Central Subway

From Wikipedia, the free encyclopedia

Central Subway
The entrance to a two-track railway tunnel
The under-construction Central Subway viewed from the south portal in October 2020
Overview
Other name(s)Third Street Light Rail Project Phase 2
LocationSan Francisco, California
Coordinates37°46′48″N 122°23′55″W / 37.779921°N 122.398540°W / 37.779921; -122.398540Coordinates: 37°46′48″N 122°23′55″W / 37.779921°N 122.398540°W / 37.779921; -122.398540 (southern portal)
StatusUnder construction
SystemMuni Metro
CrossesMarket Street Subway
Start4th Street portal
EndChinatown
No. of stations3 (plus 1 surface as part of extension project)
Operation
Work begun2012
ConstructedTutor Perini[2]
OpensSpring 2022[1]
OwnerSan Francisco Municipal Transportation Agency
OperatorSan Francisco Municipal Railway
CharacterUnderground subway tunnel for predominantly light rail line
Technical
Line length1.7 mi (2.74 km)
No. of tracks2
Track gauge4 ft 8+12 in (1,435 mm) standard gauge
ElectrifiedOverhead lines, 600 V DC
Route map
San Francisco Municipal Railway
Legend
Provision for future extension to
North Beach and the Presidio
Chinatown
BSicon CCAR.svgCalifornia Street
Union Square/​Market Street
Powell
Bay Area Rapid Transit F Market & Wharves M Ocean View N Judah S Shuttle (T Third Street)
 
Yerba Buena/​Moscone
4th and Brannan
T Third Street original routing
E Embarcadero N Judah
4th & King Caltrain

The Central Subway is an extension of the Muni Metro light rail system under construction in San Francisco, California, from the Caltrain commuter rail depot at 4th and King streets to Chinatown, with stops in South of Market (SoMa) and Union Square.

The subway is the second phase of the San Francisco Municipal Transportation Agency's Third Street Light Rail Project. The first phase opened to the public as the T Third line in 2007. Ground was broken for the Central Subway on February 9, 2010.[3] Tunnel boring for the Central Subway was completed at Columbus and Powell Street in the North Beach neighborhood of San Francisco on June 11, 2014.[4] Originally set to open in late 2018, the Central Subway is (as of November 2020) projected to open to the public in spring 2022.[5] With the addition of the Central Subway, the T Third line is projected to become the most heavily ridden line in the Muni Metro system by 2030.[6]

The extension will serve major employment and population centers in San Francisco that are underserved by rapid transit.[7] SoMa is home to the headquarters of many of San Francisco’s major software and technology companies, and substantial residential growth is projected there.[8] Union Square, located in the city's downtown, is a primary commercial and economic district.[9] Chinatown is the most densely populated neighborhood in the city.[10] The Central Subway will connect these areas to communities in eastern San Francisco, including Mission Bay, Dogpatch, Bayview–Hunters Point and Visitacion Valley. The project was initiated after the Embarcadero Freeway was torn down following the 1989 Loma Prieta earthquake, when activist Rose Pak "almost single-handedly persuaded the city to build" the Central Subway to compensate Chinatown for the loss of the fast cross-town connection.[11]

The budget to complete the Central Subway is $1.578 billion. The project is funded primarily through the Federal Transit Administration’s New Starts program. In October 2012, the FTA approved a Full Funding Grant Agreement, the federal commitment of funding through New Starts, for the Central Subway for a total amount of $942.2 million.[12] The Central Subway is also funded by the State of California, the Metropolitan Transportation Commission, the San Francisco County Transportation Authority and the City and County of San Francisco.[13]

Alignment[]

In February 2008, the San Francisco Municipal Transportation Agency board of directors voted to select the alignment for the subway.[14][15] In the approved alignment, trains travel north along 4th Street and Stockton Street, stopping at one above-ground station and three subway stations on their 1.7-mile route.

Currently northbound T Third trains turn right from 4th Street onto King Street and travel along the Embarcadero to the Market Street Subway. When the Central Subway is complete, trains will instead cross King Street and continue north on 4th Street.

The first stop will be at an above-ground station at 4th and Brannan streets. Heading north, trains will enter the subway through a portal on 4th Street between Bryant and Harrison streets, under Interstate 80. The route will then continue under 4th Street through South of Market, stopping at an underground station, the Yerba Buena/Moscone Station, at 4th and Clementina streets, near the Moscone Center. At Market Street, the subway will dip below the Market Street Subway. Another underground station serving Market Street and Union Square will be located underneath Stockton Street. This combined Union Square/Market Street Station will have entrances at the Market, Ellis and Stockton intersection and within Union Square Plaza at Stockton and Geary streets. A pedestrian passage will connect the Union Square/Market Street Station to the Muni Metro and BART Powell Street Station. The subway will then continue under Stockton Street (becoming the second tunnel under Stockton Street) to Chinatown Station, a station to be located in Chinatown at Stockton and Washington streets.[16][17] Two of the three underground stations are being constructed using cut-and-cover methods while Chinatown Station is being constructed with the sequential excavation method.[18][19]

