Putrajaya line

From Wikipedia, the free encyclopedia

Putrajaya Line
KLRT Line 12 icon.svg
Train of MRT Putrajaya Line.jpg
4-coach Hyundai Rotem EMU rolling stock during a test run, often referred to as "Ducky"
Overview
Native nameMRT Laluan Putrajaya
StatusUnder construction
95.33% as of 31 October 2021
OwnerMRT Corp
Line number12 (Yellow)
LocaleKlang Valley
Termini PY01  Kwasa Damansara
 PY13  Kampung Batu (Phase 1)
 PY41  Putrajaya Sentral (Phase 2)
Stations34[1][Note 1]
Websitemymrt.com.my
Service
TypeRapid transit
SystemRapid KL
ServicesSungai BulohKuala LumpurSerdangPutrajaya
Operator(s)Rapid Rail
Depot(s)Sungai Buloh Depot
Serdang Depot
Rolling stock49 Hyundai Rotem four-car trainsets (wide profile)
History
Planned openingPhase 1: Q2 2022
Kwasa DamansaraKampung Batu
Phase 2: January 2023; 1 year's time (2023-01)
Kampung BatuPutrajaya Sentral
Technical
Line length57.7 km (35.9 mi) start from Kwasa Damansara
52.2 km (32.4 mi)
Elevated: 38.75 km (24.08 mi)
Underground: 13.5 km (8.4 mi)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
ElectrificationThird rail, 750 VDC
Conduction systemAutomated and driverless
Route map

Legend
KG04/PY01
Kwasa Damansara
Parking Integrated Transport Terminal Sungai Buloh
9
KG03/PY02
(provisional station)
KG02/PY03
Kampung Selamat
KG01/PY04
Sungai Buloh
Parking
MRT1 Phase 1: operational
MRT2 Phase 1: opening March 2022
PY05
Damansara Damai
PY06
Sri Damansara Barat
PY07
Sri Damansara Sentral
PY08
Sri Damansara Timur
Parking
PY09
Metro Prima
PY10
Kepong Baru
PY11
Jinjang
PY12
Sri Delima
PY13
Kampung Batu
Parking
MRT2 Phase 1: opening March 2022
MRT2 Phase 2: opening January 2023
PY14
Kentonmen
PY15
Jalan Ipoh
PY16
Sentul Barat
PY17
Titiwangsa
3 4 8
PY18
Hospital Kuala Lumpur
PY19
Raja Uda
PY20
Ampang Park
Multiple fare trips5
PY21
Persiaran KLCC
PY22
Conlay
PY23
Tun Razak Exchange
9
PY24
Chan Sow Lin
3 4
PY25
Bandar Malaysia Utara
(future station)
PY26
Bandar Malaysia Selatan
 ETS   HSR  ( future station)
PY27
Kuchai
Parking
PY28
Taman Naga Emas
Parking
PY29
Sungai Besi
Parking
4
PY30
Parking (future station)
PY31
Serdang Raya Utara
Parking
PY32
Serdang Raya Selatan
Parking
PY33
Serdang Jaya
PY34
UPM
Parking
PY35
Taman Universiti
(future station)
PT36
Taman Equine
Parking
PY37
Putra Permai
PY38
16 Sierra
PY39
Cyberjaya Utara
Parking
PY40
Cyberjaya City Centre
PY41
Putrajaya Sentral
Parking  ECR 

Interchange stations

integrated paid area
single fare trip
non-integrated paid area
multiple fare trips
Route of Putrajaya line

The MRT Putrajaya Line or MRT 2, previously known as the Sungai Buloh–Serdang–Putrajaya Line (SSP Line), will be the twelfth rail transit line, the second Mass Rapid Transit (MRT) line, and the fourth fully automated and driverless rail system in the Klang Valley area. It is a part of the larger rail transport system in Kuala Lumpur known as the Klang Valley Integrated Transit System. The line is numbered 12 and coloured yellow on official transit maps.

