Extension of Island line to Western District

From Wikipedia, the free encyclopedia

Extension of Island Line to Western District
港島綫西延
Overview
LocaleDistricts: Central and Western
TerminiKennedy Town
Sheung Wan
Stations3
Service
TypeHeavy rail (rapid transit)
SystemMTR
History
Opened28 December 2014; 7 years ago (2014-12-28) (HKU and Kennedy Town)
29 March 2015; 6 years ago (2015-03-29) (Sai Ying Pun)
Technical
Track gauge1,435 mm (4 ft 8+12 in)
Electrification1.5 kV DC
Route map
South Island Line and West Island Line proposal.svg

Legend
Colour legend
West Island Line


Kennedy Town
HKU
Sai Ying Pun
Sheung Wan

The Extension of Island line to Western District (previously known as West Island line) is a three-station western extension of the Hong Kong MTR's Island line. Construction of the line began on 10 August 2009, and the two westernmost stations on line opened on 28 December 2014; the intermediary Sai Ying Pun station opened on 29 March 2015.[1][2] The first train went into service that day at 6:00 a.m. Hong Kong time.

History[]

Initial proposals[]

The MTR Corporation Limited (MTRC) submitted its first proposal for the West Island line in May 2002. This was similar to the final alignment, with stations at Sai Ying Pun, Belcher and Kennedy Town. In revisions in 2003 and 2004, the West Island line became its own line, which would interchange with the Island line at Sheung Wan or Sai Ying Pun. On 28 May 2004, planning for the line was deferred.

Alignment of Original Scheme

Final scheme[]

Alignment of the final scheme

On 25 February 2005, the Panel of Transport of Legislative Council had a meeting discussing the West and South Island lines. MTR submitted a revised scheme on 22 February. An introduction to the scheme was conducted in the meeting.

In the scheme, the West Island line included only the extension to Island line. The rest became the west section of South Island line. The Extension of Island line to Western District would run from Sheung Wan to Kennedy Town:

The scheme was gazetted in October 2007 and given final authorisation in March 2009.[2] Construction of the 3-kilometre extension started on 10 August 2009, for completion in 2014.[2] The cost of the extension is estimated to be HK$15.4 billion.[2]

Project details[]

Construction cost[]

According to the summary report of the new lines, the construction cost of the Extension of Island Line to Western District would be HK$15.4 billion (as at Dec 2008). MTR asked for government funding of less than half of the total cost. The remaining cost and the operational cost would be covered by MTR.

Features[]

One of the "lift-only" exits at HKU
New Ticket Machines at Kennedy Town

Some features are firstly introduced into these new stations to enhance services and facilities. The "lift-only" entrances are placed at HKU and Sai Ying Pun due to the depth of these station. Several high-speed lifts with doors on both sides allow to transport a high volume of passengers in and out of the stations. When fire in stations, these lifts can also be used for evacuation. Fire shutters of each lift will be lowered and air within lift will be pressurised to prevent smoke and fire.[3]

The new multi-purpose ticket machines are installed at West Island Line concourse. Using touch screens, it combines the existing functions of ticket vending machine and add-value machine. It can also buy single journey ticket and City Saver by cash or Octopus card.[4]

See also[]

References[]

  1. ^ "West Island Line targets to open in December 2014, 90% of works complete" (PDF). MTR Corporation. 29 May 2014.
  2. ^ a b c d http://www.mtr.com.hk/eng/corporate/file_rep/PR-09-093-E.pdf
  3. ^ First MTR Lift-only Entrances at HKU and Sai Ying Pun Stations Provide Convenient Vertical Access, MTR,19 November 2014