Route for second phase (under construction as the Central Subway), planned route for third phase (extension to Fisherman's Wharf), and proposed routes for fourth phase (extension to the Presidio of San Francisco)

The subway tunnels, one for northbound trains and one for southbound trains, will continue north past Chinatown Station along Stockton Street and terminate near Columbus Avenue. In the future, the northern end of the T Third line may be extended to terminate in North Beach or to Fisherman's Wharf and the Aquatic Park to connect with F Market & Wharves. Fourteen alternative routes were proposed in a 2014 study to extend the line, and daily ridership was projected to increase by 40,000 if the extension was completed.[20] San Francisco Chronicle architecture critic John King wrote there was "a compelling power to the idea of an extension that, if nothing else, would make the Central Subway seem less like a boondoggle and more of a factor in the shaping of tomorrow’s city. The empty lot of the Pagoda was a starting point for dreams. Let’s see if it can become a starting point of something real as well."[21]

Cost[]

In 2000, the estimated cost of the Central Subway project was $530 million.[22] By 2001, the cost had risen to $647 million and completion was projected for 2009.[23] When construction began in 2012, the cost had reached $1.6 billion.[24] When the main contract for Central Subway construction was awarded in May 2013 to the lowest bidder, Tutor Perini,[25] the $840 million contract was up to $120 million over the budgeted amount, which took up nearly two-thirds of the entire project's contingency.[26]

Due to the capital cost ($1.578 billion for the 1.7 mile light rail line), the Central Subway project has come under criticism from transit activists for what they consider to be poor cost-effectiveness.[27] In particular, they note that Muni's own estimates show that the project would increase Muni ridership by less than 1% and yet by 2030 would add $15.2 million a year to Muni's annual operating deficit.[28]

Chinatown Station construction site, August 2013

This position is countered by the fact that, unlike new rail construction projections in low-density areas in America, the Central Subway would augment access to the densest portions of Chinatown and the northern Financial District. Current transit access to these areas is provided entirely on the surface through small blocks that feature intense pedestrian activity and narrow streets with multi-modal street congestion. Other, lower-cost rapid transit options were explored, such as bus rapid transit (BRT), but were rejected in part because these conditions do not support the basic features of efficient BRT operations.

Compounding these conditions is the fact that many Chinatown residents are transit-dependent and do not own cars, helping rationalize funding for a subway. The high-ridership Muni bus lines serving Chinatown (e.g., the 1 California and the 30 Stockton) are typically extremely overcrowded, making service for customers more excruciating as excessive boarding activity slows travel speeds or exacerbates overcrowding until no more riders can be accepted and buses are forced to pass customers at successive stops, effectively denying them service.[24]

A group of politicians celebrate the completion of funding for the Central Subway Project
Rep. Nancy Pelosi, Mayor Ed Lee, and other dignitaries next to a poster-sized reproduction of the FTA Grant near Union Square (May 11, 2013)

In October 2012, the Federal Transit Administration (FTA) announced it would provide $942.2 million for the project under its New Starts program[29] after indicating it would approve the grant in January.[30] This award included the recognition that better, more comfortable service for an already intensively-used transit corridor, particularly for low-income residents as in Chinatown, justifies the investment even if it does not attract a high percentage of "new" riders the way a new rapid transit investment might somewhere that is not already served by extremely slow, uncomfortable high-ridership local service.[12]

Construction[]

A study released in 2000 called for the Central Subway as part of a larger plan to alleviate projected traffic gridlock which also included a light rail line along Geary.[31] Voters approved the Central Subway in 2003, and the alignment was selected in 2008.[15] Physical work began on the Central Subway in June 2012. The first phases of work included preparation of the tunnel boring machine launch site and headwalls for the Yerba Buena/Moscone Station.[32] At the time, the FTA grant had not been secured, and opponents were threatening lawsuits over potential disruption to traffic and businesses.[33]

Tunnel boring[]

TBM "Mom Chung" prepares for launch, May 2013

The two tunnel boring machines (TBMs) are named "Big Alma" and "Mom Chung" (for "Big" Alma Spreckels and Dr. Margaret "Mom" Chung, respectively).[34] Preparations for tunnel boring began on June 12, 2012, with the start of excavation for the TBM launch box on Fourth Street between Bryant and Harrison.[32] "Mom Chung" was delivered to San Francisco in April and May 2013,[35][36] and in late July 2013, "Mom Chung" began digging the tunnel for southbound T Third trains.[37] "Big Alma" began digging north in November 2013 at a slightly faster rate, 54 ft/d (0.19 m/ks), compared to the 44 ft/d (0.16 m/ks) average of "Mom Chung".[38]