It is one of three planned mass rapid transit (MRT) rail lines under the Klang Valley Mass Rapid Transit Project by MRT Corp. Phase 1 operations of the line between Kwasa Damansara and Kampung Batu stations is scheduled to be operational by March 2022.[2] The remaining line is expected to be operational in January 2023.[3][4]

The approved rail alignment is 52.2 km in length, of which 13.5 km is underground. A total of 37 stations, 11 of them underground, will be built. The line will stretch from Sungai Buloh to Putrajaya and will include densely populated areas Sri Damansara, Kepong, Batu, Jalan Ipoh, Jalan Sultan Azlan Shah, Jalan Tun Razak, KLCC, Tun Razak Exchange, Kuchai Lama, Seri Kembangan and Cyberjaya. It is expected to have a ridership of 533,000 passengers per day once completed.

The only half-sunken Jalan Ipoh MRT station along with its pedestrian bridge in the background

Chronology[]

 KG04  PY01  Kwasa Damansara cross-platform interchange station between Kajang Line and the Putrajaya Line line will commence in 2022.
 KG04  PY01  Kwasa Damansara station Level 2 island platform
 KG04  PY01  Kwasa Damansara level and platform signage, showing platforms 3 and 4 dedicated for the Putrajaya Line
 KG20  PY23  Tun Razak Exchange station's Putrajaya Line future platform
  • 13 October 2014 – The 2nd MRT line is now planned to be from Sungai Buloh, Selayang to Pandan;[5] instead of from Kuala Lumpur to Port Klang.[6][7][8]
  • 3 December 2014 – During a briefing of the 1st MRT line, the MRT CEO revealed more details about the 2nd line. He had said that the line will be 59.5 km long with 49.3 km will be elevated and 10.2 km will be underground. There will be 40 stations where 31 will be elevated and 9 will be underground. Construction is expected to begin by November 2015 will approval and public discussion starts in early 2015.[9][10]
  • 12 February 2015 – MRT Corp prepares tender for MRT2, project display in Q2.[11]
  • 16 March 2015 – MRT2 from Sungai Buloh to Putrajaya has been approved by the Federal government.[12] The project was allocated RM23 billion in the Budget 2015.[13]
  • 2 April 2015 – New alignment for MRT2 proposed.[14] The alignment south of Tun Razak Exchange was then altered drastically to provide connectivity with the proposed High Speed Rail project. With this revision, the line stands at 52.2 km long with a total of 36 stations. Of these, 11 are underground while 25 are elevated.
  • 22 April 2015 – Department of Environment (DOE)'s Detailed Environment Impact Assessment (DEIA) for the MRT2 is available for download from their website.
  • 14 May 2015 – Details of MRT2 project on public display start on 15 May 2015. The public can visit the SPAD office, MRT Corp offices, Kuala Lumpur City Hall, Selayang Municipal Council and Petaling Jaya City Council, with roadshows, primarily at shopping malls near the MRT2 alignment.[15]
  • 12 August 2016 – On the MRT2 project, the groundbreaking ceremony was expected to be held at end of the month of August 2016 or early September 2016.[16]
  • 15 September 2016 – Construction on the MRT line launched with a groundbreaking ceremony at the site of the future Putrajaya Sentral MRT station by former Prime Minister Dato' Seri Najib Tun Razak.[17]
  • 31 March 2017 – The line is 5.3% completed.[18]
  • 24 May 2017 – 7.5% of the line was completed. For the elevated section, progress of the first and second packages are at 20.9% and 10.3% respectively with increased works being seen from Jalan Kuala Selangor to Jalan Kepong. Whereas for underground works, the work progress was at 8.7%.[19]
  • June 2017 – The line is 10.25% completed, based on the video released by MRT Corp in 18 December 2017.
