Padma Bridge
Padma Bridge পদ্মা বহুমূখী সেতু | |
---|---|
Coordinates | 23°26′46″N 90°15′44″E / 23.446°N 90.2623°E |
Carries | Motor vehicles, Railway |
Crosses | Padma River |
Locale | Louhajang Upazila |
Official name | The Padma Multipurpose Bridge |
Maintained by | Bangladesh Bridge Authority |
Website | www |
Next upstream | Lalon Shah Bridge |
Characteristics | |
Design | Truss bridge |
Material | Steel |
Total length | 6,150 m (20,180 ft) |
Width | 18.18 m (59.6 ft) |
No. of spans | 41 |
No. of lanes | 3ċ |
History | |
Constructed by | China Railway Major Bridge Engineering Company Limited |
Construction start | 7 December 2014 |
Construction end | 2022(expected)[1] |
Construction cost | $3,692,000,000 |
Opening | June 2022 (expected)[1] |
Inaugurated | June 2022 |
Location | |
The Padma Multipurpose Bridge is a multipurpose road-rail bridge across the Padma River, the main distributary of Ganges, under construction in Bangladesh with its own resources.[2][3] It connects Louhajong, Munshiganj to Shariatpur and Madaripur, linking the south-west of the country, to northern and eastern regions. Padma Multipurpose Bridge is considered to be the most challenging construction project in the history of Bangladesh. The two-level steel truss bridge carries a four-lane highway on the upper level and a single track railway on a lower level.[4] The bridge with 150.12 m (492.5 ft) long 41 spans, 6.150 km (3.821 mi) total length[3] and 22.5 m (74 ft) width,[5] is the longest bridge in Bangladesh, and the longest over Ganges in terms of both span and the total length.[6] The highest depth of pile of this bridge is 122 metre, which is highest among all other bridges.[7] Padma Multipurpose Bridge, when commissioned, is expected to boost the GDP of Bangladesh by as much as 1.2 percent.[8]
History[]
The Bangladesh Bridge Authority (BBA) invited the pre-qualification tender for the project in April 2010. Construction of the bridge was expected to commence by early 2011[9] and be ready for major completion in 2013 (and complete all sections by late 2015[10][unreliable source?]).
After allegation of corruption by some people associated with project preparation the World Bank withdrew its commitment and other donors followed. The Government of Bangladesh then decided to fund the project from its own fund.[6]
China proposed building the bridge on the build-operate-transfer (BOT) basis by investing $2 billion or 70 percent of the project cost. Four companies—China Major Bridge Engineering Company, Daelim-L&T JV and Samsung C&T Corporation—purchased the tender papers. But only the Chinese company submitted their financial proposal on 24 April 2014.
On 17 June 2014, important progress had been made in the construction of the Padma Multipurpose Bridge. A construction firm, China Major Bridge Engineering Company Ltd, has been selected to construct the long aspired bridge on the river Padma. The 6.15 km bridge, costing an estimated ৳91.72 billion (US$1.1 billion).
Overview of Padma Multipurpose Bridge Project[]
Design Team :- The detailed design of the Padma Multipurpose Bridge is being delivered by a team of international and national consultants headed by AECOM.[11][unreliable source?] The team comprises AECOM, SMEC International, Northwest Hydraulic Consultants[12] and ACE Consultants, with additional assistance from Aas-Jakobsen and HR Wallingford. The Project comprises two phases. Phase 1 of the Project includes the Design Phase leading through procurement action to the award of construction contracts. Phase 2 is the Construction Phase. Phase 1 of the project commenced on 29 January 2009. A dedicated Project Office was set up in Dhaka in March 2009. Detailed design of the main bridge was carried out in AECOM's Hong Kong office. All work carried out by the design team was carried out within the framework of AECOM's Quality Management System (QMS) which is independently accredited to AS/NZS ISO 9001. The QMS is designed to control all project work undertaken by the team. A project-specific Design Management Plan was established at the outset of the project, In March 2009, the Government of Bangladesh requested AECOM to accelerate the design with a view to ensuring construction could be completed before the end of 2013. This necessitated the mobilization of additional personnel within the design team. Bangladesh Bridge Authority (BBA) established an internationally recognized Panel of Experts comprising five national and five international experts to review the design at regular intervals. In addition, an Independent Checking Engineer, Flint & Neill, was engaged to review the design criteria, specification and drawings produced by the design team to ensure the design meets the project requirements and to undertake an independent check of the detailed design of the main bridge and river training works. A key feature of the detailed design was the integration of Bangladesh counterparts into the design team, which allowed the successful training of a significant number of Bangladesh personnel in all aspects of the project and the subsequent transfer of the high level of technology involved in this large and complex project.[13]
Component of the project :
- Main Bridge
- River Training Works (RTW)
- Janjira Approach Road & Selected Bridge End Facilities
- Mawa Approach Road & Selected Bridge End Facilities
- Service Area-2
- Resettlement
- Environment
- Land Acquisition
- CSC (main bridge & RTW)
- CSC (approach roads & Service Area-2)
- Engineering Support & Safety Team (ESST)
Main Bridge 6,150 m (20,180 ft):
- Contractor : China Major Bridge Engineering Co. Ltd, China
- Contract Period: 4 years+1 years (defect liability period)
- Contract Cost : BDT: 12,133.39 crore
- Date of Work Order: 26 November 2014
- Date of Completion: 31 December 2019
- Physical Progress of Work: 85.50%
River Training Works 14 km (8.7 mi) length.