The initial plan was to remove the two TBMs near Washington Square in North Beach in 2014 once boring was complete.[39] On July 31, 2012, a lawsuit was filed in Superior Court by Marc Bruno and Save North Beach, a 501(c)(4) organization of North Beach merchants and residents who believed that the removal of the equipment on Columbus Avenue would cause permanent harm to the neighborhood near Washington Square.[40] The petitioners pointed out in their suit that they are in favor of the City's "Transit First" policy and that they would favor the removal of the equipment if a subway stop was planned, approved and financed for their neighborhood. Muni General Manager Ed Reiskin announced a plan in December 2012 to extend the tunnel to Columbus and Powell, using the site of the long-closed Pagoda Palace theater to extract the TBMs, with a potential option to purchase the Pagoda as the site of a future North Beach station.[41] In 2013, MTA reached a lease agreement with the owners of the Pagoda to tear down the old building and use its site for TBM removal. This will reduce impact of construction on the public space.[42]

On June 11, 2014, "Big Alma" broke through to the North Beach extraction shaft, joining "Mom Chung", which had arrived on June 2. The arrival of the TBMs marked the completion the boring operation phase.[4] The two TBMs were to be disassembled and removed, and the extraction shaft filled in by the end of 2014.[43] The twin tunnels were fully complete by May 2015, when Mayor Ed Lee toured the project underground. Each completed tunnel is 8,500 feet (2,600 m) long and 20 feet (6.1 m) in diameter, supported by 1,750 concrete rings placed during the boring operation.[44]

Schedule[]

Track extension construction at 4th & King (September 5–8, 2015) as a part of the Central Subway Project

Just before construction began in 2012, the start of revenue service on the Central Subway extension was scheduled for December 2018.[24] When the main contract was awarded to Tutor Perini in May 2013, schedule float (the amount of time set aside for delays) was reduced from 14.8 months to 5.2 months.[26] In 2014, the San Francisco Controller's Office audited the project and predicted it would be completed on schedule in December 2018 and slightly under budget.[45] Tunnel boring completed in June 2014, a month ahead of schedule and under budget.[44]

Over Labor Day weekend 2015, between September 5–8, the track at the intersection of 4th Street and King Street was extended, which temporarily shortened the services of T Third Street between 4th and King Station (referred to as 4th and Berry in the notice) and Sunnydale Station; the K Ingleside route also ended at Embarcadero Station and did not splice with the T Third Street route.[46][47] A similar shutdown was imposed in early November 2015. During the November shutdown, bus service was provided in lieu of the T-Third trains between Embarcadero and Sunnydale; E-Embarcadero service was suspended for two weekends; K-Ingleside again terminated at Embarcadero; and streets were closed in the vicinity of 4th and King.[48]

A Project Management Oversight Committee report released in mid-2017 reported ten months of delays in construction, pushing back the date of service as late as December 10, 2019. The $76 million contingency fund may be used to expedite completion.[62] The delays were attributed to work on the Chinatown station.[63] In December 2017, Tutor Perini (TPC) circulated a report predicting a fifteen-month delay past December 2019 due to circumstances beyond their control, including hard rock and required utility relocations. TPC is liable for penalties of up to $50,000 per day for late completion beyond December 2019.[64]

Also in December 2017, the Central Subway Program Director, John Funghi, announced he will leave the project for Caltrain, where he will head the Peninsula Corridor Electrification Project starting in February 2018.[65] In April 2018, SFMTA announced that excavation was complete for Chinatown station, which will be the last station to be completed for Central Subway in mid-2019. The other underground stations, Yerba Buena/Moscone and Union Square, are scheduled to be completed by the end of 2018 ahead of the scheduled December 2019 start of revenue service.[66]

SFMTA noted that of 37 schedule updates submitted by Tutor Perini between December 2014 and December 2017, 21 were rejected "due to multiple and repetitive issues that vary from incorrect working sequences to unrealistic forecasted completion dates to artificially steering the schedule longest path through certain portions of the project".[55]:8 Contrary to TPC's claims, SFMTA stated that ground conditions were as expected from preliminary surveys, but TPC's "mining productivity has not been as planned" and directed TPC to develop a recovery schedule. In January 2018, for example, TPC modified their construction sequence at Chinatown station and were able to shave 18 days off the schedule, changing the estimated revenue service date to November 22, 2019.[55]:8 By May 2019, the estimated opening had slipped to February 2020.[67] In September 2019, it was announced that the opening was delayed yet again, this time to mid-2021.[68] Another delay to late 2021 was announced in June 2020,[69] followed by a further delay to 2022.[1]

In March 2021, Muni imposed a deadline for major construction to complete by March 31 as part of a settlement with TPC for work order modifications and other claims; in exchange, TPC would receive a $143 million payment.[70] Test trains began operation in the subway in July 2021.[71] Final completion of construction is expected by September 2021.[72] Revenue service is expected to start in Spring 2022.[70]

Other issues[]

Residents and workers near the 4th Street portal and North Beach extraction sites noted an increase in the visible number of rats after construction began.[73][74]