  • 5 September 2017 – The line has reached the completion of 12.05% and expected to reach 19% by the end of 2017. The underground works will commence by the first quarter of 2018 with the arrival of 2 Tunnel Boring Machine (TBMs) within 2–3 weeks and another 2 of them by early next year.[20][21]
  • 26 September 2017 – The project director Datuk Amiruddin Ma’aris mentioned the line is currently achieved completion of 13.70%.[22]
  • 28 September 2017 – According to the MRT Corp director of underground works for the MRT line, Blaise Mark Pearce, 23% of the underground works for the MRT line were expected to be completed by the end of 2017.[23]
  • 10 October 2017 – An explosion has occurred at the Mass Rapid Transit (MRT) station construction site in Bandar Malaysia. According to the police, it was believed that the explosion happened because of an old unexploded bomb from the Second World War through the initial investigation. Three Bangladesh workers were seriously injured and two of them lost their legs while another suffered injuries on the hands and legs.[24]
  • 13 October 2017 – Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) has won the prestigious “Be Inspired Awards 2017” for its use of Building Information Modelling (BIM) in the construction of the MRT line.[25]
  • 13 November 2017 – The first Tunnel Boring Machine arrived in Port Klang and delivered to site. The rest are expected to arrive in coming weeks.[26]
  • 18 December 2017 – MRT Corp released a video describing the progress of the MRT line from 2016 to 2017 in YouTube. The progress is described in packages. The progress statistics are: 23.68%, 15.43%, 9.05%, 10.32%, 35.31% and 11.51% respectively for packages V201, V202, V203, V210, Serdang Depot and underground.[27]
  • 1 January 2018 – Malaysia's 1st shopping mall, Ampang Park, is officially ceased its operation in order to make way to the construction of the Ampang Park station under such line.
  • 18 February 2018 – The line has achieved 21% completion. The final Tunnel Boring Machine for the MRT line is expected to be launched by mid-2019.[28]
  • 1 March 2018 – Underground works commenced with the first Tunnel Boring Machine. The launching is done at the shaft located at the Bandar Malaysia North MRT station. The line has achieved 22% completion according to the CEO of the MRT Corp, Datuk Seri Shahril Mokhtar.[29]
  • 3 March 2018 – A construction worker died while two others survived when a launching gantry at an MRT construction site in Jalan Jinjang (Work Package V203), collapsed at around 11:40pm.[30]
  • 23 April 2018 – The Director of Strategic Communications and Stakeholder Relations from MRT Corp, Dato' Najmuddin Abdullah, says the line is now completed at the progress of more than 24%.[31]
  • June 2018 – The line is 30% completed, based on the video released by MRT Corp in 9 December 2018.
  • 11 July 2018 – The line was close to 30% complete as at early July, according to the project director Datuk Amiruddin Ma’aris.[32]
  • 8 October 2018 – The Finance Minister, Lim Guan Eng announced the decision to change the project structure as well as terminate the contract from MMC-Gamuda and re-tender the unfinished underground portion of the project by an open tender process, due to the fact the Federal Government and MMC-Gamuda have failed to reach an agreement relating to the underground portion of the construction project. This decision had caused a lot of protests from MMC-Gamuda and workers due to the fact that some 20,000 workers tend to lose their job.[33][34]
  • 9 October 2018 – The shares of MMC and Gamuda fell due to the government's decision to terminate the underground section project.[35]
  • 10 October 2018 – The Prime Minister, Tun Dr. Mahathir Mohamad told the press that the decision to cancel the contract from MMC-Gamuda for the underground portion will be reconsidered.[36]
