, one refueling element study, and one refueling element prototype
OrbitBeyond Two refueling element prototypes
Sierra Nevada Corporation One descent element study, one descent element prototype, one transfer vehicle study, one transfer vehicle prototype, and one refueling element study
SpaceX One descent element study, one descent element prototype

Advanced Exploration Lander[]

The Advanced Exploration Lander, used as a stand-in while HLS designs are finalized

The Advanced Exploration Lander is a three-stage lander concept used as a design reference for commercial proposals. As proposed, after departure from the Gateway, a transfer module would take the crew to a low lunar orbit and then separate, after which the descent module would handle the rest of the journey to the lunar surface. A crew of up to four could spend up to two weeks on the surface before reboarding the ascent module, which would take them back to the Gateway. Each module would have a mass of approximately 12 to 15 metric tons and would be delivered separately by commercial launchers and integrated at the Gateway. The astronauts would board the lander at the Gateway's near-rectilinear halo orbit that goes between about 1,000 and 70,000 kilometers (620 and 43,500 miles) above the Moon, with the circular low orbit about 100 kilometers (62 miles) high. Both the ascent and transfer modules could be designed to be reused, with the descent module left on the lunar surface.[140]

HERACLES[]

HERACLES (Human-Enhanced Robotic Architecture and Capability for Lunar Exploration and Science) is a planned ESA-JAXA-CSA space cargo transport system that will feature a robotic lunar lander called European Large Logistic Lander (EL3),[141] which can be configured for different operations such as up to 1,500 kg (3,300 lb) of payload,[142] sample-returns, or prospecting resources found on the Moon.[143] ESA approved the project in November 2019.[142][144][145] Its first mission is envisioned for launch in the mid to late 2020s aboard an Ariane 6.[146][141]

The EL3 lander will be launched directly to the Moon and will have a landing mass of approximately 1,800 kg (4,000 lb).[147] It will be capable of transporting a Canadian robotic rover to explore, prospect potential resources, and load samples up to 15 kg (33 lb) on the ascent module.[148] The rover would then traverse several kilometers across the Schrödinger basin on the far side of the Moon to explore and collect more samples to load on the next EL3 lander.[149][147] The ascent module would return each time to the Gateway, where it would be captured by the Canadian robotic arm and samples transferred to an Orion spacecraft for transport to Earth with returning astronauts.[150][151]

Astronauts[]

On 10 January 2020, NASA's 22nd astronaut group, nicknamed the "Turtles", graduated and were assigned to the Artemis program. The group includes two Canadian Space Agency (CSA) astronauts. The group earned their nickname from the prior astronaut group, "The 8-Balls", as is a tradition dating back to "The Mercury Seven" in 1962 which subsequently provided the "Next Nine" with their nickname. They were given this name, for the most part, because of Hurricane Harvey. Some of the astronauts will fly on the Artemis missions to the Moon and may be part of the first crew to fly to Mars.[152]

On 9 December 2020, Vice President Mike Pence announced first group of 18 astronauts (9 male and 9 female), the Artemis team, who could be selected as astronauts of early missions of Artemis program:[153]

Planned surface operations[]

An artist's rendition of an Artemis astronaut wearing the xEMU spacesuit and xPLS life support backpack during an EVA on the Moon.

As of February 2020, a lunar stay during a Phase 1 Artemis mission will be about seven days and will have five extravehicular activities (EVA). A notional concept of operations (i.e., a hypothetical but possible plan) would include the following: On Day 1 of the stay, astronauts touchdown on the Moon but do not conduct an EVA. Instead, they prepare for the EVA scheduled for the next day in what is referred to as "The Road to EVA". On Day 2, the astronauts open the hatch on the Human Landing System and embark on EVA 1 which will be six hours long. It will include collecting a contingency sample, conducting public affairs activities, deploying the experiment package, and acquiring samples. The astronauts will stay close to the landing site on this first EVA. EVA 2 begins on day 3. The astronauts characterize and collect samples from permanently shadowed regions. Unlike the previous EVA, the astronauts will go further from the landing site, up to 2 kilometres (1.2 mi), and up and down slopes of 20°. Day 4 will not include an EVA but Day 5 will. EVA 3 may include activities such as collecting samples from an ejecta blanket. Day 6 will have the two astronauts deploy a geotechnical instrument alongside an environmental monitoring station for in-situ resource utilization (ISRU). Day 7 will have the final and shortest EVA; this EVA will only last one hour rather than the others' six hours in duration from egress to ingress and mostly comprises preparations for the lunar liftoff, including jettisoning hardware. Once the final EVA is concluded, the astronauts will return into the Human Landing System and the vehicle will launch from the surface and join up with Orion/Gateway.[154]

A render of the Artemis Base Camp

Artemis Base Camp[]

Artemis Base Camp is the prospective lunar base that was proposed to be established at the end of the 2020s. It would consist of three main modules: the Foundational Surface Habitat, the Habitable Mobility Platform, and the Lunar Terrain Vehicle. It would support missions of up to two months and be used to study technologies to use on Mars. The idea would be to build upon this initial base site for decades through both Government and commercial programs. Currently Shackleton Crater is the prime target for this outpost due to its wide variety of lunar geography and water ice. It would fall under the guidelines of the Outer Space Treaty.[155][156]

Foundational Surface Habitat[]

A render of the Foundational Surface Habitat

Little is known about the surface outpost with most information coming from studies and launch manifests that include its launch. It would be commercially built and possibly commercially launched in 2028 along with the Mobile Habitat.[157] The first habitat is referred to as the Artemis Foundation Habitat formerly the Artemis Surface Asset. Current launch plans show that landing it on the surface would be similar to the HLS. The pressurized habitat would be sent to the Gateway where it would then be attached to a descent stage separately launched from a commercial launcher, it would utilize the same transfer stage used for the HLS. Other designs from 2019 see it being launched from an SLS Block 1B as a single unit and landing directly on the surface. It would then be hooked up to a surface power system launched by a CLPS mission and tested by the Artemis 6 crew. The location of the base would be in the south pole region and most likely be a site visited by prior crewed and robotic missions.[155][6]

Habitable Mobility Platform[]

NASA Habitable Mobility Platform based on the post Constellation Space Exploration Vehicle.

The Habitable Mobility Platform would be a large pressurized rover used to transport crews across large distances. NASA has developed multiple pressurized rovers including the Space Exploration Vehicle built for the Constellation program which was fabricated and tested. In the 2020 flight manifest it was referred to as the Mobile Habitat suggesting it could fill a similar role to the ILREC Lunar Bus. It would be ready for the crew to use on the surface but could also be autonomously controlled from the Gateway or other locations. Mark Kirasich, who is the acting director of NASA's Advanced Exploration Systems, has stated that the current plan is to partner with JAXA and Toyota to develop a closed cabin rover to support crews for up to 14 days (currently known as ). "It's very important to our leadership at the moment to involve JAXA in a major surface element", he said. "... The Japanese, and their auto industry, have a very strong interest in rover-type things. So there was an idea to — even though we have done a lot of work — to let the Japanese lead development of a pressurized rover. So right now, that's the direction we're heading in". In regards to the SEV, Senior Lunar Scientist Clive Neal said "Under Constellation NASA had a sophisticated rover put together, It's pretty sad if it's never going to get to the Moon". but also said that he understands the different scopes of the Constellation Program and Artemis Program and the focus on international collaboration.[155][158][159][160][161]

Lunar Terrain Vehicle[]

NASA's baseline Lunar Terrain Vehicle

In February 2020, NASA released two requests for information regarding both a crewed and uncrewed unpressurized surface rover. The LTV would be propositioned by a CLPS vehicle before the Artemis 3 mission. It would be used to transport crews around the exploration site. It would serve a similar function as the Apollo Lunar Rover. In July 2020, NASA will move to formally establish a program office for the rover at the Johnson Space Center in Houston.[155][needs update]

VIPER[]

The VIPER (Volatiles Investigating Polar Exploration Rover) is a lunar rover by NASA planned to be delivered to the surface of the Moon as early as December 2022. The rover will be tasked with prospecting for lunar resources in permanently shadowed areas in the lunar south pole region, especially by mapping the distribution and concentration of water ice. The mission builds on a previous NASA rover concept called Resource Prospector, which was cancelled in 2018.[162]

The VIPER rover is part of the Lunar Discovery and Exploration Program managed by the Science Mission Directorate at NASA Headquarters, and it is meant to support the crewed Artemis program.[163] NASA's Ames Research Center is managing the rover project. The hardware for the rover is being designed by the Johnson Space Center, while the instruments are provided by Ames Research Center, Kennedy Space Center, and Honeybee Robotics.[163] The project manager is Daniel Andrews, and the project scientist is Anthony Colaprete, who is implementing the technology developed for the now cancelled Resource Prospector rover. The estimated cost of the mission is US$250 million.