- Contractor : Sinohydro Corporation Limited, China.
- Contract Period: 4 years+1 years (defect liability period).
- Contract Cost : BDT: 9,400 crore.
- Date of Work Order: 31 December 2014.
- Date of Completion: 31 December 2019
- Physical Progress of Work: 66%
Janjira Approach Road & Selected Bridge End Facilities 10.50 km (6.52 mi) length
- Contractor : AML-HCM JV.
- Contract Period : 3 years+1 year (defect liability period).
- Contract Cost : BDT: 1097.40 crore.
- Date of Work Order: 8 October 2013.
- Date of Completion: 31 October 2016
- Physical Progress of Work: 100%
Mawa Approach Road & Selected Bridge End Facilities 1.50 km (0.93 mi) length
- Contractor : AML-HCM JV.
- Contract Period : 2.5 years+1 year (defect liability period).
- Contract Cost : BDT: 193.40 crore.
- Date of Work Order: 27 January 2014
- Date of Completion: 31 July 2017
- Physical Progress of Work: 100%.
Service Area-2:
- Contractor : Abdul Monem Ltd.
- Contract Period : 2.5 years+1 year (defect liability period).
- Contract Cost : BDT: 208.71 crore.
- Date of Work Order: 12 January 2014
- Date of Completion: 31 July 2017
- Physical Progress of Work: 100%
Resettlement:
- Total Additional Grant: BDT: 645.95 crore (up to September 2019)
- Total No. of Plots: 2752
- 2418 plots have been handed over to the PAP (up to September 2019)
- Date of Work Order: 1 June 2009
- Date of Completion: 30 June 2020
Environment:
- Total No. of Trees Planted: 1,69,957
- Date of Work Order: 1 June 2009
- Date of Completion: 30 June 2020
Land Acquisition:
- Total Land Acquisition:
- Munshiganj: Acquired: 329.64 hectares, Handed Over: 319.92 hectares
- Madaripur: Acquired: 1601.19 hectares, Handed Over: 553.18 hectares
- Shariatpur: Acquired: 610.96 hectares, Handed Over: 579.95 hectares
- Date of Work Order: 1 August 2006
- Date of Completion: 31 December 2019
CSC (Main Bridge & RTW):
- Consultant : Korea Expressway Corporation, South Korea & Associates.
- Contract Period: 4 years+1 years (defect liability period).
- Contract Cost : BDT: 383.15 crore.
- Date of Signing Contract : 3 November 2014.
- Date of Completion: 30 November 2019
- The Progress of Work: 84%
CSC (Approach Road & Service Area):
- Consultant : Special Works Organization (SWO-West), Bangladesh Army in association with Bureau of Research, Testing and Consultation of BUET.
- Contract Period : 3 years+1 year (defect liability period).
- Contract Cost : BDT: 133.49 crore.
- Date of Work Order: 13 October 2013
- Date of Completion: 31 October 2018
- The progress of Work: 100%.
Engineering Support & Safety Team (ESST):
- ESST : Bangladesh Army.
- Contract Period: 4 years+1 years (defect liability period).
- Contract Cost : BDT: 72.14 crore.