  • 11 October 2018 – The Economic Affairs' Minister, Dato' Seri Azmin Ali confirmed that the Cabinet has set up a committee to review the underground contract that was awarded to MMC-Gamuda for the project. According to the source, the four members of the committee are Minister of Finance Lim Guan Eng, Minister of Works Baru Bian, Transport Minister Anthony Loke and Economic Affairs Minister Azmin Ali.[37]
  • 17 October 2018 – The Finance Minister, Lim Guan Eng said the decision to terminate the contract was Cabinet's decision.[34]
  • 26 October 2018 – Due to budget concerns, and a re-tender, construction costs proposed by MMC-Gamuda is about half what it was previously. The two Bandar Malaysia Stations have also been cancelled. The cost for construction of the underground portion is now RM13.11 billion. This brought to the entire cost for this project to be RM30.53 billion from the RM39.35 billion previously. This means MMC-Gamuda now secured the contract of the underground section and allowed to continue the construction.[38][39]
  • 13 November 2018 – Three MRT stations from the MRT Kajang Line (Sungai Buloh, Kampung Selamat and Kwasa Damansara) closed for two days to accommodate the first migration system works of the line.
  • 9 December 2018 – MRT Corp released another video describing the progress of the MRT line from 2017 to 2018 in YouTube. The progress is described in packages. The progress for all packages have been mentioned. Package V201 achieved the highest progress with 45.7% whilst package V206 achieve the lowest progress with 13.1%. Underground section had the progress with 33.3%.[40]
  • 24 January 2019 – The first batch of carriages for the two sets of trains have arrived at Westport, Port Klang.
  • 29 January 2019 – First TBM breakthrough happened at Chan Sow Lin station. The TBM was bored between Bandar Malaysia North and Chan Sow Lin. MRT Corp Sdn Bhd strategic communications and stakeholder relations director, Datuk Najmuddin Abdullah said the overall construction was on track with a 41% completion rate as of December 2018.[41]
  • 9 March 2019 – Three MRT stations from the MRT Kajang Line (Sungai Buloh, Kampung Selamat and Kwasa Damansara) closed again for two days to accommodate the second migration system works of the line.[42]
  • 15 March 2019 – Second TBM breakthrough at Chan Sow Lin station based on the Instagram source from Datuk Najmuddin Abdullah.[43]
  • 15 March 2019 – Ninth and final TBM breakthrough of the year at Ampang Park station.[44]
  • 17 January 2020 – MRT is 70% completed with expected completion date for Phase 2 delayed to January 2023.[45]
  • 31 October 2020 – MRT Putrajaya Line construction is 82.51% completed. Phase One from the Kwasa Damansara to the Kampung Batu will begin operations in July 2021, while the rest of the line from the Kampung Batu Station to the Putrajaya Sentral will be operational under Phase Two in January 2023.
  • 3 April 2021 – The Construction progress of Phase One section of the MRT Putrajaya Line (Kwasa DamansaraKampung Batu) is at 97% and will begin operations in August 2021.[46]
  • 7 July 2021 - MRT Corp decided to postpone the opening of phase 1 from August to mid-November 2021 due to the COVID-19 movement control order in Malaysia.[4]
  • 16 November 2021 - MRT Corp announced that Phase 1 opening will be delayed again to March 2022 as further tests are required. No exact date was provided.
  • 2 December 2021 - MMC-Gamuda won Major Project of the Year award from International Tunnelling and Underground Space Association (ITA) for projects above 500 million euros. They managed to beat out the Ismailia Tunnels project under the Suez Canal, Egypt and Shantou Bay Tunnel project from China.[47]
  • 6 December 2021 - MMC Gamuda also bagged the International Project of the Year at the Ground Engineering Awards 2021 in London.[47]