The VIPER rover will operate at a south pole region yet to be determined. VIPER is planned to rove several kilometers, collecting data on different kinds of soil environments affected by light and temperature — those in complete darkness, occasional light, and in constant sunlight. Once it enters a permanently shadowed location, it will operate on battery power alone and will not be able to recharge them until it drives to a sunlit area. Its total operation time will be approximately 100 Earth days.

Both the launcher and the lander to be used will be competitively provided through the Commercial Lunar Payload Services (CLPS) contractors. NASA is aiming at landing the rover as early as December 2022.[164]

Space suits[]

xEMU suit for lunar surface extravehicular activity (EVA)
OCSS suit for launch and reentry

The Artemis program will make use of two space suits revealed in October 2019: the Exploration Extravehicular Mobility Unit (xEMU),[165] and the Orion Crew Survival System (OCSS).[166]

Artemis flights[]

The Orion capsule in the Pacific Ocean, following the Exploration Flight Test-1 mission

Orion testing[]

Five uncrewed test launches of the Orion spacecraft have been conducted prior to the launch of Artemis 1. The first was the MLAS Pad Abort Test of the Max Launch Abort System with a boilerplate Orion capsule on 8 July 2009. The second test launch was the Ares I-X Development Flight Test including an instrumented boilerplate Orion capsule on 28 October 2009. The third, Pad Abort-1,[167] was a successful test of Orion's launch escape system using a boilerplate capsule on 6 May 2010.[167][168] The fourth test launch of Orion was Exploration Flight Test-1 on 5 December 2014,[169][170] in which a prototype version of the Orion spacecraft was launched atop a Delta IV Heavy rocket, and its reaction control system and other components were tested during two medium Earth orbits reaching an apogee of 5,800 km (3,600 mi) and crossing the Van Allen radiation belts before making a high-energy reentry at 32,000 km/h (20,000 mph).[171][172] The fifth and final test of Orion prior to Artemis 1 was Ascent Abort-2 on 2 July 2019, a follow-up to Pad Abort-1, which tested the final iteration of the launch abort system on a 10,000 kg (22,000 lb) Orion boilerplate at maximum aerodynamic load,[173][174][175] using a custom Minotaur IV-derived launch vehicle built by Orbital ATK.[175][176]

Orion development test flights
Mission Patch Launch Launch vehicle Outcome Duration
MLAS Pad Abort Test
MLAS mission patch.png
  • 8 July 2009, 10:26 UTC
  • Wallops
Max Launch Abort System Success 1 minute
Ares I-X
Development Flight Test
AresIX patch02.svg
  • 28 October 2009, 15:30 UTC
  • Kennedy LC-39B
Ares I-X Success 6 minutes
Pad Abort-1
https://commons.wikimedia.org/wiki/File:Orion_Pad_Abort_1.png
  • 6 May 2010, 13:03 UTC
  • White Sands
Orion Launch Abort System Success 1 minute, 35 seconds
Exploration Flight Test-1
https://commons.wikimedia.org/wiki/File:Exploration_Flight_Test-1_insignia.png
  • 5 December 2014, 12:05 UTC
  • Cape Canaveral SLC-37
Delta IV Heavy (Delta 369) Success 4 hours, 25 minutes
Ascent Abort-2
https://commons.wikimedia.org/wiki/File:Ascent_Abort-2.png
  • 2 July 2019, 11:00 UTC
  • Cape Canaveral SLC-46
Orion Abort Test Booster
(Peacekeeper/Minotaur IV first stage)
Success 3 minutes, 13 seconds

Planned missions[]

As of December 2020, all crewed Artemis missions will be launched on the Space Launch System from Kennedy Space Center Launch Complex 39B. Current plans call for some supporting hardware to be launched on other vehicles and from other launch pads.

Mission Patch Launch date Crew Launch vehicle Duration Goal
Artemis I
Exploration Mission-1 patch.png
22 November 2021[177] N/A SLS Block 1 Crew ≈25 days Uncrewed lunar orbit and return
Artemis II To be designed by the crew September 2023[3] TBA SLS Block 1 Crew ≈10 days 4-person lunar flyby
Artemis III To be designed by the crew Officially September 2024 but likely to be delayed[178] TBA SLS Block 1 Crew ≈30 days 4-person lunar orbit with 2-person lunar landing
Artemis IV To be designed by the crew March 2026[179] TBA SLS Block 1B Crew ≈30 days 4-person lunar orbit and delivery of Gateway i-HAB module[180]

Proposed missions[]

A proposal curated by William H. Gerstenmaier before his 10 July 2019 reassignment[181] suggested four launches of the SLS Block 1B launch vehicle with crewed Orion spacecraft and logistics modules to the Gateway between 2024 and 2028.[182][183] The crewed Artemis IV through IX would launch yearly between 2025 and 2030,[82] testing in situ resource utilization and nuclear power on the lunar surface with a partially reusable lander. Artemis VII would deliver in 2028 a crew of four astronauts to a Surface lunar outpost known as the Foundation Habitat along with the Mobile Habitat.[82] The Foundation Habitat would be launched back to back with the Mobile Habitat by an undetermined super heavy launcher[82] and would be used for extended crewed lunar surface missions.[82][184][185] Prior to each crewed Artemis mission, various payloads to the Gateway, such as refueling depots and expendable elements of the lunar lander, would be deployed by commercial launch vehicles.[183][185] The most updated manifest simply includes missions suggested in NASA's timelines that have not been designed or funded from Artemis IV-IX.[186][82][157]

Mission Launch date Crew Launch vehicle Duration
Artemis V 2026 TBA SLS Block 1B Crew ≈30 days
Artemis VI 2027 TBA SLS Block 1B Crew ≈30 days
Artemis VII 2028 TBA SLS Block 1B Crew ≈30 days
Artemis VIII 2029 TBA SLS Block 2 Crew ≈60 days
Artemis IX 2030 TBA SLS Block 2 Crew ≈60 days
Artemis X 2031 TBA SLS Block 2 Crew ≈60 days
Artemis XI 2032 TBA SLS Block 2 Crew ≈60 days
And so on...

Support missions[]

Artemis support missions are robotic missions flown through both the CLPS program and Gateway program.[82] (all future dates NET)
Date Mission objective Mission name Launch vehicle Outcome
Q4 2021[187] NRHO Pathfinder mission CAPSTONE CAPSTONE Electron Planned
Q1 2022 First launch of the Nova-C lunar lander by Intuitive Machines[70] IM-1 Falcon 9 Planned
Q1 2022 First launch of the Peregrine lunar lander by Astrobotic[188] Peregrine Mission One Vulcan Centaur[189] Planned
Q4 2022 ISRU tech demonstration converting lunar ice to H2O using Intuitive Machines Nova-C PRIME-1[190] Falcon 9[191] Planned
November 2023 Tools for mapping the lunar surface temperature, radiation, and hydrogen delivered by Masten Space Systems via their XL-1 lander. Masten Mission One[192] Falcon 9[193] Planned
November 2023[194] Delivery of NASA's VIPER rover on the Griffin lunar lander to the lunar surface by Astrobotic Technology[194][195] VIPER Falcon Heavy[196] Planned
2023 Fuel Cells Demo 1 delivered to surface via CLPS lander[157] Artemis support mission Commercial launch vehicle Planned
2023 Delivery of Starship HLS for HLS Demo landing mission Artemis HLS Demo Starship Planned
2024 Delivery of the Lunar Terrain Vehicle ahead of Artemis III[197] Artemis support mission Commercial launch vehicle Planned
October 2024 Delivery of Starship HLS for Artemis III Artemis HLS 1 Starship Planned
November 2024[73] Launch of the Power and Propulsion Element (PPE) and the Habitation and Logistics Outpost (HALO) as an integrated assembly. First two Lunar Gateway modules. Artemis support mission Falcon Heavy Planned
2024 ISRU Subsystems, lunar regolith to O2, performed by crew on surface Artemis support mission Commercial launch vehicle Planned
2025 (Proposed) Moon landing support mission(s) for Artemis IV Artemis support mission Commercial launch vehicle Proposed
2025 Fuel Cells Demo 2 Artemis support mission Commercial launch vehicle Planned
2026 (Proposed) Moon landing support mission(s) for Artemis V Artemis support mission Commercial launch vehicle Proposed
2027 Delivery of ESPRIT Refueling Module (ERM) Artemis support mission Commercial launch vehicle Planned
2027 (Proposed) Moon landing support mission(s) for Artemis VI Artemis support mission Commercial launch vehicle Proposed
2027 Cryo Fluid Management Systems Artemis support mission Commercial launch vehicle Planned
2027 Surface power crew demonstration mission Artemis support mission Commercial launch vehicle Planned
2028 (Proposed) delivery of a Gateway station module Artemis support mission Commercial launch vehicle Proposed
2028 (Proposed) Moon landing support mission(s) for Artemis VII Artemis support mission Commercial launch vehicle Proposed
2028 (Proposed) delivery of the Foundation Habitat to the lunar south pole[157] Artemis support mission Space Launch System Block 1B / 2[citation needed] Proposed
2028 (Proposed) delivery of the JAXA closed cabin rover to the lunar south pole Artemis support mission Space Launch System Block 1B / 2[citation needed] Proposed
2029 (Proposed) Moon landing support mission(s) for Artemis VIII Artemis support mission Commercial launch vehicle Proposed
2030 (Proposed) Moon landing support mission(s) for Artemis IX Artemis support mission Commercial launch vehicle Proposed