- Date of Work Order : 13 October 2013
- Date of Completion: 31 October 2018
- Progress of Work : 100%
Current status of project[]
As of November 2020, more than 92% of the construction (all the main steel frame spans are set on the piers) of the 6.15-kilometre-long two-tier Padma Multipurpose Bridge has been completed.[14] The China Major Bridge Engineering Corporation (MBEC), which was appointed for the main bridge, will carry out the work. The soil testing and dredging works have been going on for the last four months for the river training. The bridge will have a total of 42 pillars. Each will have six piles beneath. Steel spans will be placed on the pillars. The bridge will have a total of 41 spans.
Work on the Padma Multipurpose Bridge is broadly divided into five parts—the main bridge, river training, two link roads and infrastructure (service area) construction. China's Sinohydro Corporation was appointed for the river training works while Bangladesh's Abdul Monem Limited was given the contract for the two link roads and infrastructure construction.
In October 2017, more than one and a half years after the main construction work began, the first span was installed between pillars 37 and 38, indicating timely progress on the project.[15]
In 27 November 2020, construction of 42 pillars out of 42 has been completed.[16]
The final (41st) span of the bridge was installed on 10 December 2020 at 12:02 PM.[8][17]
The last road slab was installed on the span that linked the pillars 12 and 13 of the Padma bridge on 24 August 2021 at 10:12 AM.[18]
After completion, the bridge will be the longest bridge in Bangladesh.
The new completion date of the bridge is estimated to be in June 2022.[1]
Controversy and rumours[]
From the beginning, the Padma Multipurpose Bridge negotiation had been involved in controversy and conspiracy. The World Bank stated that they found, "credible evidence corroborated by a variety of sources which points to a high-level corruption conspiracy among Bangladeshi government officials, SNC-Lavalin executives, and private individuals in connection with the Padma Multipurpose Bridge Project."[19] As a result of the alleged corruption, the World Bank initially refused to sanction the proposed loan for constructing the bridge and imposed conditions for the continuation of loan talks with the government. In accordance with one of these conditions Communications Minister Syed Abul Hossain had to resign, as he was alleged to have been involved in the corruption.[20] SNC-Lavalin accepted a negotiated resolution agreement where the company and its affiliates were barred from taking part from bidding for World Bank contracts for 10 years. This is particularly significant as one of the four criteria required before the international donor agrees to a negotiated settlement is: "Whether an accused party has admitted culpability". Some assume that SNC Lavalin had done so.[21]
However, the corruption allegations were subsequently found to be false and without merit and a Canadian Court subsequently dismissed the case.[22]
In 2017, controversial former ICC prosecutor Luis Gabriel Moreno Ocampo, came to Dhaka to monitor the progress of the alleged Padma Multipurpose Bridge corruption investigation.[23]
The World Bank sent a panel of three, headed by Ocampo, to review the steps taken by the ACC in the Padma Multipurpose Bridge investigation. As recommended by the panel, the ACC filed a case implicating former Bridges Division secretary Mosharraf Hossain Bhuiyan and six other high-ranking government officials. Bhuiyan had to be in jail in the case (meaningless sentence). However, a Canadian court found "no proof" of bribery conspiracy in the project and acquitted in January (Year??) three executives of charges that SNC-Lavalin Group Inc staff planned to bribe Bangladesh officials in the Padma Multipurpose Bridge project.[23]
Rumours spread on social media platforms like Facebook that human heads would be required in the construction of the Padma Bridge in July 2019. This led to the beating of many people in different parts of Bangladesh and the handing over of them to the police. Later on 9 July 2019, the bridge construction authority sent a notification to the media stating that the incident was rumoured and baseless. Researchers advised the bridge authorities to spread all the details of the construction of the bridge among the people[24][25]
Gallery[]
The Padma Bridge in September 2021
The Padma Bridge in November, 2021(1)
The Padma Bridge in November, 2021(2)
The Padma Bridge in November, 2021(3)
The Padma Bridge in November, 2021(4)
Under Construction image[]
Under Construction padma multipurpose bridge
Under Construction padma multipurpose bridge
Under Construction padma multipurpose bridge
Under Construction padma multipurpose bridge
See also[]
- 99th Composite Brigade, a Bangladesh Army brigade deployed to ensure security of the bridge
- Ganges Barrage Project, another proposed mega-project to combat the water deficiency caused by the Farakka Barrage
- Jamuna Bridge, a similar completed bridge across the Jamuna River
- Padma Cantonment, a cantonment built near the Padma Multipurpose Bridge
- List of megaprojects in Bangladesh
References[]
- ^ a b c "Padma Bridge likely to open to traffic by June 2022". Dhaka Tribune. Retrieved 22 December 2020.