Station designs[]

Elevated station concepts[]

The proposed design for the elevated stations is based on the “Serambi” concept. This concept is focused on the inspiring interaction and communication at a foyer or entrance space of a house such as the entrance space at a traditional “rumah kampung” or “rumah panjang”. The design opted is a simple and timeless design, which is derived from various design concepts, including that of the Japanese “Zen” concept. Other aspects include open space, natural lighting and ventilation, and natural visual effects via play of lighting and shadows.[48]

Compared to the Kajang Line's elevated station design, the columns have been pushed to the sides of the station, giving the stations an open and airy feel.

Underground station concepts[]

Each of the underground stations will carry its own individual theme, similar to that of the Kajang Line stations. The proposed designs range from preserving the rustic, reflecting tidal rhythm, promoting well-being, vibrancy, pulse of life, discovering culture, molding forms, inspired by nature to streamlined flow.[48]

List of stations[]

The MRT Putrajaya Line Route Map

Following the initial proposal during the public display period, 37 stations have been approved along 52.2 km of track.[49]

The stations listed below are as displayed on the government website for the draft environmental impact assessment.[50] All the station names are interim and subject to change.

28 (23 elevated + 1 half-sunken + 4 underground) out of 35 stations (excluding the ones on the MRT Kajang Line) are expected to have feeder bus services.

Station Code Station Name Image Platform type Position Park & Ride MRT Feeder Bus Lines Working Name Interchange/Notes
 KG04  PY01  Kwasa Damansara MRT SBK Kwasa Damansara station.jpg Stacked Island Elevated N/A Kota Damansara Northern terminus.

Cross-platform interchange with  KG04  Kajang Line

Kwasa Damansara station, along with the adjoining Sungai Buloh and Kampung Selamat stations are on the MRT Kajang Line. However, once operations commence on the Putrajaya Line, these three stations will be annexed by the Putrajaya Line, thus making Kwasa Damansara the interchange station between the two MRT lines

 PY02  RRI - - - - - RRI Shelved station
 PY03  Kampung Selamat PY Line Kampung Selamat Station 1.jpg Side Elevated N/A T104 Kampung Baru Sungai Buloh
 PY04   KA08  Sungai Buloh Sungai Buloh MRT Station 4.jpg Island Elevated T100, T101, T102, T103, T105 Sungai Buloh Interchange station, without paid area integration, to  KA08  Port Klang Line and  ETS  KTM ETS.
Phase 1 (under construction, to be ready by March 2022)
 PY05  Damansara Damai PY Line Damansara Damai Station 2.jpg Island Elevated N/A Damansara Damai
 PY06  Sri Damansara Barat PY Line Sri Damansara Barat Station 2.jpg Island Elevated Sri Damansara West
 PY07  Sri Damansara Sentral Sri Damansara Sentral MRT Station 1.jpg Side Elevated Sri Damansara East
 PY08  Sri Damansara Timur Sri Damansara Timur MRT Station 1.jpg Island Elevated Kepong Sentral Connecting station to  KA07  Port Klang Line and  ETS  KTM ETS.
 PY09  Metro Prima Metro Prima MRT station (200121).jpg Island Elevated N/A Metro Prima
 PY10  Kepong Baru Jalan Kepong 3.jpg Island Elevated N/A Kepong Baru
 PY11  Jinjang Jinjang MRT station (200121).jpg Island Elevated Jinjang
 PY12  Sri Delima Sri Delima MRT station (200121).jpg Island Elevated N/A Seri Delima
 PY13   KC03  Kampung Batu Kampung Batu MRT station under construction.jpg Island Elevated N/A Kampung Batu Connecting station to  KC03  Seremban Line.

Terminus station for Phase 1.

Phase 2 (under construction, to be ready by January 2023)
 PY14  Kentonmen Kentonmen MRT station (200117).jpg Side Elevated Kentonmen
 PY15  Jalan Ipoh Jalan Ipoh MRT Station.jpg Island Half-sunken N/A Jalan Ipoh
 PY16  Sentul Barat Sentul Barat MRT station 2021.jpg Island Underground N/A Sentul West Theme: Preserving the Rustic
 PY17  AG3  SP3  MR11  Titiwangsa Titiwangsa MRT Station construction site (211030) 07.jpg Island Underground N/A N/A Titiwangsa Interchange station with  AG3  SP3  MR11  Ampang Line, Sri Petaling Line and KL Monorail.

Proposed interchange with  CC08  MRT Circle Line.