Construction of the Union Square/Market Street station required closing Stockton Street just north of Market, which depressed traffic to retailers in Union Square.[75] During the excavation, workers accidentally breached a water main in July 2014, causing basement-level flooding in shops along Geary between Stockton and Grant.[76] The ensuing cleanup took several days and required a few businesses to keep stores closed.[77] Since Stockton Street has been closed between Geary and Ellis, starting in 2014, construction is suspended in December and the area is transformed into a pedestrian plaza known as "Winter Walk". Some[who?] have called for Winter Walk to be made a permanent year-round fixture, but notable opposition included Rose Pak, who wanted to retain Stockton as a link from Market to Chinatown.[78]

Workers breached a natural gas pipeline in May 2015 while working on the Yerba Buena/Moscone station, forcing the evacuation of the nearby Yerba Buena Center for the Arts.[79]

Art[]

"One Hundred Years: History of the Chinese in America", a mural painted by James Leong originally for the Ping Yuen housing project in Chinatown, was enlarged, printed, and wrapped in 2012 around the Hogan & Vest building at Stockton & Washington, at the future Chinatown station site, prior to that building's demolition.[80] In addition, temporary murals have been painted on the construction barricades erected around the Chinatown and Yerba Buena/Moscone stations.[81] Planning for the temporary murals began in January 2013 and $409,075 was allocated to cover commissions of $25,000 each to up to 10 artists and production costs. The art would be printed on adhesive vinyl and wrapped onto the plywood panels, measuring approximately 8 ft (2.4 m) high by 190 ft (58 m) long at Chinatown, along Stockton, or 160 ft (49 m) long at Yerba Buena/Moscone, along Folsom.[82] Artworks included:

Temporary art was also installed around the Pagoda Palace Theatre from 2014 to 2017, while it was being used to extract the two tunnel boring machines.[95] Permanent installations are planned for each station.[96] A draft of the Central Subway Arts Master Plan was presented to the San Francisco Arts Commission in September 2008.[97] Artworks are divided into "landmark" and "wayfinding" categories. Candidates were announced in July 2010[98] and the winning entrants were announced on August 5, 2010:[99][100][101]

Permanent art at Central Subway stations
Chinatown[102]
  Landmark Wayfinding Other(s)
Title "Yang Ge Dance of Northeast China" "Urban Archaeology" "A Sense of Community"
Artist Tomie Arai Clare Rojas
Notes Two large-scale laser-cut metal panels painted red, based on traditional Chinese paper cutting and featuring traditional folk heroes. One is 16 by 37 feet (4.9 m × 11.3 m), to be installed in the mezzanine landing, and the other is 30 by 35 feet (9.1 m × 10.7 m), to be installed in the ticketing hall. A large mural measuring 100 feet (30 m) and varying in height between 4–9 feet (1.2–2.7 m) featuring images of the life and history of the Chinatown area rendered in architectural glass. A large tile mural based on Chinese textile samples arranged in a Cathedral Quilting pattern. The finished mural will be a semicircle measuring approximately 35 by 14+12 feet (10.7 m × 4.4 m).[103][104]
Union Square/Market Street[105]
  Landmark Wayfinding Other(s)
Title "Lucy in the Sky" "Untitled"
(working titles: "Illuminated Scroll" and "Reflected Loop")
"Convergence: Commute Patterns"
Artist Erwin Redl Jim Campbell and Werner Klotz
Notes Hundreds of 10 by 10 inches (250 mm × 250 mm) LED-array-illuminated translucent panels, programmed to change colors, display patterns, and animations. Project installed by close of fiscal year 2021 (June 30, 2021).[106] A stainless steel ribbon measuring approximately 250 feet (76 m) long and varying in width between 4–8 feet (1.2–2.4 m), winding overhead. Project installed by close of fiscal year 2021 (June 30, 2021).[106] Patterns on the glass deck and elevators superimposed on a topographical map, illustrating commute patterns in the Bay Area.[107][108]
Yerba Buena/Moscone[109]
  Landmark Wayfinding Other(s)
Title "Untitled"
(working title: "Arc Cycle")
(canceled) "Node" "Untitled"
(working title: "Face C/Z")
Artist Catherine Wagner Tom Otterness Roxy Paine Leslie Shows
Notes photographs taken during the late 1970s during the construction of Moscone Center, rendered on etched granite panels approximately 10 by 12.5 feet (3.0 m × 3.8 m). One photograph will be rendered in art glass at the surface level station entry at 14 by 23 feet (4.3 m × 7.0 m).[110][111] Project installed by close of fiscal year 2021 (June 30, 2021).[106] 59 bronze sculptures. Canceled in November 2011 after it was publicized that Otterness had previously filmed himself in 1977 shooting a dog for the piece "Shot Dog Film".[112][113] A 110-foot (34 m) tall sculpture shaped like a branch, tapering from a diameter of 48 inches (1,200 mm) at the base to 14 inch (6.4 mm) at the peak. A photographic image of iron pyrite enlarged to 36 by 15 feet (11.0 m × 4.6 m) and rendered in glass, metal, gravel, and other materials.[114][115][116] Project installed by close of fiscal year 2021 (June 30, 2021).[106]
4th and Brannan[117]
  Landmark Wayfinding Other(s)
Title N/A "Microcosmic"
(working title: "Microscopic")[118]
Artist
Notes A kinetic sculpture approximately 14 by 17 feet (4.3 m × 5.2 m) atop a 40-foot (12 m) high pole, featuring 31 rotating points.[119] Project installed by close of fiscal year 2020 (June 30, 2020).[120]

