Namma Metro
Overview | |||
---|---|---|---|
Owner | Bengaluru Metro Rail Corporation Limited (BMRCL) | ||
Locale | Bengaluru | ||
Transit type | Rapid transit | ||
Number of lines | 2 | ||
Line number |
| ||
Number of stations | 51[1] | ||
Daily ridership | 518,074 (January 2020)[2] | ||
Annual ridership | 174.22 million (2020)[2] | ||
Chief executive | Anjum Parvez (MD) | ||
Headquarters | BMTC Complex, K.H. Road, Shanthinagar, Bengaluru | ||
Website | bmrc.co.in | ||
Operation | |||
Began operation | October 20, 2011 | ||
Train length | 6 coaches[3] | ||
Headway | 4–15 minutes[4] | ||
Technical | |||
System length | 56.1 km (34.9 mi) | ||
No. of tracks | 2 | ||
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge | ||
Electrification | 750 V DC third rail | ||
Average speed | 36 km/h (22 mph) | ||
Top speed | 80 km/h (50 mph) | ||
|
Namma Metro ("Our Metro" in Kannada), also known as Bangalore Metro or Bengaluru Metro, is a rapid transit system serving the city of Bengaluru, India. Upon its inauguration, it became the first metro system in South India.[5] Namma Metro has a mix of underground, at grade, and elevated stations. The system runs on standard-gauge tracks.
Bengaluru Metro Rail Corporation Limited (BMRCL), a joint venture of Government of India and the State Government of Karnataka, is the agency for building, operating and expanding the Namma Metro network.[6] Services operate daily between 05:00 and 23:00 running with a headway varying between 4–20 minutes.[7] The trains initially began with three coaches but were later converted to six coaches as ridership grew.[8] Power is supplied by 750 volt direct current through third rail. As of January 2020, the metro system had an average daily ridership of about 518,000 passengers.[6]
History[]
This section needs additional citations for verification. (August 2021) |
The State Town Planning Department had recommended looking into a mass rapid transit project, i.e. a metro for Bangalore city way back in 1977. A high-level Committee had also agreed that a metro study was warranted and a team from Southern Railway (SR) was commissioned to do this in 1981. The Southern Railway team recommended a 2-corridor metro, 24 km in length in addition to commuter rail lines and a ring railway.[9]
In 1993, the State of Karnataka established another committee to look into mass rapid transit. This committee had again recommended the same metro project put forward by SR in 1983 and the same circular railway.[9]
The state created Bangalore Mass Rapid Transit Ltd (BMRTL) in 1994, with terms of reference to seek a public/private partnership for a mass rapid transit project. The government immediately introduced a special city cess dedicated to the anticipated mass rapid transit project. BMRTL commissioned a feasibility study which came up with an elevated, LRT-based, 96-km long network on 6 routes. A private consortium led by United Breweries Group undertook further development of the project on BOT basis. However, the project hadn't taken off.[9]
In 2003, the Government of Karnataka commissioned the Delhi Metro Rail Corporation (DMRC), which had successfully developed the Delhi Metro, to carry out a detailed preparation study for a metro in Bangalore, to be done emulating the technical and financial aspects of the approach used in Delhi. The study recommended a 2-line metro, 18 km and 15 km in length, cross shaped. The middle of the cross was to be at the Central Railway Station in Bangalore, completely underground. The economic rate-of-return was forecast at 22.3%. The financial forecast assumes a government subsidy for interest payments and some depreciation, i.e. fare revenue will cover somewhat more than direct operating costs. The Government accepted this option. BMRTL ceased to exist and was replaced by Bangalore Metro Rail Corporation Ltd (BMRCL).[9]
Network[]
Namma Metro lines[]
Purple Line[]
Purple Line is aligned east to west and connects Baiyyapanahalli in the east with Kengeri station in the southwest. The line is 25.7 km long and has 22 stations. It is elevated on both east and west sides and has a 4.8 km underground section in the middle. The Line passes through prime activity centers of the city (MG Road, Majestic, Railway Station, Vidhana Soudha etc.). It is currently being expanded on its eastern reach.