Theme: Tidal Rhythm

 PY18  Hospital Kuala Lumpur Island Underground N/A N/A Hospital Kuala Lumpur Theme: Promoting Well-Being
 PY19  Raja Uda Island Underground N/A N/A Kampung Baru North Theme: Resonating Heritage
 PY20  Ampang Park Ampang Park MRT Station construction site 2 (211031).jpg Stacked Underground N/A N/A Ampang Park Connecting station to  KJ9  Kelana Jaya Line Theme: Vibrancy
 PY21  Persiaran KLCC Kuala Lumpur City Centrer during MCO in April 2020 02.jpg Stacked Underground N/A N/A KLCC East Theme: Pulse of Life
 PY22  Conlay Island Underground N/A N/A Conlay Theme: Discovering Culture
 PY23  KG20  Tun Razak Exchange (TRX) SBK Line TRX Platform 5.jpg Stacked Island Underground N/A T407 Tun Razak Exchange Cross-platform interchange with  KG20  Kajang Line Theme: Islamic Corporate
 PY24  AG11  SP11  Chan Sow Lin Chan Sow Lin MRT Station construction site (211106).jpg Island Underground N/A Chan Sow Lin Interchange station with  AG11  SP11  Ampang Line and Sri Petaling Line Theme: Moulding Forms
 PY25  Bandar Malaysia Utara Island Underground N/A Bandar Malaysia North Construction works are being carried out as of April 2021[51] Theme: Inspired By Nature


(Provisional station)

 PY26  Bandar Malaysia Selatan Island Underground N/A Bandar Malaysia South Construction works are being carried out as of April 2021.[51] Proposed interchange with Seremban Line and KLIA Transit

Theme: Streamlined Flow


(Provisional station)

 PY27  Kuchai Kuchai Station MRT track - Mapillary (9XW5XWJ6lqIkLzHfzMllBJ).jpg Island Elevated Kuchai Lama Proposed interchange with  CC26  MRT Circle Line
 PY28  Taman Naga Emas Island Elevated Taman Naga Emas
 PY29  SP16  Sungai Besi PY Line Sungai Besi Station 1.jpg Side Elevated Sungai Besi Interchange station with  SP16  Sri Petaling Line
 PY30  Taman Teknologi - - - - - Technology Park (Provisional station)
 PY31  Serdang Raya Utara Island Elevated Serdang Raya North
 PY32  Serdang Raya Selatan Island Elevated Serdang Raya South
 PY33  Serdang Jaya Island Elevated N/A Seri Kembangan
 PY34  UPM Island Elevated UPM
 PY35  Taman Universiti - - - - - Taman Universiti (Provisional station)
 PY36  Taman Equine Island Elevated Equine Park
 PY37  Putra Permai Island Elevated N/A Taman Putra Permai
 PY38  16 Sierra Island Elevated N/A 16 Sierra
 PY39  Cyberjaya Utara Island Elevated Cyberjaya North
 PY40  Cyberjaya City Centre Island Elevated N/A Cyberjaya City Centre
 PY41  Putrajaya Sentral Putrajaya Sentral MRT Station (211127) 03.jpg Island Elevated Putrajaya Sentral Connecting station to  KT3 KLIA Transit and proposed 14 Putrajaya Monorail.

Rolling stock[]

The rolling stock will be provided by HAP Consortium which consists of Hyundai Rotem, Apex Communications and POSCO Engineering. The trains are assumed to be driverless with a capacity of 1,200 passengers in a 4-car trainsets formation.[52]

Car length (over coupler): 18.6 m to 20.1 m

Number of passenger doors per car side / door width: 4 / 1400 mm

Traction power supply: 750 VDC, 3rd rail

Exact rolling stock details have not yet been released.

