Sucat–Paco–Araneta–Balintawak Transmission Line

From Wikipedia, the free encyclopedia
Sucat–Paco–Araneta–Balintawak Transmission Line
A segment of the transmission line along Tomas Claudio Street/PNR in Pandacan, Manila, with the lattice tower 154 at the foreground.
A segment of the transmission line along Tomas Claudio Street/PNR in Pandacan, Manila, with the lattice tower 154 at the foreground.
Location
CountryPhilippines
ProvinceMetro Manila
Coordinates14°26′40″N 121°3′9″E / 14.44444°N 121.05250°E / 14.44444; 121.05250 (Sucat Substation)
14°34′50″N 120°59′54″E / 14.58056°N 120.99833°E / 14.58056; 120.99833 (Paco Substation)
14°37′6″N 121°0′56″E / 14.61833°N 121.01556°E / 14.61833; 121.01556 (Araneta Substation)
14°39′38″N 121°0′44″E / 14.66056°N 121.01222°E / 14.66056; 121.01222 (Balintawak Substation)
FromSucat Substation
ToBalintawak Substation
Ownership information
OwnerNational Power Corporation (2000–March 1, 2003)
National Transmission Corporation (March 1, 2003–present)
OperatorNational Power Corporation (2000–March 1, 2003)
National Transmission Corporation (March 1, 2003–January 15, 2009)
National Grid Corporation of the Philippines (January 15, 2009–present)[a]
Construction information
Construction started1996; 26 years ago (1996)
Commissioned2000; 22 years ago (2000)
Technical information
TypeOverhead transmission line
Type of currentHVAC
Total length34 km (21 mi)
No. of transmission towers241 (214 steel poles, 26 lattice towers, and 1 portal tower)
AC voltage230 kV
No. of poles214
No. of circuits1

The Sucat–Paco–Araneta–Balintawak Transmission Line (abbreviated as SA,[b] 8LI1QUE-DIM,[c] 8LI1DIM-MNA,[d] 8LI1MNA-MUN,[e]) also known as Muntinlupa–Manila–Doña Imelda–Quezon Transmission Line, is a 230,000 volt, single-circuit, three-part transmission line in Metro Manila, Philippines that connects Sucat and Balintawak substations of National Grid Corporation of the Philippines (NGCP), with line segment termination at NGCP Araneta substation in Quezon City and Manila Electric Company (Meralco) Paco substation in Paco, Manila.

History[]

Rerouting of the transmission line segment along Quirino Avenue in Paco, using new steel pole 144, as a result of the construction of Skyway Stage 3.

The Sucat–Paco–Araneta–Balintawak Transmission Line began construction in 1996[1] and went into service in 2000. It is operated by the privately-owned National Grid Corporation of the Philippines (NGCP) since January 15, 2009, and previously by government-owned companies National Transmission Corporation (TransCo) and National Power Corporation (NAPOCOR). It was owned previously by NAPOCOR from 2000 to March 1, 2003 and is owned currently by TransCo since March 1, 2003.

With the construction of the Skyway Stage 3, several steel poles are being replaced by newer ones specifically those along the Araneta segment and also added new poles on certain portions of the line.[citation needed]

Route description[]

The Sucat–Paco–Araneta–Balintawak Transmission Line passes through the cities of Muntinlupa, Taguig, Makati, Manila, and Quezon City. The Sucat–Paco and Paco–Araneta segments are under NGCP's South Luzon Operations and Maintenance (SLOM) District 1 (South Western Tagalog) while the Araneta–Balintawak segment is under North Luzon Operations and Maintenance (NLOM) District 7 (National Capital Region).[2]

Sucat–Paco[]

Steel pole 49 anchoring the line to a portal tower, located along Upper McKinley Road, Bonifacio Global City, Taguig.

The transmission line starts at Sucat Substation where it parallels Manuel L. Quezon Avenue and Laguna Lake Highway before it turns left. It then passes to Diego Silang Village and parallels with Carlos P. Garcia Avenue. It goes to the left again, passing through Manila American Cemetery and Bonifacio Heights before paralleling to South Luzon Expressway (SLEx) from Maricaban Creek to Magallanes Interchange and Osmeña Highway from Magallanes Interchange to Quirino Avenue. At Magallanes Interchange, it crosses to Epifanio delos Santos Avenue (EDSA). It continues on a straight route and after crossing Gil Puyat Avenue are 7 new steel poles that were used for the relocation of the line due to the construction of Skyway Stage 3. It crosses to San Andres Bukid and Paco. The cut-in connection to Meralco Paco substation is located in this district, where the line's Sucat–Paco section ends.

Poles 118 (foreground) and 119 (behind it) of the transmission line, with anchor designs, beside PNR and SLEx. Also seen is pole 120, having replaced an older structure to give way to the Skyway Stage 3 project.

Paco–Araneta[]

The line parallels to Tomas Claudio Street (or Paco–Santa Mesa Road), PNR Metro Commuter railroad and Magsaysay Boulevard, turns left to Gregorio Araneta Avenue and run parallel with the said avenue and Skyway Stage 3, and the line's Paco–Araneta section ends at Araneta Substation.