References[]

  1. ^ Jump up to: a b "Central Subway: Slowed by COVID-19 But Still Making Progress" (Press release). San Francisco Municipal Transportation Agency. November 12, 2020.
  2. ^ Rodriguez, Joe Fitzgerald (July 10, 2017). "Central Subway project faces up to 10-month delay". San Francisco Examiner. Retrieved July 18, 2017.
  3. ^ Rhodes, Michael (February 9, 2010). "City Leaders Gather for Central Subway Groundbreaking Ceremony". Streetsblog SF. Retrieved April 25, 2014.
  4. ^ Jump up to: a b Cabanatuan, Michael (June 24, 2014). "S.F. Central Subway's big dig done". San Francisco Chronicle. Retrieved June 25, 2014.
  5. ^ "SFMTA: COVID-19 impacts delay completion of Central Subway project". San Francisco Examiner. Retrieved November 14, 2020.
  6. ^ "Central Subway will move San Francisco in right direction". San Francisco Examiner. October 14, 2012. Retrieved August 18, 2013.
  7. ^ Quan, Holly (December 6, 2011). "San Francisco Commute Speeds Drop Dramatically". KPIX-TV CBS SF Bay Area. Retrieved August 18, 2013.
  8. ^ "East SoMa Area Plan". San Francisco General Plan. San Francisco Planning Department. Archived from the original on April 15, 2013. Retrieved November 5, 2012.
  9. ^ "Downtown Area Plan". San Francisco General Plan. San Francisco Planning Department. Archived from the original on December 8, 2012. Retrieved November 5, 2012.
  10. ^ "Community Health Status Assessment: City and County of San Francisco" (PDF). San Francisco Department of Public Health. Archived from the original (pdf) on August 8, 2014. Retrieved November 5, 2012.
  11. ^ "Rose Pak flashes red light on Stockton Street pedestrian mall". SFChronicle.com. August 7, 2016. Retrieved July 5, 2020.
  12. ^ Jump up to: a b "U.S. Transportation Secretary LaHood Announces $942.2 Million to Extend San Francisco's Third Street Light Rail System". Federal Transit Administration. Archived from the original on October 26, 2012. Retrieved November 5, 2012.
  13. ^ "Central Subway Project Funding/Budget". San Francisco Municipal Transportation Agency (SFMTA). Retrieved November 5, 2012.
  14. ^ "MTA Board Selects Central Subway Alignment". Transbay Blog. Retrieved February 21, 2008.
  15. ^ Jump up to: a b Nevius, C.W. (April 22, 2013). "The hole in subway opponents' arguments". San Francisco Chronicle. Retrieved December 6, 2017.
  16. ^ Vega, Cecilia M. (February 20, 2008). "S.F. Chinatown subway plan gets agency's nod". San Francisco Chronicle. Retrieved August 18, 2013.
  17. ^ "Central Subway Alignment". San Francisco Municipal Transportation Agency (SFMTA). Retrieved November 5, 2012.
  18. ^ Roberston, Michelle (January 26, 2017). "A subterranean 'cathedral': Stunning new photos of Central Subway construction". San Francisco Chronicle. Retrieved December 12, 2017.
  19. ^ "Central Subway Project, San Francisco". Railway Technology. Retrieved May 1, 2018.
  20. ^ Cabanatuan, Michael (November 26, 2014). "Extending SF's Central Subway would draw riders, study says". San Francisco Chronicle. Retrieved December 7, 2017.
  21. ^ King, John (December 3, 2014). "Central Subway extension to Fisherman's Wharf makes sense". San Francisco Chronicle. Retrieved December 7, 2017.
  22. ^ Cabanatuan, Michael (March 23, 2000). "Transit Panel Readies $3.3 Billion Wish List for Gov. Davis / Hwy. 4, I-680 improvements among projects". San Francisco Chronicle. Retrieved December 6, 2017.
  23. ^ Cabanatuan, Michael (December 17, 2001). "Transit plan a commuter's dream / 'Baby bullet' trains, a new bus terminal, BART to Silicon Valley". San Francisco Chronicle. Retrieved December 6, 2017.
  24. ^ Jump up to: a b c Lee, Stephanie M. (March 14, 2012). "SF Chinatown's Stockton could get more elbow room". San Francisco Chronicle. Retrieved December 6, 2017.
  25. ^ Tutor Perini (April 18, 2013). "Proposal for Contract No. 1300" (PDF). Central Subway Blog. Retrieved December 14, 2017.
  26. ^ Jump up to: a b Cabanatuan, Michael (May 21, 2013). "S.F.'s Central Subway straining budget". San Francisco Chronicle. Retrieved December 6, 2017.
  27. ^ "Central Subway: Visionary Project or Colossal Boondoggle?". Transbay Blog. Retrieved December 16, 2007.
  28. ^ "Third Street Light Rail Project Environmental Impact Statement / Environmental Impact Report". ICF Kaiser Engineers, Inc., et al. Retrieved December 16, 2007.