The 4-car trainsets will be maintained at 2 purpose built facilities, Sungai Buloh and Serdang depots, located nearby Kwasa Damansara and the proposed Taman Universiti stations respectively.[53]

References[]

  1. ^ "PUTRAJAYA LINE STATIONS". Archived from the original on 15 January 2021. Retrieved 1 January 2021.
  2. ^ "Second phase of Putrajaya MRT on track for 2023 opening". Free Malaysia Today | FMT. 4 October 2021.
  3. ^ "Twitter @MRTMalaysia". Twitter.com. Retrieved 12 July 2021.
  4. ^ a b "Putrajaya Line MRT Phase 1 Expected To Open In November 2021". 8 July 2021.
  5. ^ "Original plan was for new MRT2 to start from Sg Buloh and not Selayang". The Star Online. Archived from the original on 5 May 2015. Retrieved 27 April 2015.
  6. ^ "Draft Urban Rail Development Plan" (PDF). Draft Greater KL/ Klang Valley Land Public Transport Master Plan. SPAD. Retrieved 22 February 2012.
  7. ^ "Gamuda, MMC likely to get RM24.9bil KVMRT 2 tunnelling job". The Star. 15 May 2013. Archived from the original on 15 December 2013. Retrieved 2 September 2013.
  8. ^ "KVMRT line 2". KVMRT. 19 May 2013. Archived from the original on 20 December 2013. Retrieved 2 September 2013.
  9. ^ Ch'ng, Brenda (3 December 2014). "Building of new MRT second line to begin next November". The Star. Star. Star Publication. Archived from the original on 2 December 2020. Retrieved 3 December 2014.
  10. ^ "New alignment for Sg Buloh-Putrajaya MRT line proposed". The Star Online. Archived from the original on 5 April 2015. Retrieved 3 April 2015.
  11. ^ "MRT Corp prepares tender for Line 2, project display in Q2". thestar.com.my. Archived from the original on 1 August 2015. Retrieved 16 May 2015.
  12. ^ "MRT line 2 from Sg Buloh to Putrajaya gets green light". The Rakyat Post. Archived from the original on 4 March 2016. Retrieved 22 September 2014.
  13. ^ "Budget 2015: Boon for construction". The Star Online. Archived from the original on 12 October 2014. Retrieved 11 October 2014.
  14. ^ "New alignment for Sg Buloh-Putrajaya MRT line proposed". The Star Online. Archived from the original on 5 April 2015. Retrieved 3 April 2015.
  15. ^ "Details of MRT2 project on public display tomorrow". The Star Online. Archived from the original on 15 May 2015. Retrieved 14 May 2015.
  16. ^ "MRT Corp to submit Line 3 study to govt by year-end – Business News | The Star Online". www.thestar.com.my. Archived from the original on 9 May 2017. Retrieved 17 August 2016.
  17. ^ "PM launches RM32b second MRT line to turn Klang Valley into world class city". 15 September 2016. Retrieved 1 June 2017.
  18. ^ "MMC Gamuda Media Statement" (PDF). MRT SUNGAI BULOH – SERDANG – PUTRAJAYA LINE PROGRESSING AS SCHEDULED. 27 February 2017. Archived (PDF) from the original on 6 June 2017. Retrieved 1 June 2017.
  19. ^ "Mini buses, cycle facilities proposed to boost MRT usage - Metro News | The Star Online". www.thestar.com.my. Archived from the original on 5 March 2018. Retrieved 4 March 2018.
  20. ^ beritanasionalrtm rasmi (4 September 2017), MRT SSP - 4 MESIN TBM BARU DAN 8 SEDIA ADA AKAN MULA PENGGALIAN 2018 [5 SEPT 2017], retrieved 22 September 2017
  21. ^ "MRT Corp: Tunnelling work for SSP line to start next year". www.thesundaily.my. Archived from the original on 4 March 2018. Retrieved 4 March 2018.
  22. ^ "Sentul police quarters make way for MRT SSP line, occupants to get new units". NST Online. 26 September 2017. Archived from the original on 4 March 2018. Retrieved 4 March 2018.