Criticism[]

The Artemis program has received criticisms from several space professionals.

Mark Whittington, who is a contributor to The Hill and an author of several space exploration studies, stated in an article that the "lunar orbit project doesn't help us get back to the Moon".[198]

Aerospace engineer, author, and Mars Society founder Robert Zubrin has voiced his distaste for the Gateway which is part of the Artemis program as of 2020. He presented an alternative approach to a 2024 crewed lunar landing called "", a successor to his proposed Mars Direct. His vision phases out the SLS and Orion, replacing them with the SpaceX launch vehicles and SpaceX Dragon 2. It also proposes using a heavy ferry/lander that would be refueled on the lunar surface via in situ resource utilization and transfer the crew from LEO to the lunar surface. The concept bears a heavy resemblance to NASA's own Space Transportation System proposal from the 1970s.[199]

Former Apollo 11 astronaut Buzz Aldrin disagrees with NASA's current goals and priorities, including their plans for a lunar outpost. He also questioned the benefit of the idea to "send a crew to an intermediate point in space, pick up a lander there and go down". However, Aldrin expressed support for Robert Zubrin's Moon Direct concept which involves lunar landers traveling from Earth orbit to the lunar surface and back.[200]

House Authorization Bill of 2020[]

The leadership of the House Science Committee introduced a bipartisan NASA authorization bill on 24 January 2020 that would significantly alter NASA's current plans to return humans to the Moon and rather would focus on a Mars orbital mission in 2033. Bill H.R. 5666 would change the lunar landing date from 2024 to 2028 and put the program as a whole underneath a larger space exploration plan. The bill became stuck in the House Committee on Science, Space, and Technology and there were no committee votes or further action for the remainder of the congressional term. Major proposed changes included:[201][202]

  • Creation of a new Moon to Mars program office with a goal of landing humans on Mars "in a sustainable manner as soon as practicable"
  • A 2028 target date for a lunar landing to allow the technology to mature
  • A NASA developed expendable Human Landing System (HLS), something along the line of the Advanced Exploration Lander or the expendable Altair design
  • An integrated Orion / HLS system launching on a single Space Launch System Block 1B, similar to the Saturn / Apollo combination possibly using the Boeing HLS design
  • The requirement of one uncrewed and one crewed test flight of the HLS before a lunar landing is attempted, something not currently required
  • Once operational, the system would perform two lunar landings a year rather than one
  • No base would be set up on the lunar surface rather, the missions would follow the "flag and footsteps" approach of Apollo
  • Development of the Gateway as a separate program to test Mars transportation technologies and not be required for lunar operations
  • ISRU technologies would be managed under a program separate from the Moon to Mars campaign and not be required for either mission
  • International Space Station funding would be extended to 2030

Many of these changes such as uncrewed HLS test flights[203] and the development of the Gateway as no longer essential to Artemis[204] were implemented into the current timeline.

Gallery[]

See also[]

  • Apollo program – 1961–1972 program which landed the first humans on the Moon
  • Colonization of the Moon – Proposed establishment of a permanent human community or robotic industries on the Moon
  • Commercial Crew Development
  • Deep Space Transport – Crewed interplanetary spacecraft concept
  • First Lunar Outpost - A crewed lunar program proposal from the SEI
  • List of crewed spacecraft
  • Space policy of the United States
  • International Lunar Resources Exploration Concept – Lunar exploration concept
  • NASA Astronaut Group 23
  • Chinese Lunar Exploration Program - A Chinese crewed lunar program include international partners e.g. Russia.

Notes[]

  1. ^ OrbitBeyond subsequently asked to be released from the contract, and NASA did so later in 2019.[when?]

References[]