  29. ^ Cabanatuan, Michael (October 11, 2012). "Giant day for Central Subway". San Francisco Chronicle. Retrieved December 6, 2017.
  30. ^ Lochhead, Carolyn (January 19, 2012). "Central Subway funds get a key OK". San Francisco Chronicle. Retrieved December 6, 2017.
  31. ^ Epstein, Edward (April 19, 2000). "Even $5.6 Billion Plan Means Gridlock in S.F. Future, Experts Say / In next 30 years, city needs to pay more on transit". San Francisco Chronicle. Retrieved December 12, 2017.
  32. ^ Jump up to: a b Cabanatuan, Michael (June 11, 2012). "S.F. Central Subway tunnel construction to begin". San Francisco Chronicle. Retrieved December 6, 2017.
  33. ^ Cabanatuan, Michael (July 19, 2012). "Central Subway work starts amid problems". San francisco Chronicle. Retrieved December 6, 2017.
  34. ^ "Mom Chung and Big Alma: The Central Subway's Tunnel Boring Machines" (PDF) (Press release). San Francisco Municipal Transit Agency. June 16, 2014. Retrieved March 10, 2017.
  35. ^ Wildermuth, John (April 19, 2013). "Central Subway workers prepare for boring machine". San Francisco Chronicle. Retrieved December 6, 2017.
  36. ^ Coté, John; Tucker, Jill (May 9, 2013). "Mayor Lee excited about Central Subway". San Francisco Chronicle. Retrieved December 6, 2017.
  37. ^ "TBM Mom Chung launches, beginning tunnel construction beneath SF". Central Subway Blog. July 26, 2013. Archived from the original on August 18, 2013. Retrieved August 18, 2013.
  38. ^ Cabanatuan, Michael (August 6, 2014). "Machines quietly tunneling in Muni's Central Subway project". San Francisco Chronicle. Retrieved December 6, 2017.
  39. ^ Cabanatuan, Michael (July 19, 2012). "Central Subway work starts amid problems". San Francisco Chronicle. Retrieved August 18, 2013.
  40. ^ Coté, John (August 4, 2012). "North Beach tunnel plan angers residents". San Francisco Chronicle. Retrieved December 6, 2017.
  41. ^ Matier, Phil; Ross, Andy (December 2, 2012). "Muni subway plan to appease North Beach". San Francisco Chronicle. Retrieved March 10, 2017.
  42. ^ Riley, Neal (February 14, 2013). "MTA reaches lease deal with Pagoda Palace". San Francisco Chronicle. Retrieved December 6, 2017.
  43. ^ "Construction Update | July 04 – July 14". Central Subway Blog. July 3, 2014. Retrieved July 7, 2014.
  44. ^ Jump up to: a b Cabanatuan, Michael (May 19, 2015). "S.F. leaders tour completed Central Subway tunnel". SFGate. Retrieved May 25, 2015.
  45. ^ Cabanatuan, Michael (November 19, 2014). "Controller says Central Subway on track — both budget and completion". San Francisco Chronicle. Retrieved December 7, 2017.
  46. ^ Banchero, Rick (September 2, 2015). "Muni, Traffic Impacts Ahead on a Laborious Labor Day Weekend". On Tap (blog). San Francisco Municipal Transportation Agency. Retrieved December 12, 2017.
  47. ^ "Projects, Events to Heavily Impact Traffic and Transit this Labor Day Weekend" (PDF) (Press release). San Francisco Municipal Transportation Agency. September 2, 2015. Archived from the original (PDF) on September 10, 2015. Retrieved December 12, 2017.
  48. ^ Cabanatuan, Michael (November 5, 2015). "Central Subway work to disrupt traffic for 8 days". San Francisco Chronicle. Retrieved December 12, 2017.
  49. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. January 2015. Retrieved December 14, 2017.
  50. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. July 2015. Retrieved December 14, 2017.
  51. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. January 2016. Retrieved December 14, 2017.
  52. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. July 2016. Retrieved December 14, 2017.
  53. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. January 2017. Retrieved December 14, 2017.
  54. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. July 2017. Retrieved December 14, 2017.
  55. ^ Jump up to: a b c Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. January 2018. Retrieved April 7, 2018.
  56. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. July 2018. Retrieved October 17, 2018.
  57. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. January 2019. Retrieved March 20, 2019.
  58. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. July 2019. Retrieved November 4, 2019.
  59. ^ Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. January 2020. Retrieved June 30, 2020.
  60. ^ Jump up to: a b Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. July 2020. Retrieved October 8, 2020.