Araneta–Balintawak[]

The transmission line along EDSA–Roosevelt area

The line continues paralleling Araneta Avenue and Skyway Stage 3 until it passes to Valentin Ventura Street, Tuktukan Street, and Kaingin Road before it crosses to EDSA. It turns left and after a few meters is the transmission line's terminus which is Balintawak Substation.

Technical description[]

The transmission line consists of 214 steel poles (54 on the Balintawak–Araneta segment (1–54) and 160 on the Araneta–Paco and Paco–Sucat segments (1–8, 30-149, 150A, 150B, and 155–185)), 26 lattice towers (9-29, 150, and 151–154), and 1 portal tower located between steel poles 49 and 50 ((8LI1MNA-MUN)97) totaling to 241 transmission structures. Steel poles have flag tower design (suspension and anchor variants), while lattice towers have incomplete tower design. Portal towers are used on portions of the line where it intersects with another power line. It has a length of 34 kilometers (21 mi) and is a single-circuit, double-bundle power line.

From 2000 until the completion of the line's cut-in connection to Manila Electric Company (Meralco) Paco Substation, it was a two-part power line. Due to the construction of the line's cut-in connection to Meralco Paco Substation, two new steel poles were added between poles 143 and 144 of the Sucat–Araneta segment of the line. This cut-in connection to the said substation also made the transmission line from being a two-part to three-part power line.

In 2018, a portal tower located between steel poles 53 and 54 ((8LI1MNA-MUN)92) was removed and retired to give way for the widening of Lawton Avenue in Taguig.

Health controversy[]

The SLEx (Makati) – Bonifacio Heights (Taguig) segment of Sucat–Paco–Araneta–Balintawak Transmission Line was criticized by the residents living along the Tamarind Road in Dasmariñas Village, Makati, who claimed the transmission line pose health risks. The said segment is located within 10 meters of Tamarind Road in the said village. The residents, led by Atty. Eduardo F. Hernandez, blamed the electromagnetic fields (EMF) emanated by the 230-kV power lines for such health issues as cancer, leukemia, and miscarriage. They also took note of no consultation with regards to the construction of the transmission line.[1]

A case was filed in Makati Regional and Metropolitan Trial Court (Makati RTC) in 2000, but was raised to the Supreme Court after failed negotiations.[3] Responding to the petition filed by the residents, the Supreme Court ruled in 2006 that the safety issue of the lines was "evidentiary in nature," although they took note of the potential health risks due to EMF radiation exposure with regards to the scientific studies. The Court also added that long-term human safety should be of paramount importance as opposed to the presumption of economic benefits.[4] Citing the said ruling, the Makati RTC in October 2008 obliged the National Transmission Corporation (TransCo) to "de-energize" the Sucat–Paco–Araneta–Balintawak Transmission Line.[5]

TransCo vice president for operations Carlito Claudio warned in November 2008 that complete retirement of the transmission line could trigger "hours-long rotating blackouts, just like during the power crisis in the 1990s," that might adversely impact the country's leading economic hubs of Makati and Ortigas, and added the unfeasibility of building an alternate underground cable line that would cost ₱1 billion. Former TransCo president Alan Ortiz noted the transmission line as a crucial line, and said claims of electromagnetic radiation associated with high-voltage transmission lines like this "have yet to be 100-percent scientifically established."[6] TransCo submitted a motion to the Supreme Court asking that they be granted until January 31, 2009 to carry out activities and coordination works in alleviating the impact of the impending shutdown, but was refused and instead supported the Makati RTC's decision in shutting the transmission line down.[3]

In its February 5, 2013 order, the Makati RTC approved the request of the petitioners, referring the case back to another branch following the failure of the judicial dispute resolution.[7] The case is still pending at its pre-trial stage.[8]

Gallery[]

Notes[]

  1. ^ As stated on High Voltage signs placed on new steel poles that were used due to the construction of Metro Manila Skyway Stage 3, including 2 new poles located along Tomas Claudio, Pandacan, Manila.
  2. ^ Abbreviation used on the line's Sucat–Araneta segment.
  3. ^ NGCP abbreviation of the line's Balintawak–Araneta segment.
  4. ^ NGCP abbreviation of the line's Araneta–Paco segment.
  5. ^ NGCP abbreviation of the line's Paco–Sucat segment.

References[]

  1. ^ a b "'Silent killer' at Tamarind Road". PhilStar.com. January 27, 2015. Retrieved September 21, 2019.
  2. ^ "Operations - National Grid Corporation of the Philippines: Business Scope". ngcp.ph. Retrieved April 12, 2021.
  3. ^ a b "3-hour brownouts loom over Metro Manila, Bulacan". GMA News. November 27, 2008. Retrieved August 25, 2020.
  4. ^ "G.R. No. 145328". Lawphil.net. Retrieved September 21, 2019.
  5. ^ "Removal of power line to cut RP's competitiveness". GMA News. November 28, 2008. Retrieved August 25, 2020.
  6. ^ Gatdula, Donnabelle L. (November 28, 2008). "Transco warns of blackouts". Philstar.com. Retrieved April 23, 2020.
  7. ^ "MERALCO submitted its Motion for Leave to File and to Admit Attached Reply on". Course Hero. Retrieved September 22, 2020.
  8. ^ "Preliminary Information Statement for Annual Stockholders' Meeting on May 26, 2020" (PDF). PDS Group. Retrieved January 11, 2021.

External links[]

Retrieved from ""