  1. ^ Jump up to: a b Berger, Eric (11 February 2020). "NASA puts a price on a 2024 Moon landing — US$35 billion". Ars Technica. Archived from the original on 11 February 2020. Retrieved 11 February 2020.
  2. ^ Jump up to: a b c d "NASA: Moon to Mars". nasa.gov. NASA. Archived from the original on 5 August 2019. Retrieved 19 May 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  3. ^ Jump up to: a b Sloss, Philip (31 May 2021). "NASA evaluating schedule, launch date forecasts for Artemis 2". NASASpaceFlight. Retrieved 1 June 2021.
  4. ^ Jump up to: a b Gebhardt, Chris (6 April 2017). "NASA finally sets goals, missions for SLS — multi-step plan to Mars". NASASpaceFlight.com. Archived from the original on 21 August 2017. Retrieved 21 August 2017.
  5. ^ Jump up to: a b Grush, Loren (18 July 2019). "NASA's daunting to-do list for sending people back to the Moon". The Verge. Archived from the original on 7 December 2019. Retrieved 28 August 2019.
  6. ^ Jump up to: a b Berger, Eric (20 May 2020). "NASA's full Artemis plan revealed: 37 launches and a lunar outpost". Ars Technica. Archived from the original on 23 May 2019. Retrieved 24 May 2020.
  7. ^ Jump up to: a b "NASA: Artemis Accords". nasa.gov. NASA. Archived from the original on 16 May 2020. Retrieved 16 May 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  8. ^ "NASA signs agreement with Italy to cooperate on Artemis". SpaceNews. 25 September 2020. Retrieved 30 September 2020.
  9. ^ Potter, Sean (13 October 2020). "NASA, International Partners Advance Cooperation with Artemis Accords". NASA. Archived from the original on 19 February 2021. Retrieved 16 March 2021.
  10. ^ "NASA Gains Broad International Support for Artemis Program at IAC". nasa.gov. NASA. 8 November 2019. Archived from the original on 28 July 2020. Retrieved 24 May 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  11. ^ "Brazil Signs Artemis Accords". NASA.gov. 15 June 2021.
  12. ^ Potter, Sean (27 May 2021). "Republic of Korea Joins List of Nations to Sign Artemis Accords". NASA. Archived from the original on 27 May 2021. Retrieved 27 May 2021.
  13. ^ NASA.gov
  14. ^ "White House endorses Artemis program". SpaceNews. 4 February 2021. Retrieved 29 April 2021.
  15. ^ Jump up to: a b c d Berger, Eric (16 April 2021). "NASA selects SpaceX as its sole provider for a lunar lander - "We looked at what's the best value to the government."". Ars Technica. Archived from the original on 17 April 2021. Retrieved 17 April 2021.
  16. ^ Moskowitz, Clara (7 January 2011). "NASA Stuck in Limbo as New Congress Takes Over". Space.com. Archived from the original on 22 October 2020. Retrieved 19 October 2020.
  17. ^ (8 September 2009). "Charter of the Review of U.S. Human Space Flight Plans Committee". NASA. Archived from the original on 8 April 2021. Retrieved 9 September 2009. Public Domain This article incorporates text from this source, which is in the public domain.
  18. ^ Amos, Jonathan (11 October 2010). "Obama signs Nasa up to new future". BBC News. Archived from the original on 26 September 2020. Retrieved 30 September 2020.
  19. ^ Review of U.S. Human Space Flight Plans Committee; Augustine; Austin; Chyba; et al. "Seeking A Human Spaceflight Program Worthy of A Great Nation" (PDF). Final Report. NASA. Archived (PDF) from the original on 16 February 2019. Retrieved 15 April 2010. Public Domain This article incorporates text from this source, which is in the public domain.
  20. ^ "President Barack Obama on Space Exploration in the 21st Century". NASA. Archived from the original on 14 December 2017. Retrieved 1 September 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  21. ^ "S.3729 - National Aeronautics and Space Administration Authorization Act of 2010". United States Congress. 11 October 2010. Archived from the original on 28 April 2021. Retrieved 9 January 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  22. ^ Clark, Stephen (30 June 2017). "Trump signs order reviving long-dormant National Space Council". Spaceflight Now. Archived from the original on 9 November 2020. Retrieved 30 June 2017.
  23. ^ Grush, Loren (17 May 2019). "NASA administrator on new Moon plan: "We're doing this in a way that's never been done before"". The Verge. Archived from the original on 4 July 2020. Retrieved 20 May 2019.
  24. ^ Pearlman, Robert (14 May 2019). "NASA Names New Moon Landing Program Artemis After Apollo's Sister". Space.com. Archived from the original on 26 July 2019. Retrieved 14 May 2019.
  25. ^ Chang, Kenneth (13 May 2019). "For Artemis Mission to Moon, NASA Seeks to Add Billions to Budget". The New York Times. ISSN 0362-4331. Archived from the original on 25 May 2019. Retrieved 21 July 2019.
  26. ^ Harwood, William (17 July 2019). "NASA boss pleads for steady moon mission funding". CBS News. Archived from the original on 12 November 2020. Retrieved 28 August 2019.
  27. ^ Foust, Jeff (27 September 2019). "Senate appropriators advance bill funding NASA despite uncertainties about Artemis costs". SpaceNews. Retrieved 30 September 2019.
  28. ^ Fernholz, Tim. "Trump wants US$1.6 billion for a Moon mission and proposes to get it from college aid". Quartz. Archived from the original on 8 November 2020. Retrieved 14 May 2019.
  29. ^ Berger, Eric (14 May 2019). "NASA reveals funding needed for Moon program, says it will be named Artemis". Ars Technica. Archived from the original on 27 July 2019. Retrieved 22 May 2019.
  30. ^ "Appropriations Committee Releases Fiscal Year 2021 Commerce-Justice-Science Funding Bill". 7 July 2020. Archived from the original on 5 August 2020. Retrieved 7 August 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  31. ^ "House bill offers flat funding for NASA". SpaceNews. 7 July 2020. Archived from the original on 12 July 2020. Retrieved 30 September 2020.
  32. ^ Bartels, Meghan (5 February 2021). "NASA has a lot to tackle this year as Biden takes charge. Here's what the agency's acting chief has to say". Space.com. Archived from the original on 2 March 2021. Retrieved 20 March 2021.
  33. ^ Feldscher, Jacqueline (16 February 2021). "NASA reassesses Trump's 2024 moon goal". Politico. Archived from the original on 2 March 2021. Retrieved 20 March 2021.
  34. ^ Berger, Eric (18 February 2021). "Acting NASA chief says 2024 Moon landing no longer a "realistic" target". Ars Technica. Archived from the original on 4 March 2021. Retrieved 20 March 2021.
  35. ^ "White House endorses Artemis program". SpaceNews. 4 February 2021. Retrieved 29 April 2021.
  36. ^ "Press Briefing by Press Secretary Jen Psaki and National Security Advisor Jake Sullivan, February 4, 2021". whitehouse.gov. 4 February 2021. Archived from the original on 11 March 2021. Retrieved 19 March 2021.
  37. ^ Rincon, Paul (5 February 2021). "Artemis: Biden administration backs US Moon shot". BBC News Online. Archived from the original on 16 March 2021. Retrieved 19 March 2021.
  38. ^ Davenport, Christian (2 March 2021). "The Biden administration has set out to dismantle Trump's legacy, except in one area: Space". The Washington Post. Archived from the original on 28 April 2021. Retrieved 19 March 2021.
  39. ^ Jump up to: a b Burghardt, Thomas (14 May 2019). "NASA aims for quick start to 2024 Moon landing via newly named Artemis Program". NASASpaceFlight.com. Archived from the original on 22 May 2019. Retrieved 28 August 2019.
  40. ^ Jump up to: a b Harwood, William (31 May 2019). "NASA taps three companies for commercial moon missions". CBS News. Archived from the original on 26 February 2020. Retrieved 28 August 2019.
  41. ^ Foust, Jeff (31 May 2019). "NASA awards contracts to three companies to land payloads on the moon". SpaceNews. Retrieved 28 August 2019.
  42. ^ Bergin, Chris (19 March 2018). "NASA courts commercial options for Lunar Landers". NASASpaceFlight.com. Archived from the original on 8 May 2018. Retrieved 18 October 2018. NASA's new Commercial Lunar Payload Services (CLPS) effort to award contracts to provide capabilities as soon as 2019.
  43. ^ "NASA Expands Plans for Moon Exploration: More Missions, More Science". NASA. Archived from the original on 16 February 2020. Retrieved 4 June 2018. Public Domain This article incorporates text from this source, which is in the public domain.
  44. ^ Jump up to: a b Foust, Jeff (28 April 2018). "NASA emphasizes commercial lunar lander plans with Resource Prospector cancellation". SpaceNews. Archived from the original on 18 October 2018. Retrieved 18 October 2018. ... selected but unspecified instruments from RP will instead be flown on future commercial lunar lander missions under a new Commercial Lunar Payload Services (CLPS) program. NASA released a draft request for proposals for that program April 27. [...] Under CLPS, NASA plans to issue multiple indefinite-delivery indefinite-quantity (IDIQ) contracts to companies capable of delivering payloads to the lunar surface. Companies would have to demonstrate their ability to land at least 10 kilograms of payload on the lunar surface by the end of 2021.