The first 6.7-kilometre (4.2 mi), 6-station stretch (Reach 1) of the Purple Line between Baiyappanahalli in the east and Mahatma Gandhi Road opened on 20 October 2011.[10] This was the inaugural section of Namma Metro.[11] The second 6.4-kilometre (4.0 mi), 6-station stretch (Reach 2) between Mysore Road and Magadi Road opened on 16 November 2015.[12] The underground section, a 4.8 km (3.0 mi) stretch from Cubbon Park to Bengaluru City (KSR) Railway Station opened on 29 April 2016, thus linking east and west sections that were already opened. Opening the underground section completed the entire Purple Line in Phase-1. A 7.5 km extension on the south west opened on 30 August 2021 under phase-2.
Green Line[]
The Green Line is aligned north to south and connects Nagasandra in the north-west to Silk Institute in the south-west, covering a distance of 30.4 kilometres (18.9 mi)[13] and serving 30 stations.[14] It is elevated on both north and south sides and has a 4.0 km underground section in the middle. The Line passes through industrial areas (Peenya, Yeshwanthapur) in the north and also through commercial hubs (Majestic, Chikpete, City Market) and connects large residential catchments in the south (Basavanagudi, Jayanagar, Banashankari etc.). It is currently being expanded at its northwestern end.
The first 9.9-kilometre (6.2 mi), 10-station stretch (Reach 3/3A) of the Green Line opened 1 March 2014.[15][16] The stretch connected Sampige Road to Peenya Industry.[17] The second 2.5-kilometre (1.6 mi), 3-station stretch (Reach 3B) of the Green Line from Peenya Industry to Nagasandra, opened on 1 May 2015.[18][19] The third stretch connecting Sampige Road to Yelachenahalli was inaugurated on 17 June 2017 and opened the next day, thereby completing the entire Phase 1.[20][21] These stretches (including the underground section) were inaugurated by then President late Shri Pranab Mukherjee on 17 March 2017.[22][23] The 6.29-kilometre (3.91 mi) stretch from Yelachenahalli to Silk Institute was inaugurated on 14 January 2021, making it the first section of Phase-2 to be opened for service.[24]
Namma Metro | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
Line | Opening date | Last extension | Stations[14] | Length[25](km) | Terminals | Rolling stock | Track gauge (mm) | Power | Minimum headway | |
Purple Line | 20 October 2011 | 29 August 2021 | 23 | 25.72 | Baiyyappanahalli | Kengeri | BEML | 1435mm | 750 V DC third rail | 5 |
Green Line | 1 March 2014 | 15 January 2021 | 29 | 30.37 | Nagasandra | Silk Institute | BEML | 1435mm | 750 V DC third rail | 5 |
Total | 52 [b] | 56.1 |
[b] Discrepancies in total number of stations is due to an interchange station that is counted once for each line.
Section details and opening dates
Section | Phase | Length (km)[25] | Terminal stations | Opening date | |
---|---|---|---|---|---|
Reach 1 (east) | 1 | 6.7 | Baiyyappanahalli | M G Road | 20 October 2011 |
Reach 2 (west) | 1 | 6.4 | Mysuru Road | Magadi Road | 16 Nov 2015[12][26] |
Underground UG1 (east–west) | 1 | 4.8 | Mahatma Gandhi Road | Magadi Road | 30 April 2016 |
Reach 2A/B (west) | 2 | 7.5 | Mysuru Road | Kengeri | 30 August 2021 |
Reach 3 (north) | 1 | 5.1 | Sampige Road | Yeshwanthpura | 1 March 2014[16] |
Reach 3A (north) | 1 | 4.8 | Yeshwanthpura | Peenya Industry | 1 March 2014[16] |
Reach 3B (north) | 1 | 2.5 | Peenya Industry | Nagasandra | 1 May 2015[18][19] |
Underground UG2 (north–south) | 1 | 4.0 | Sampige Road | National College | 18 June 2017[27] |
Reach 4 (south) | 1 | 4.1 | National College | R V Road | 18 June 2017[27] |
Reach 4A (south) | 1 | 3.9 | Rashtreeya Vidyalaya | Yelachenahalli | 18 June 2017[27] |
Reach 4B (South) | 2 | 6.3 | Yelachenahalli | Silk Institute | 15 January 2021[28] |
More lines and extensions are under construction. When completed, the 2nd phase (currently underway) will provide connectivity to the city's tech hubs of Electronic City and Whitefield, besides covering the eastern half of Outer Ring Road (ORR) and providing service to the Kempegowda International Airport in the north of the city.