  61. ^ Jump up to: a b Central Subway Monthly Progress Report (PDF) (Report). San Francisco Municipal Transportation Agency. January 2021. Retrieved June 16, 2021.
  62. ^ Rodriguez, Joe Fitzgerald (July 25, 2017). "Central Subway completion date delayed again". San Francisco Examiner. Retrieved July 26, 2017.
  63. ^ Cabanatuan, Michael (September 13, 2017). "Central Subway could start partial service in time to serve Warriors' arena". SF Gate. Retrieved September 26, 2017.
  64. ^ Matier, Phil; Ross, Andy (December 5, 2017). "SF's Central Subway falling further behind schedule, builder warns". San Francisco Chronicle. Retrieved December 6, 2017.(subscription required)
  65. ^ Phelan, Lori (December 11, 2017). "Central Subway Program Director Accepts New Position at Caltrain" (Press release). SFMTA. Retrieved January 29, 2018.
  66. ^ Cabanatuan, Michael (April 3, 2018). "San Francisco's Central Subway is getting closer to completion". San Francisco Chronicle. Retrieved April 4, 2018.
  67. ^ Hoe, Albert. "Central Subway Monthly Progress Report (May 2019)" (PDF). SFMTA. Municipal Transportation Agency. Retrieved June 27, 2019.
  68. ^ Rodriguez, Joe Fitzgerald (September 11, 2019). "Central Subway to debut in 2021, nearly three years later than planned". San Francisco Examiner.
  69. ^ "Central Subway Update – Projected to be Open for Service by the End of 2021" (Press release). San Francisco Municipal Transportation Agency. June 5, 2020.
  70. ^ Jump up to: a b Graf, Carly (March 3, 2021). "Major construction on Central Subway to end by March 31". San Francisco Examiner. Retrieved June 16, 2021.
  71. ^ Guilfoil, Jackson (July 21, 2021). "After nearly 10 years of construction, trains finally start runs through Central Subway". Bay City News.
  72. ^ Slowey, Kim (March 19, 2021). "Tutor Perini low bidder on Los Angeles LAX airport-Metro transit hub". Construction Drive. Retrieved March 20, 2021.
  73. ^ Ho, Vivian (November 14, 2013). "Rats scatter from Central Subway construction". San Francisco Chronicle. Retrieved December 6, 2017.
  74. ^ Ho, Vivian (April 3, 2014). "North Beach rats may be result of Central Subway work". San Francisco Chronicle. Retrieved December 6, 2017.
  75. ^ Matier, Phil; Ross, Andy (September 29, 2014). "Union Square merchants not digging new subway". San Francisco Chronicle. Retrieved December 7, 2017.
  76. ^ Coté, John (July 12, 2014). "Water main break floods Union Square retailers". San Francisco Chronicle. Retrieved December 7, 2017.
  77. ^ Ho, Vivian (July 15, 2014). "Crews cleaning up flooded Union Square stores". San Francisco Chronicle. Retrieved December 7, 2017.
  78. ^ Cabanatuan, Michael; Sernoffsky, Evan (November 22, 2016). "Stockton Street becomes holiday pedestrian plaza — should closure be permanent?". San Francisco Chronicle. Retrieved December 7, 2017.
  79. ^ Green, Emily; Rubenstein, Steve (May 20, 2015). "Streets reopen, gas leak capped in San Francisco". San Francisco Chronicle. Retrieved December 12, 2017.
  80. ^ "Mural from CHSA Collection Featured at Central Subway Project Site" (Press release). Chinese Historical Society of America. February 24, 2012. Retrieved December 14, 2017.
  81. ^ Whiting, Sam (June 10, 2014). "New Mural snakes along fence of Central Subway". Arts & Not (blog). San Francisco Chronicle. Retrieved December 12, 2017.
  82. ^ Lovvorn, Jennifer (January 16, 2013). "Central Subway: Temporary art on barricade project outline" (PDF). San Francisco Arts Commission. Retrieved August 17, 2021.
  83. ^ Jump up to: a b "Panel Summary -- artist selection panel meeting 1" (PDF). San Francisco Arts Commission. May 9, 2013. Retrieved August 17, 2021.
  84. ^ Jump up to: a b "Chinatown Central Subway Station: Kota Ezawa Mural". flickr. San Francisco Arts Commission. Retrieved August 16, 2021.
  85. ^ Whiting, Sam (April 7, 2014). "Chinatown 'Panorama' mural like an oceangoing travelogue". SF Gate. Retrieved August 16, 2021.
  86. ^ "YBM barricade, Colosky final design" (PDF). San Francisco Arts Commission. December 18, 2013. Retrieved August 17, 2021.
  87. ^ "Randy Colosky Central Subway Construction Barrier". flickr. San Francisco Arts Commission. Retrieved August 16, 2021.
  88. ^ Jump up to: a b "Artist selection panel meeting summary" (PDF). San Francisco Arts Commission. September 16, 2014. Retrieved August 17, 2021.