  45. ^ Werner, Debra (24 May 2018). "NASA to begin buying rides on commercial lunar landers by year's end". spacenews.com. SpaceNews. Archived from the original on 18 October 2018. Retrieved 18 October 2018. NASA also will look for payloads for the miniature landers in addition to landers capable of delivering 500 to 1000 kilograms to the surface of the Moon.
  46. ^ Jump up to: a b c d "NASA Announces New Partnerships for Commercial Lunar Payload Delivery Services" (Press release). NASA. 29 November 2018. Archived from the original on 25 November 2020. Retrieved 29 November 2018. Public Domain This article incorporates text from this source, which is in the public domain.
  47. ^ Jump up to: a b c d "NASA chooses three companies to send landers to the moon". upi.com. UPI. Archived from the original on 22 January 2020. Retrieved 1 June 2019.
  48. ^ "Commercial lunar lander company terminates NASA contract". SpaceNews. 30 July 2019. Retrieved 30 July 2019.
  49. ^ Richardson, Derek (26 February 2019). "NASA selects experiments to fly aboard commercial lunar landers". Spaceflight Insider. Archived from the original on 17 July 2019. Retrieved 28 August 2019.
  50. ^ Hautaluoma, Grey (1 July 2019). "NASA Selects 12 New Lunar Science, Technology Investigations" (Press release). NASA. Archived from the original on 19 August 2019. Retrieved 28 August 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  51. ^ "DRAFT Lunar Surface Instrument and Technology Payloads Call for Community Comment". Solar System Exploration Research Virtual Institute (SSERVI). NASA. 14 February 2018. Archived from the original on 3 August 2019. Retrieved 17 August 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  52. ^ "NASA Selects Experiments for Possible Lunar Flights in 2019" (Press release). NASA. 21 February 2019. Archived from the original on 16 August 2019. Retrieved 28 August 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  53. ^ Grush, Loren (18 November 2019). "NASA partners with SpaceX, Blue Origin, and more to send large payloads to the Moon". The Verge. Archived from the original on 6 December 2019. Retrieved 11 December 2019.
  54. ^ "New Companies Join Growing Ranks of NASA Partners for Artemis Program" (Press release). NASA. 18 November 2019. Archived from the original on 27 November 2019. Retrieved 11 December 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  55. ^ Jump up to: a b "NASA selects Masten Space Systems to deliver cargo to the Moon in 2022". Archived from the original on 28 April 2021. Retrieved 12 April 2020.
  56. ^ "Masten Space Systems Awarded $76M to Help NASA Deliver Lunar Sci-Tech Payloads - GovCon Wire". Archived from the original on 9 May 2020. Retrieved 3 May 2020.
  57. ^ Jump up to: a b "NASA Selects Firefly Aerospace for Artemis Commercial Moon Delivery in 2023". NASA (Press release). 4 February 2021. Archived from the original on 4 February 2021. Retrieved 4 February 2021.
  58. ^ "Lunar Lander". Firefly Aerospace. 1 February 2021. Archived from the original on 5 February 2021. Retrieved 4 February 2021.
  59. ^ Jump up to: a b c d Sheetz, Michael (30 April 2020). "NASA awards contracts to Jeff Bezos and Elon Musk to land astronauts on the Moon". cnbc.com. Archived from the original on 30 April 2020. Retrieved 30 April 2020.
  60. ^ Potter, Sean (3 December 2020). "NASA Selects Companies to Collect Lunar Resources for Artemis". NASA. Archived from the original on 28 January 2021. Retrieved 18 February 2021.
  61. ^ September 2020, Mike Wall 01. "Meet 'Lunar Cruiser': Japan's big moon rover for astronauts gets a nickname". Space.com. Archived from the original on 18 January 2021. Retrieved 18 February 2021.
  62. ^ "About". 7 Sisters. Archived from the original on 4 February 2021. Retrieved 18 February 2021.
  63. ^ "Ontario Lottery and Gaming Corporation - EVENING LOTTERY WINNING NUMBERS - March 28, 2021". www.yahoo.com. Archived from the original on 28 April 2021. Retrieved 5 April 2021.
  64. ^ "Exclusive: Trump administration drafting 'Artemis Accords' pact for moon mining". Reuters. 6 May 2020. Archived from the original on 15 May 2020. Retrieved 15 May 2020.
  65. ^ Wall, Mike (15 May 2020). "NASA lays out 'Artemis Accords' for responsible Moon exploration". Space.com. Archived from the original on 16 May 2020. Retrieved 16 May 2020.
  66. ^ Jump up to: a b Grush, Loren (13 October 2020). "US and seven other countries sign NASA's Artemis Accords to set rules for exploring the Moon". The Verge. Archived from the original on 13 October 2020. Retrieved 13 October 2020.
  67. ^ "Україна стала дев'ятою країною, яка підписала Домовленості в рамках програми "Артеміда"". nkau.gov.ua (in Ukrainian). Archived from the original on 15 November 2020. Retrieved 15 November 2020.
  68. ^ "NASA Administrator Signs Statement of Intent with Brazil on Artemis Cooperation". 14 December 2020. Archived from the original on 15 December 2020. Retrieved 15 December 2020.
  69. ^ Potter, Sean (27 May 2021). "Republic of Korea Joins List of Nations to Sign Artemis Accords". NASA.
  70. ^ Jump up to: a b Berger, Eric (31 May 2019). "NASA picks three companies to attempt Moon landings in 2020 and 2021". Ars Technica. Archived from the original on 15 February 2020. Retrieved 17 December 2019.
  71. ^ Barensky, Stefan (24 July 2019). "Airbus propose un remorqueur translunaire" (in French). Aerospatium. Archived from the original on 7 October 2019. Retrieved 10 January 2020.
  72. ^ Sloss, Philip (11 September 2018). "NASA updates Lunar Gateway plans". NASASpaceFlight.com. Archived from the original on 17 October 2018. Retrieved 17 October 2018.
  73. ^ Jump up to: a b c "NASA, Northrop Grumman Finalize Moon Outpost Living Quarters Contract". NASA (Press release). 9 July 2021. Retrieved 9 July 2021.
  74. ^ "NASA Awards Contract to Launch Initial Elements for Lunar Outpost". NASA (Press release). 9 February 2021. Archived from the original on 9 February 2021. Retrieved 9 February 2021.
  75. ^ Jump up to: a b c Gebhardt, Chris (17 June 2019). "NASA determining the best course for commercial Lunar Gateway resupply". NASASpaceFlight.com. Retrieved 28 August 2019.
  76. ^ Aguiar, Laura (14 June 2019). "NASA to Partner with American Industry to Supply Artemis Moon Missions" (Press release). NASA. Archived from the original on 21 August 2019. Retrieved 28 August 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  77. ^ Weitering, Hanneke (23 May 2019). "NASA Has a Full Plate of Lunar Missions Before Astronauts Can Return to Moon". Space.com. Archived from the original on 25 May 2019. Retrieved 28 August 2019. And before NASA sends astronauts to the moon in 2024, the agency will first have to launch five aspects of the Gateway, all of which will be commercial vehicles that launch separately and join each other in lunar orbit. First, a power and propulsion element will launch in 2022. Then, the crew module will launch (without a crew) in 2023. In 2024, during the months leading up to the crewed landing, NASA will launch the last critical components: a transfer vehicle that will ferry landers from the Gateway to a lower lunar orbit, a descent module that will bring the astronauts to the lunar surface, and an ascent module that will bring them back up to the transfer vehicle, which will then return them to the Gateway.
  78. ^ Smith, Marcia (26 May 2021). "Nelson: "Watch the Chinese"". SpacePolicyOnline.com. Retrieved 26 May 2021.
  79. ^ Jump up to: a b "Blue Origin wins lion's share of NASA funding for human-rated lunar lander". spaceflightnow.com. Spaceflight Now. 30 April 2020. Archived from the original on 1 May 2020. Retrieved 30 April 2020.
  80. ^ "Space Launch System". aerospaceguide.net. Archived from the original on 26 July 2019. Retrieved 11 December 2019.
  81. ^ "The NASA Authorization Act of 2010". Featured Legislation. Washington D.C., United States: United States Senate. 15 July 2010. Archived from the original on 10 April 2011. Retrieved 28 August 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  82. ^ Jump up to: a b c d e f g "Forward to the Moon: NASA's Strategic Plan for Human Exploration" (PDF). NASA. 4 September 2019 [Updated 9 April 2019]. Retrieved 9 December 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  83. ^ Kyle, Ed (16 May 2019). "NASA's Space Launch System". spacelaunchreport. Archived from the original on 6 June 2019. Retrieved 22 May 2019.