  23. ^ "MRT2 tunnelling works to be improved with new TBM machines". www.thesundaily.my. Archived from the original on 4 March 2018. Retrieved 4 March 2018.
  24. ^ "Blast at MRT construction site caused by World War 2 bomb". NST Online. 11 October 2017. Archived from the original on 4 March 2018. Retrieved 4 March 2018.
  25. ^ "MRT Sungai Buloh-Serdang-Putrajaya (SSP) Line's technology wins award". NST Online. 13 October 2017. Archived from the original on 4 March 2018. Retrieved 4 March 2018.
  26. ^ MYMRTUNDERGROUND (28 November 2017), KVMRT LINE 2 SSP PROGRESS VIDEO NO.1 (AUG 2016 to NOV 2017), archived from the original on 8 May 2020, retrieved 4 March 2018
  27. ^ MRTMalaysia (18 December 2017), MRT SSP Line Project Progress Video (2016-2017), archived from the original on 28 February 2020, retrieved 4 March 2018
  28. ^ "MRT SSP Line work on track". www.thesundaily.my. Archived from the original on 5 March 2018. Retrieved 4 March 2018.
  29. ^ "MRT Corp saves 15% cost from refurbished TBMs". themalaysianreserve.com. Archived from the original on 2 March 2018. Retrieved 4 March 2018.
  30. ^ "Worker killed as launching gantry collapses at MRT construction site [NSTTV]". NST Online. 4 March 2018. Archived from the original on 4 March 2018. Retrieved 4 March 2018.
  31. ^ "MRT line 2 at 24% completion, ahead of schedule (Updated)". www.thesundaily.my. Archived from the original on 26 April 2018. Retrieved 25 April 2018.
  32. ^ "MRT Sg Buloh line 30% done - Business News | The Star Online". www.thestar.com.my. Archived from the original on 12 July 2018. Retrieved 12 July 2018.
  33. ^ "23% saved on MRT2 above-ground works, underground part to be retendered says Guan Eng - Nation | The Star Online". www.thestar.com.my. Archived from the original on 6 November 2018. Retrieved 6 November 2018.
  34. ^ a b "Termination of MMC-Gamuda MRT2 contract a Cabinet decision, says Guan Eng - Nation | The Star Online". www.thestar.com.my. Retrieved 6 November 2018.
  35. ^ "Gamuda, MMC shares fall - Business News | The Star Online". www.thestar.com.my. Archived from the original on 6 November 2018. Retrieved 6 November 2018.
  36. ^ "PM: We may reconsider contract - Nation | The Star Online". www.thestar.com.my. Archived from the original on 6 November 2018. Retrieved 6 November 2018.
  37. ^ "Azmin confirms setting up of Cabinet committee to review MRT2 contract - Nation | The Star Online". www.thestar.com.my. Archived from the original on 6 November 2018. Retrieved 6 November 2018.
  38. ^ "MoF: MMC-Gamuda to continue underground MRT2, costs cut to RM13.11b". The Edge Markets. 26 October 2018. Archived from the original on 29 October 2018. Retrieved 29 October 2018.
  39. ^ "Cabinet accepts MMC-Gamuda offer - Business News | The Star Online". www.thestar.com.my. Archived from the original on 6 November 2018. Retrieved 6 November 2018.
  40. ^ MRTMalaysia (9 December 2018), MRT SSP Line Project Progress Video (2017-2018), archived from the original on 10 April 2020, retrieved 21 March 2019
  41. ^ Nair, Vijenthi; Sakdon, Zawin. "First tunnel on second MRT line completed - Metro News | The Star Online". www.thestar.com.my. Retrieved 21 March 2019.
  42. ^ March 2019, Published 2 weeks ago on 06. "Three MRT stations to close for two days | Malay Mail". www.malaymail.com. Archived from the original on 21 March 2019. Retrieved 21 March 2019.
  43. ^ "Najmuddin Abdullah on Instagram: ""My favourite tunnel boring machine (TBM) because its number is 777"