  89. ^ "Maria Park - Central Subway Construction Barrier". flickr. San Francisco Arts Commission. Retrieved August 16, 2021.
  90. ^ "New Temporary Mural in Chinatown" (Press release). San Francisco Arts Commission. Retrieved August 16, 2021.
  91. ^ "Maria Park installed" (PDF). San Francisco Arts Commission. September 21, 2016. Retrieved August 17, 2021.
  92. ^ "Maria Park's 150-Foot Mural in San Francisco Slows Time". Cornell AAP. February 14, 2017. Retrieved August 16, 2021.
  93. ^ "Visual Arts Committee minutes". San Francisco Arts Commission. October 19, 2016. Retrieved August 17, 2021.
  94. ^ "Jason Jägel - Chinatown Construction Barrier". flickr. San Francisco Arts Commission. Retrieved August 16, 2021.
  95. ^ "Visual Arts Committee minutes". San Francisco Arts Commission. September 18, 2013. Retrieved August 17, 2021.
  96. ^ "Central Subway Public Art Program". San Francisco Arts Commission. Retrieved December 12, 2017.
  97. ^ "Visual Arts Committee minutes". San Francisco Arts Commission. September 17, 2008. Retrieved August 17, 2021.
  98. ^ "Public Art Proposal Display from July 9-16". Central Subway Blog. July 2, 2010. Retrieved December 14, 2017.
  99. ^ "Public Art Program Announces Winners". Central Subway Blog. August 5, 2010. Archived from the original on December 15, 2017. Retrieved December 14, 2017.
  100. ^ "Public Art Program Update". Central Subway Blog. March 22, 2016. Retrieved December 14, 2017.
  101. ^ "Central Subway Public Art Program". San Francisco Arts Commission. Retrieved June 4, 2018.
  102. ^ "Public Art Proposals: CTS". Central Subway Blog. July 14, 2010. Retrieved December 14, 2017.
  103. ^ "Panel Summary: Artist selection panel - meeting 2, Crosscut Cavern Wall artwork at Chinatown Station" (PDF). San Francisco Arts Commission. April 3, 2013. Retrieved August 17, 2021.
  104. ^ Rojas, Clare (April 15, 2015). "Chinatown Subway Mural" (PDF). San Francisco Arts Commission. Retrieved August 17, 2021.
  105. ^ "Public Art Proposals: UMS". Central Subway Blog. July 12, 2010. Retrieved December 14, 2017.
  106. ^ Jump up to: a b c d Public Art Program Annual Report FY2021 (PDF) (Report). San Francisco Arts Commission. 2021. Retrieved August 17, 2021.
  107. ^ Lovvorn, Jennifer (May 11, 2012). "Central Subway Union Square Station: Glass elevator enclosure and deck detailed public art project outline" (PDF). San Francisco Arts Commission. Retrieved August 17, 2021.
  108. ^ "Panel Summary: Artist selection panel -- meeting 2" (PDF). San Francisco Arts Commission. April 3, 2013. Retrieved August 17, 2021.
  109. ^ "Public Art Proposals: MOS". Central Subway Blog. July 13, 2010. Retrieved December 14, 2017.
  110. ^ Wagner, Catherine (October 19, 2011). "Final design drawings, Moscone Station public art, San Francisco" (PDF). City of San Francisco. Retrieved June 4, 2018.
  111. ^ "Wagner as installed" (PDF). San Francisco Arts Commission, Visual Arts Committee. June 16, 2021. Retrieved August 17, 2021.
  112. ^ Sabatini, Joshua (September 16, 2011). "Sculptor who killed dog set to make San Francisco Central Subway art". San Francisco Examiner. Retrieved December 14, 2017.
  113. ^ Sabatini, Joshua (November 17, 2011). "Dog-killer artist loses SF contract, keeps second". San Francisco Examiner. Retrieved December 14, 2017.
  114. ^ Lovvorn, Jennifer (May 11, 2012). "Central Subway Moscone station: Ticketing Hall wall detailed public art project outline" (PDF). San Francisco Arts Commission. Retrieved August 17, 2021.
  115. ^ "Panel Summary: Artist selection panel - meeting 2, Yerba Buena/Moscone Station Ticketing Hall wall" (PDF). San Francisco Arts Commission. April 3, 2013. Retrieved August 17, 2021.
  116. ^ "Shows as installed" (PDF). San Francisco Arts Commission, Visual Arts Committee. June 16, 2021. Retrieved August 17, 2021.
  117. ^ Horgos, Bonnie (November 11, 2012). "Santa Cruz County Stories, Moto Ohtake: Local artist's sculptures juxtapose structure with chaos". Santa Cruz Sentinel. Retrieved June 4, 2018.
  118. ^ Ohtake, Moto. "Microcosmic: Art Proposal for the 4th and Brannan Street Platform Station" (PDF). City of San Francisco. Retrieved June 4, 2018.
  119. ^ Ohtake, Moto (2014). "Microcosmic, project shop drawings" (PDF). San Francisco Arts Commission. Retrieved August 17, 2021.
  120. ^ Public Art Program Annual Report FY2020 (PDF) (Report). San Francisco Arts Commission. 2020. Retrieved August 17, 2021.