  84. ^ Loff, Sarah (16 October 2019). "NASA Commits to Future Artemis Missions With More SLS Rocket Stages". NASA. Archived from the original on 17 October 2019. Retrieved 18 October 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  85. ^ Jackson, Shanessa (11 September 2018). "Competition Seeks University Concepts for Gateway and Deep Space Exploration Capabilities". nasa.gov. NASA. Archived from the original on 17 June 2019. Retrieved 19 September 2018. Public Domain This article incorporates text from this source, which is in the public domain.
  86. ^ Greicius, Tony (20 September 2016). "JPL Seeks Robotic Spacecraft Development for Asteroid Redirect Mission". nasa.gov. Archived from the original on 17 June 2019. Retrieved 30 May 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  87. ^ "NASA closing out Asteroid Redirect Mission". spacenews.com. SpaceNews. 14 June 2017. Retrieved 30 May 2019.
  88. ^ "Asteroid Redirect Robotic Mission". jpl.nasa.gov. NASA. Archived from the original on 30 May 2019. Retrieved 30 May 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  89. ^ "NASA awards Artemis contract for lunar gateway power, propulsion". aerotechnews.com. 25 May 2019. Archived from the original on 30 May 2019. Retrieved 30 May 2019.
  90. ^ "Deep Space Gateway and Transport: Concepts for Mars, Moon Exploration Unveiled | Space Exploration". sci-news.com. Archived from the original on 30 May 2019. Retrieved 30 May 2019.
  91. ^ Clark, Stephen (24 May 2019). "NASA chooses Maxar to build keystone module for lunar Gateway station". Spaceflight Now. Archived from the original on 5 June 2019. Retrieved 30 May 2019.
  92. ^ Foust, Jeff (3 November 2017). "NASA issues study contracts for Deep Space Gateway element". SpaceNews. Retrieved 11 December 2019.
  93. ^ Gebhardt, Chris (6 April 2017). "NASA finally sets goals, missions for SLS – eyes multi-step plan to Mars". NASASpaceFlight.com. Archived from the original on 21 August 2017. Retrieved 9 April 2017.
  94. ^ Foust, Jeff (30 August 2019). "ISS partners endorse modified Gateway plans". SpaceNews. Retrieved 11 December 2019.
  95. ^ "NASA Asks American Companies to Deliver Supplies for Artemis Moon Missions" (Press release). NASA. 23 August 2019. NASA Press Release M019-14. Public Domain This article incorporates text from this source, which is in the public domain.
  96. ^ Planetary Society. "Humans in Deep Space". planetary.org. Archived from the original on 17 November 2019. Retrieved 6 August 2019.
  97. ^ Jump up to: a b Foust, Jeff (23 July 2019). "NASA to sole source Gateway habitation module to Northrop Grumman". SpaceNews. Retrieved 11 December 2019.
  98. ^ Jump up to: a b "Justification for other than full and open competition (JOFOC) for the Minimal Habitation Module (MHM)". fbo.gov. NASA. Archived from the original on 3 September 2019. Retrieved 23 July 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  99. ^ Anderson, Gina (5 June 2020). "NASA Awards Northrop Grumman Artemis Contract for Gateway Crew Cabin". NASA. Archived from the original on 8 November 2020. Retrieved 23 August 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  100. ^ Messier, Doug (23 July 2019). "NASA Awards Contract to Northrop Grumman for Lunar Gateway Habitat Module". Parabolic Arc. Archived from the original on 29 July 2019. Retrieved 11 December 2019.
  101. ^ "NASA takes Gateway off the critical path for 2024 lunar return". spacenews.com. SpaceNews. 13 March 2020. Archived from the original on 15 March 2020. Retrieved 16 March 2020.
  102. ^ Potter, Sean (27 October 2020). "NASA, European Space Agency Formalize Artemis Gateway Partnership". NASA. Archived from the original on 27 October 2020. Retrieved 28 October 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  103. ^ Wall, Mike (27 October 2020). "Europe will help build NASA's moon-orbiting Gateway space station". Space.com. Archived from the original on 1 November 2020. Retrieved 28 October 2020.
  104. ^ "Dragon XL revealed as NASA ties SpaceX to Lunar Gateway supply contract". NASASpaceFlight.com. 27 March 2020. Archived from the original on 28 March 2020. Retrieved 2 July 2020.
  105. ^ Jump up to: a b c d Potter, Sean (30 April 2020). "NASA Names Companies to Develop Human Landers for Artemis Missions". nasa.gov. NASA. Archived from the original on 11 May 2020. Retrieved 12 June 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  106. ^ Mahoney, Erin (22 October 2020). "NASA, Human Lunar Lander Companies Complete Key Artemis Milestone". NASA. Archived from the original on 31 October 2020. Retrieved 29 October 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  107. ^ Jump up to: a b c d Burghardt, Thomas (1 May 2020). "NASA Selects Blue Origin, Dynetics, and SpaceX Human Landers for Artemis". NASASpaceFlight.com. Archived from the original on 15 May 2020. Retrieved 12 June 2020.
  108. ^ Jump up to: a b Berger, Eric (30 April 2020). "NASA awards lunar lander contracts to Blue Origin, Dynetics and Starship". Ars Technica. Archived from the original on 13 May 2020. Retrieved 12 June 2020.
  109. ^ Potter, Sean (30 April 2020). "NASA Names Companies to Develop Human Landers for Artemis Missions". NASA. Archived from the original on 11 May 2020. Retrieved 15 May 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  110. ^ Jump up to: a b "NextSTEP H: Human Landing System". NASA. 27 January 2021. Archived from the original on 8 December 2020. Retrieved 31 January 2021.
  111. ^ Brown, Katherine (16 April 2021). "NASA Picks SpaceX to Land Next Americans on Moon". NASA. Archived from the original on 22 April 2021. Retrieved 22 April 2021.
  112. ^ Davenport, Christian. "Elon Musk's SpaceX wins contract to develop spacecraft to land astronauts on the moon". The Washington Post. Archived from the original on 16 April 2021. Retrieved 16 April 2021.
  113. ^ Jump up to: a b Brown, Katherine (16 April 2021). "As Artemis Moves Forward, NASA Picks SpaceX to Land Next Americans on Moon". NASA.gov. Archived from the original on 16 April 2021. Retrieved 17 April 2021.
  114. ^ Jump up to: a b "Dynetics protests NASA HLS award". SpaceNews. 27 April 2021. Retrieved 28 April 2021.
  115. ^ "Blue Origin protests NASA Human Landing System award". SpaceNews. 26 April 2021. Retrieved 28 April 2021.
  116. ^ https://www.theverge.com/2021/4/30/22412771/nasa-spacex-hls-moon-lander-blue-origin-protest
  117. ^ https://www.cnbc.com/2021/04/30/nasa-tells-spacex-to-halt-lunar-lander-work-pending-contract-challenges.html
  118. ^ Sirota, Sara; Grim, Ryan (25 May 2021). "Senate Preparing $10 Billion Bailout Fund for Jeff Bezos Space Firm". The Intercept. Retrieved 2 June 2021.
  119. ^ Ferreira, Becky (26 May 2021). "Bernie Sanders Is Fighting a Massive 'Bailout' to Jeff Bezos' Space Company". Vice. Retrieved 2 June 2021.
  120. ^ Berger, Eric (24 May 2021). "Bernie vs. Blue – Bernie Sanders wants to stop NASA funding for Blue Origin". Ars Technica. Retrieved 2 June 2021.
  121. ^ Hamilton, Isobel (25 May 2021). "Bernie Sanders is trying to block Jeff Bezos' Blue Origin from getting $10 billion NASA funding for a moon-landing mission". Business Insider. Retrieved 2 June 2021.
  122. ^ "S.1260 - Endless Frontier Act". Congress.gov. 8 June 2021. Retrieved 10 June 2021.
  123. ^ Berger, Eric (10 June 2021). "NASA doesn't need to test SLS anymore, but the Senate mandates it anyway". Ars Technica. Retrieved 10 June 2021.
  124. ^ Foust, Jeff (30 July 2021). "GAO denies Blue Origin and Dynetics protests of NASA lunar lander contract". SpaceNews. Retrieved 2 August 2021.
  125. ^ "Statement on Blue Origin-Dynetics Decision". 30 July 2021.
  126. ^ Sheetz, Michael (4 August 2021). "Bezos' Blue Origin calls Musk's Starship 'immensely complex & high risk' for NASA moon missions". CNBC. Retrieved 4 August 2021.
  127. ^ "Despite Of Competitor Protests NASA Pays SpaceX $300 Million To Continue Developing A Starship Lunar Lander". 14 August 2021.
  128. ^ "Jeff Bezos' Blue Origin sues NASA, escalating its fight for a Moon lander contract". The Verge. 16 August 2021. Retrieved 16 August 2021. protest prevented SpaceX from starting its contract for 95 days while the GAO adjudicated the case.
  129. ^ Sheetz, Michael (16 August 2021). "Bezos' Blue Origin takes NASA to federal court over award of lunar lander contract to SpaceX". CNBC. Retrieved 16 August 2021.
  130. ^ https://www.washingtonpost.com/technology/2021/08/16/blue-origin-spacex-rivalry-lawsuit-nasa/
  131. ^ Berger, Eric (16 August 2021). "Here's why Blue Origin thinks it is justified in continuing to protest NASA". Ars Technica.