- ^ "By self-funding the Padma dridge,Dhaka has got the West off its back". The Economic Times. Retrieved 10 December 2020.
- ^ a b "Main Bridge Details (Technical)". Padma Multipurpose Bridge Project. Retrieved 10 December 2020.
- ^ Sultana Munima (14 October 2014). "Korean co gets Pawdda bridge supervision work". The Financial Express. Dhaka. Retrieved 11 November 2014.
- ^ "Padma Multipurpose Bridge Project, Volume II: Environmental Assessment". World Bank. 6 September 2010. Retrieved 15 April 2021.
- ^ a b "Padma Bridge -- New Lifeline of Development". The Daily Star. 18 January 2016.
- ^ ৩ বিশ্ব রেকর্ড করল পদ্মা সেতু. Jugantor (in Bengali). Retrieved 22 December 2020.
- ^ a b "Last span of Padma Multipurpose Bridge installed". The Daily Star. 10 December 2020. Retrieved 10 December 2020.
- ^ "Funds for Pawdda Bridge Arranged". Bangladesh News. 4 December 2010. Archived from the original on 5 February 2018. Retrieved 5 January 2011.
- ^ "ADB Approves Loan for Bangladesh Bridge Project". roadtraffic-technology.com. 30 November 2010. Retrieved 5 January 2011.
- ^ http://www.roadtraffic-technology.com/projects/padma-bridge/padma-bridge4.html
- ^ "NHC Project: Multipurpose Bridge - Padma". www.nhcweb.com.
- ^ Wheeler, W. K.; Aves, R. J.; Tolley, C.J.; Zaman, Mohammad; Islam, Md. R (2010). "Detailed design of the Padma Multipurpose Bridge, Bangladesh – An overview" (PDF). In Amin, A. F. M. (ed.). Proceedings of the IABSE-JSCE Joint Conference on Advances in Bridge Engineering-II, August 8–10, 2010, Dhaka, Bangladesh. Dhaka: Bangladesh Group of IABSE. pp. 120–133. ISBN 978-984-33-1893-0.
- ^ "Present Status of the project". Padma Multipurpose Bridge Project.
- ^ "Padma Multipurpose Bridge becomes visible as first span installed". bdnews24.com.
- ^ "Padma Multipurpose Bridge: 39th span installed, only 2 more to go". Dhaka Tribune. 27 November 2020. Retrieved 27 November 2020.
- ^ "Last span of Padma Multipurpose Bridge installed". Daily Sun. Retrieved 10 December 2020.
- ^ "It's possible to walk across the Padma now". The Daily Star. 24 August 2021.
- ^ "World Bank Statement on Padma Multipurpose Bridge". World Bank. Retrieved 8 December 2015.
- ^ "Abul Hossain resigns". BanglaNews24.com. 23 July 2012. Archived from the original on 10 April 2013. Alt URL
- ^ Bergman, David (26 February 2017). "Alt-facts in Bangladesh: Politicians spin Canada corruption ruling to make government look good". Scroll.in.
- ^ "Canada court finds no proof of Pawdda bridge bribery conspiracy". The Daily Star. 11 February 2017.
- ^ a b "Ex-prosecutor Ocampo 'undermines' International Criminal Court, leaked documents reveal". bdnews24.com. 5 October 2017.
- ^ গুজবের জবাব দিলো পদ্মাসেতু. Daily Prothom Alo (in Bengali). 10 July 2019. Retrieved 1 January 2019.
- ^ পদ্মা সেতু তৈরিতে মানুষের মাথা লাগার গুজব কেন ছড়ালো?. BBC Bangla (in Bengali). 10 July 2019. Retrieved 1 January 2021.
External links[]
- Bangladesh Bridge Authority, Padma Multipurpose Bridge
- Padma Bridge will Change Destiny of Bangladesh
Wikimedia Commons has media related to Padma Bridge. |
- Railway bridges in Bangladesh
- Road bridges in Bangladesh
- Road-rail bridges
- Truss bridges
- Toll bridges in Bangladesh
- Bridges over the Ganges
- Bridges under construction