Iron Gate II Hydroelectric Power Station

From Wikipedia, the free encyclopedia
Iron Gate II Hydroelectric Power Station
Dam Serbia Djerdap 2.jpg
LocationGogoșu, Mehedinți County,
Romania
Mihajlovac, Bor District,
Serbia
Coordinates44°18′16″N 22°33′54″E / 44.30444°N 22.56500°E / 44.30444; 22.56500Coordinates: 44°18′16″N 22°33′54″E / 44.30444°N 22.56500°E / 44.30444; 22.56500
Construction began1977
Opening date1984
Dam and spillways
ImpoundsDanube River
Height35 m (115 ft)
Length412 m (1,352 ft)[1]
Reservoir
CreatesIron Gates II Reservoir
Total capacity0.6 km3 (0.14 cu mi)
Catchment area579,200 km2 (223,600 sq mi)
Surface area52 km2 (20 sq mi)
Power Station
TurbinesRomania: 10 × 32 MW
Serbia: 10 × 27 MW
Installed capacityRomania: 321 MW
Serbia: 270 MW
Annual generationRomania: 1.3 TWh
Serbia: 1.31 TWh

The Iron Gate II (Romanian: Porțile de Fier II, Serbian: Ђердап II, romanizedĐerdap II) is a large dam on the Danube River, between Romania and Serbia.

Characteristics[]

The dam is built at the Danube's 853 km (530 mi).[2] The project started in 1977 as a joint-venture between the governments of Romania and Yugoslavia for the construction of large dam on the Danube River which would serve both countries. At the time of completion in 1984 the dam had 16 units generating a total of 432 MW, divided equally between the two countries at 216 MW each.

The Romanian part of the power station was modernised and another 2 units were installed; the nominal capacity of the 10 units was increased from 27 MW to 32 MW thus having an installed capacity of 321 MW. The Romanian side of the power station produces approximately 1.3 TWh per annum.

The Serbian part of the power station currently has 10 units with a nominal capacity of 27 MW each and a total power generation capacity of 270 MW.[3] producing approximately 1.31 TWh per annum. At the celebration ceremony for the 27 years since the power station's deployment it was announced that production in 2011 reached 1.46 TWh despite bad weather conditions.[4] As of 2018 the Serbian side of the power plant is in the process of revitalization; when finished, the power of each aggregate will be lifted from 27 to 32 MW.[2]

Current total power generation capacity of the power station is 591 MW.

In 2011, a border checkpoint between Serbia and Romania for cars and light cargo vehicles was open.

Iron Gate III Hydroelectric Power Station[]

Plans for the third dam were drafted in 1973 by the Energoprojekt holding and Jaroslav Černi Institute. Selected location was the village of Dobra, in the Golubac municipality, at the Danube's 1,007 kilometres (626 mi). Iron Gate III was planned as the reversible power plant, which would pump water into the uphill reservoirs on the Brodica, Pesača and Železnički Potok localities. The tunnels were to lift water from the altitude of 68 metres (223 ft) (Danube level), to 407 metres (1,335 ft) (uphill reservoirs). The reservoirs would also accept water from the neighboring streams, and collect a total of 587,000,000 cubic metres (2.07×1010 cu ft) of water. All reservoirs would be connected with tunnels, from 1.95 kilometres (1.21 mi) (Pesača-Vodostan) to 8.1 kilometres (5.0 mi) long (Brodica-Pesača). In total, after three phases of construction, the power plant would have a total installed capacity of 2,400 MW.[5]

The studies were conducted into the 1980s, and the terrain was surveyed and measured, as it is made of karst. Apart from Yugoslavia and Romania, representatives of the electric companies from USSR and West Germany also participated in the surveys. Romania was to build a similar facility on its side of the river. Both states also planned additional power plants of 120 MW adjoining the third dams, which were to function only during the high water levels, accepting the water surplus. Uphill the Danube, Yugoslavia also planned additional reversible power plant "Bistrica" (680 MW), operational only on water streams in the hills, so the permit from the Danube Commission would not be needed. If built at the time, the Iron Gate III-Bistrica system would make 37% of Serbian electricity production capacity in 2021.[5]

See also[]

References[]

  1. ^ Specifications
  2. ^ a b Slobodan T. Petrović (14 March 2018). ""Đerdap 2" najbliža veza sa Rumunijom" ["Đerdap 2" closest link to Romania]. Politika (in Serbian). p. 25.
  3. ^ HE Đerdap 2 Technical Features (in Serbian) Archived 2012-03-06 at the Wayback Machine
  4. ^ Municipality of Negotin: Iron Gate 2 Day
  5. ^ a b Slobodan T. Petrović (30 September 2021). "Budućnost EPS-a je u "Đerdapu 3"" [Future of EPS is in "Đerdap 3"]. Politika (in Serbian). p. 14.