  132. ^ "Dynetics To Develop Nasas Artemis Human Lunar Landing System". Dynetics. Archived from the original on 9 August 2020. Retrieved 24 August 2020.
  133. ^ Jump up to: a b D'Zio, Bill (1 May 2020). "NASA picks who will land people on the Moon... sort of..." westeastspace.com. Archived from the original on 17 May 2020. Retrieved 3 July 2020.
  134. ^ Mahoney, Erin (30 April 2020). "NASA Selects Blue Origin, Dynetics, SpaceX for Artemis Human Landers". NASA. Archived from the original on 4 March 2021. Retrieved 9 June 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  135. ^ Sheetz, Michael (19 August 2020). "Meet Dynetics, the company racing against SpaceX and Blue Origin to return astronauts to the Moon". cnbc.com. CNBC. Archived from the original on 30 August 2020. Retrieved 27 August 2020.
  136. ^ "Intuitive Machines selected to build engines for Boeing's Human Lander System Technology Development". intuitivemachines.com. 24 October 2019. Archived from the original on 9 November 2019. Retrieved 9 November 2019.
  137. ^ "Boeing Proposes "Fewest Steps to the Moon" for NASA's Human Lander". boeing.mediaroom.com. 5 November 2019. Archived from the original on 6 November 2019. Retrieved 6 November 2019.
  138. ^ Clark, Stephen. "Boeing proposes SLS-launched lunar lander". Spaceflight Now. Archived from the original on 11 November 2019. Retrieved 11 November 2019.
  139. ^ "NASA awards US$45.5 million to 11 American companies to "advance human lunar landers"". mlive.com. 22 May 2019. Archived from the original on 26 July 2020. Retrieved 3 July 2020.
  140. ^ "NASA studying three-stage approach to human-class lunar landers". spacenews.com. SpaceNews. 20 November 2018. Retrieved 2 July 2020.
  141. ^ Jump up to: a b Messier, Doug (8 December 2019). "Helping Heracles EL3 to Survive the Long, Cold, Dark Lunar Nights". Parabolic Arc. Archived from the original on 10 December 2019. Retrieved 10 December 2019.
  142. ^ Jump up to: a b Foust, Jeff (December 2019). "Funding Europe's space ambitions". The Space Review. Archived from the original on 29 December 2019. Retrieved 10 December 2019.
  143. ^ "The Heracles European Large Logistic Lander". esa.int. Archived from the original on 10 December 2019. Retrieved 10 December 2019.
  144. ^ Hebden, Kerry (29 November 2019). "Hera mission is approved as ESA receives biggest ever budget". Room. Archived from the original on 10 December 2019. Retrieved 10 December 2019.
  145. ^ Foust, Jeff (28 November 2019). "ESA declares success at ministerial meeting". SpaceNews. Retrieved 10 December 2019.
  146. ^ European Space Agency (29 May 2020). "Get Your Ticket to the Moon: Europe's First Ever Lunar Lander". SciTechDaily. Archived from the original on 28 April 2021. Retrieved 2 July 2020.
  147. ^ Jump up to: a b Landing on the Moon and returning home: Heracles. Archived 10 December 2019 at the Wayback Machine ESA. Accessed on 10 December 2019
  148. ^ "HERACLES: An ESA-JAXA-CSA Joint Study on Returning to the Moon. H. Hiesinger, M. Landgraf, W. Carey, Y. Karouji, T. Haltigin, G. Osinski, U. Mall, K. Hashizume, HERACLES Science Working Group, HERACLES International Science Definition Team. 50th Lunar and Planetary Science Conference 2019 (LPI Contrib. No. 2132)".
  149. ^ Landgraf, Markus; Carpenter, James; Sawada, Hirotaka (22 October 2015). HERACLES Concept - An International Lunar Exploration Study. Lunar Exploration Analysis Group (2015). Bibcode:2015LPICo1863.2039L. Retrieved 28 August 2019.
  150. ^ "Landing on the Moon and returning home: Heracles". ESA. 7 June 2019. Archived from the original on 29 August 2019. Retrieved 28 August 2019.
  151. ^ Lunar Robotic Mission Heracles Will Scout for Human Landings Archived 2 May 2020 at the Wayback Machine Elizabeth Howell, Space.com 28 June 2019
  152. ^ Pearlman, Robert Z. (10 January 2020). "NASA graduates new class of astronauts to join Artemis-era missions". Space.com. Archived from the original on 10 January 2020. Retrieved 10 January 2020.
  153. ^ "Meet the Artemis Team". NASA. Archived from the original on 22 January 2021. Retrieved 9 December 2020.
  154. ^ "Exploration EVA System Concept of Operations Summary for Artemis Phase 1 Lunar Surface Mission". ntrs.nasa.gov. NASA Technical Report Server. Archived from the original on 28 April 2021. Retrieved 18 April 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  155. ^ Jump up to: a b c d "NASA's Plan for Sustained Lunar Exploration and Development". nasa.gov.[dead link] Public Domain This article incorporates text from this source, which is in the public domain.
  156. ^ "NASA's Lunar Exploration Program Overview". NASA. 21 September 2020.[dead link] Public Domain This article incorporates text from this source, which is in the public domain.
  157. ^ Jump up to: a b c d Weitering, Hanneke (12 February 2020). "NASA has a plan for yearly Artemis moon flights through 2030. The first one could fly in 2021". Space.com. Archived from the original on 28 February 2020. Retrieved 20 February 2020.
  158. ^ "NASA to seek ideas for an Artemis lunar rover". SpaceNews. 20 November 2019. Retrieved 24 January 2020.
  159. ^ "NASA - Three Days in the Desert Tests Lunar "RV"". nasa.gov. Archived from the original on 26 July 2020. Retrieved 24 January 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  160. ^ Berger, Eric (15 July 2020). "NASA's first lunar habitat may be an RV-like rover built by Toyota". Ars Technica. Archived from the original on 15 July 2020. Retrieved 16 July 2020.
  161. ^ Bullard, Benjamin (15 July 2020). "NASA eyes closed-cabin rover "like an RV for the Moon" in first step toward long-term lunar presence". syfy.com. Archived from the original on 12 August 2020. Retrieved 16 July 2020.
  162. ^ Bartels, Meghan (16 October 2019). "Moon VIPER: NASA Wants to Send a Water-Sniffing Rover to the Lunar South Pole in 2022". Space.com. Archived from the original on 5 December 2020. Retrieved 10 December 2020.
  163. ^ Jump up to: a b Loff, Sarah (23 October 2019). "New VIPER Lunar Rover to Map Water Ice on the Moon". NASA. Archived from the original on 19 February 2021. Retrieved 7 January 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  164. ^ Bartels, Meghan (25 October 2019). "NASA Will Launch a Lunar VIPER to Hunt Moon Water in 2022". Space.com. Archived from the original on 2 January 2020. Retrieved 7 January 2020.
  165. ^ Mahoney, Erin (4 October 2019). "A Next Generation Spacesuit for the Artemis Generation of Astronauts". NASA. Archived from the original on 19 October 2019. Retrieved 24 October 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  166. ^ Crane, Aimee (15 October 2019). "Orion Suit Equipped to Expect the Unexpected on Artemis Missions". NASA. Archived from the original on 19 October 2019. Retrieved 24 October 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  167. ^ Jump up to: a b Pearlman, Robert (6 May 2010). "NASA tests Pad Abort system, building on 50 years of astronaut escape system tests". collectspace.com. Archived from the original on 25 May 2019. Retrieved 25 May 2019. "The Orion Pad Abort-1 team has successfully tested the first U.S. designed abort system since Apollo", said Doug Cooke, NASA's associate administrator for the exploration systems directorate, at a post-flight briefing [...] The PA1 test was conducted under NASA's Constellation program, which a former NASA administrator described as "Apollo on steroids".
  168. ^ David, Leonard (25 May 2019). "NASA Test Launches Rocket Escape System for Astronauts". Space.com. Archived from the original on 25 May 2019. Retrieved 25 May 2019. Called Pad Abort-1, the US$220 million Orion escape system test showcased the system that could be used to rescue a crew and its spacecraft in case of emergencies at the launch pad.
  169. ^ Davis, Jason (5 December 2014). "Orion Returns to Earth after Successful Test Flight". The Planetary Society. Archived from the original on 25 May 2019. Retrieved 25 May 2019. NASA's Orion spacecraft returned safely to Earth this morning following a picture-perfect test mission. [...] Orion itself was originally part of NASA's now-defunct Constellation program, and is now a key component of the space agency's Mars plans.
  170. ^ Clark, Stuart; Sample, Ian; Yuhas, Alan (5 December 2014). "Orion spacecraft's flawless test flight puts Mars exploration one step closer". The Guardian. Archived from the original on 25 May 2019. Retrieved 25 May 2019. The launch at 12.05 UTC aboard a Delta IV heavy rocket from Cape Canaveral, Florida, was as free of problems as Thursday's aborted attempt was full of them. Immediately, Nasa tweeted "Liftoff! #Orion's flight test launches a critical step on our #JourneytoMars".
  171. ^ Kramer, Miriam (5 December 2014). "Splashdown! NASA's Orion Spaceship Survives Epic Test Flight as New Era Begins". Space.com. Archived from the original on 17 October 2018. Retrieved 17 October 2018. Orion's key systems were put to the test during the flight, which launched atop a United Launch Alliance Delta 4 Heavy rocket [...] the craft hit Earth's atmosphere as the capsule was flying through space at about 20,000 mph (32,000 km/h).
  172. ^ "Orion Exploration Flight Test No. 1 timeline". Spaceflight Now. 4 December 2014. Archived from the original on 9 December 2014. Retrieved 17 October 2018. The first orbital test flight of NASA's Orion crew capsule will lift off on top of a United Launch Alliance Delta 4 rocket from Cape Canaveral's Complex 37B launch pad. The rocket will send the unmanned crew module 3,600 miles above Earth...
  173. ^ Sloss, Philip (24 May 2019). "NASA Orion AA-2 vehicle at the launch pad for July test". NASASpaceFlight.com. Archived from the original on 25 May 2019. Retrieved 25 May 2019. This will be the second and final planned LAS test following the Pad Abort-1 (PA-1) development test conducted in 2010 as a part of the ccanceled [sic] Constellation Program and the abort system design changed from PA-1 to AA-2 both inside and outside [...] in preparation for a scheduled daybreak test on 2 July 2010.
  174. ^ "Image: The Orion test crew capsule". Phys.org. 3 August 2018. Archived from the original on 17 October 2018. Retrieved 17 October 2018. In the Ascent Abort-2 test, NASA will verify that the Orion spacecraft's launch abort system can steer the capsule and astronauts inside it to safety in the event of an issue with the Space Launch System rocket when the spacecraft is under the highest aerodynamic loads it will experience during ascent...
  175. ^ Jump up to: a b Johnson Space Center (November 2017). "Ascent Abort Flight Test-2". NASA. Retrieved 17 October 2018. In April 2019, Orion is scheduled to undergo a full-stress test of the LAS, called Ascent Abort Test 2 (AA-2), where a booster provided by Orbital ATK will launch from Cape Canaveral Air Force Station in Florida, carrying a fully functional LAS and a 22,000-pound Orion test vehicle...[dead link] Public Domain This article incorporates text from this source, which is in the public domain.
  176. ^ Orbital Sciences Corporation (11 April 2007). "Orbital to Provide Abort Test Booster for NASA Testing". Northrop Grumman. Archived from the original on 25 May 2019. Retrieved 25 May 2019. Orbital Sciences Corporation (NYSE:ORB) today announced that it has been selected [...] to design and build the next-generation NASA Orion Abort Test Booster (ATB).
  177. ^ Grush, Loren (22 January 2020). "NASA administrator on the year ahead: 'A lot of things have to go right'". The Verge. Archived from the original on 22 January 2020. Retrieved 22 January 2020.
  178. ^ "NASA's development of next-generation spacesuits" (PDF). 10 August 2021. , the suits would not be ready for flight until April 2025 at the earliest ... a lunar landing in late 2024 as NASA currently plans is not feasible.
  179. ^ "NASA's Management of the Gateway Program for Artemis Missions" (PDF). Office of Inspector General (OIG). NASA. 10 November 2020. p. 3. Archived (PDF) from the original on 28 April 2021. Retrieved 4 January 2021. Artemis IV is scheduled to launch in March 2026 (as of August 2020). Public Domain This article incorporates text from this source, which is in the public domain.
  180. ^ "FY 2022 Budget Estimates – Gateway – Program Projects – International Habitat (I-Hab)" (PDF). NASA. 6 May 2021. p. 97. Retrieved 9 July 2021. Delivery of I-Hab to the Gateway will be via the SLS Block 1B launch vehicle with Orion providing orbital insertion and docking.
  181. ^ Davenport, Christion (10 July 2019). "Shakeup at NASA as space agency scrambles to meet Trump moon mandate". The Washington Post. Archived from the original on 11 July 2019. Retrieved 10 July 2019.
  182. ^ Berger 2019a. "Developed by the agency's senior human spaceflight manager, Bill Gerstenmaier, this plan is everything Pence asked for — an urgent human return, a Moon base, a mix of existing and new contractors".
  183. ^ Jump up to: a b Foust 2019a. "After Artemis 3, NASA would launch four additional crewed missions to the lunar surface between 2025 and 2028. Meanwhile, the agency would work to expand the Gateway by launching additional components and crew vehicles and laying the foundation for an eventual Moon base".
  184. ^ Berger 2019a. "This decade-long plan, which entails 37 launches of private and NASA rockets, as well as a mix of robotic and human landers, culminates with a "Lunar Surface Asset Deployment" in 2028, likely the beginning of a surface outpost for long-duration crew stays".
  185. ^ Jump up to: a b Berger 2019a, [Illustration]. "NASA's "notional" plan for a human return to the Moon by 2024, and an outpost by 2028".
  186. ^ Foust, Jeff (18 April 2019). "Independent report concludes 2033 human Mars mission is not feasible". SpaceNews. Archived from the original on 22 August 2020. Retrieved 6 December 2019.
  187. ^ "Rocket Lab to Launch NASA Funded Commercial Moon Mission from New Zealand". Rocket Lab (Press release). 6 August 2021. Retrieved 8 August 2021.
  188. ^ Potter, Sean (31 May 2019). "NASA Selects First Commercial Moon Landing Services for Artemis". NASA. Archived from the original on 16 December 2019. Retrieved 17 December 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  189. ^ "Astrobotic Selects United Launch Alliance Vulcan Centaur Rocket to Launch its First Mission to the Moon". ulalaunch.com. United Launch Alliance. Archived from the original on 19 August 2019. Retrieved 17 December 2019.
  190. ^ "NASA Lunar ISRU Strategy" (PDF). ntrs.nasa.gov. NASA. Archived (PDF) from the original on 20 February 2020. Retrieved 20 February 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  191. ^ "Intuitive Machines picks SpaceX for second Moon mission". Houston Chronicle. 13 January 2021. Archived from the original on 13 January 2021. Retrieved 13 January 2021.
  192. ^ "NASA selects Masten Space Systems to deliver cargo to the Moon in 2022". TechCrunch. Archived from the original on 28 April 2021. Retrieved 12 April 2020.
  193. ^ "SpaceX will launch Masten's first lander to the Moon in 2022". TechCrunch. Archived from the original on 28 April 2021. Retrieved 27 August 2020.
  194. ^ Jump up to: a b "NASA Selects Astrobotic to Fly Water-Hunting Rover to the Moon". NASA. 11 June 2020. Archived from the original on 25 June 2020. Retrieved 24 June 2020. Public Domain This article incorporates text from this source, which is in the public domain.
  195. ^ Loff, Sarah (23 October 2019). "New VIPER Lunar Rover to Map Water Ice on the Moon". NASA. Archived from the original on 19 February 2021. Retrieved 17 December 2019. Public Domain This article incorporates text from this source, which is in the public domain.
  196. ^ "Archived copy". Archived from the original on 19 April 2021. Retrieved 14 April 2021.CS1 maint: archived copy as title (link)
  197. ^ Howell, Elizabeth (22 November 2019). "NASA Eyes a New Moon Rover for Astronauts and Robot Lunar Explorers". Space.com. Archived from the original on 28 June 2020. Retrieved 5 April 2020.
  198. ^ Whittington, Mark (16 June 2018). "NASA's unnecessary US$504 million lunar orbit project doesn't help us get back to the Moon". The Hill. Archived from the original on 14 November 2019. Retrieved 20 December 2018.
  199. ^ Moon Direct. Retrieved from https://www.thenewatlantis.com/publications/moon-direct Archived 28 April 2021 at the Wayback Machine.
  200. ^ Foust, Jeff (16 November 2018). "Advisory group skeptical of NASA lunar exploration plans". SpaceNews. Retrieved 20 December 2018.
  201. ^ "House introduces NASA authorization bill that emphasizes Mars over moon". SpaceNews. 25 January 2020. Archived from the original on 27 January 2020. Retrieved 27 January 2020.
  202. ^ Clark, Stephen. "Bipartisan House bill spurns 2024 Moon landing goal, favoring focus on Mars". Spaceflight Now. Archived from the original on 27 January 2020. Retrieved 27 January 2020.
  203. ^ "Three winning bids for NASA's human landing system". spacepolicyonline.com. Archived from the original on 3 July 2020. Retrieved 3 July 2020.
  204. ^ Gohd, Chelsea (16 March 2020). "NASA's "critical path" to the Moon no longer requires a Lunar Gateway". Space.com. Archived from the original on 16 May 2020. Retrieved 3 July 2020.

Sources[]

External links[]

Retrieved from ""