Construction[]
Phase 1[]
Delhi Metro Rail Corporation Limited (DMRC) prepared and submitted the detailed project for the first phase of Namma Metro in May 2003. The DPR was for a 33 km (21 mi) network with 32 stations for Phase 1 of the project, using standard gauge. The project was approved by the Union Cabinet on 25 April 2006. The foundation stone for construction of Phase 1 was laid by then Prime Minister Dr. Manmohan Singh on 24 June 2006.[29] Navayuga Engineering Company Limited was awarded the first contract to construct Reach 1 of the east–west corridor in 2006. Civil construction on the first section (Reach-1) of the Purple Line between Baiyyappanahalli and Mahatma Gandhi Road, commenced on 15 April 2007.[30]
DPRs for a northern extension (from Yeshwanthapura to Nagasandra) and a southern extension (from Rashtreeya Vidyalaya Road to Yelachenahalli) was submitted in October 2007 and June 2008 respectively. With these extensions, the total route length for phase-1 became 42.3 km. The objective was to connect the metro to the Outer Ring Road at northern and southern ends, and also cover the industrial areas of Peenya in the north-west, thereby providing better connectivity and increasing ridership. In October 2008, the Government of Karnataka approved this extension, which would cost an additional ₹1,763 crore (US$250 million).[31]
Underground section[]
Both lines in Phase-1 have tunnel sections in the city center which were the first metro tunnels built in South India.[5] Construction of underground sections in Phase 1 commenced during late 2012. The delay was due to cancellation of the initial tenders called during early 2008 as the entire DPR had to be revised and bids received were too high.[32] A second round of tendering was done in late 2009 with the gigantic Majestic inter-change station as a separate package.[33] Bids were awarded for the tunnel sections during 2011 and construction began in 2012.
The tunnels bored with tunnel boring machines (TBMs), located approximately 60 feet below ground level, have a diameter of 5.5 meters and are 5 meters apart. The TBMs were nicknamed Helen, Margarita,[34] Kaveri, Krishna and Godavari.[35]
Tunnel boring of underground section UG1 (on east–west corridor) was completed on 17 March 2014.[36] Track works and 3rd rail electrification works were completed on the 4.8 km east–west tunnel of the Purple line between Cubbon Park and Magadi Road and Bangalore Metro Rail Corporation Ltd (BMRCL) began trials on 23 November 2015. The entire stretch of the Purple Line was opened on 29 April 2016.[37]
Tunnel boring of underground section UG2 (on north–south corridor) was completed on 23 September 2016. The tunneling faced a major delay when the cutter head of TBM Godavari was broken and spares had to be awaited.[38] Trial runs on the 4.0 km east–west tunnel of the Green line between Sampige Road and National College were commenced on 31 March 2017. The entire stretch of Green Line was opened on 19 June 2017, thus completing phase-1 of the project.[39]
Opening[]
After missing deadlines, Namma Metro's first section (Reach-1) had finally opened to the public on 20 October 2011.[40][41][42] There was an overwhelming response by the public at commencement of operations. As per BMRCL sources, within the first 3 days of operations 169,019 people rode the metro.[43] At the end of the 4th day, about 200,000 passengers had already commuted on Namma Metro. Namma Metro's first 12-day cumulative revenue was ₹1 crore (US$140,000).[44]
The northern section of Green Line (Reach 3,3A,3B) was initially scheduled to be opened by the end of 2012. However, it was delayed and finally opened on 1 March 2014.[45] BMRCL MD Pradeep Singh Kharola stated that about 25,000 passengers travelled on the line on the opening day.[16] In the first month of operations, 7.62 lakh people used the line, at an average of 24,605 daily, generating revenues of ₹1.5 crore (US$210,000).
The first underground section (on the Purple line) commenced operations on 30 April 2016, thus providing through connectivity between east and west of the city.
The second underground section, along with southern reaches (viz. Reach 4,4A) was opened on 18 June 2017.[46]
Once the east and west reaches were inter-connected with opening of the underground section of the purple line, ridership surged hugely. After the north–south underground section was opened (simultaneously with the elevated reach 4,4A in the south), the network provided connectivity in all four directions with interchange between the lines and this further increased ridership. Ridership kept increasing and was around 4,50,000 daily (September 2019).[47]
Phase 1 lines and sections[]
Phase 1 comprises two lines spanning a length of 42.30 kilometres (26.28 mi), of which about 8.82 kilometres (5.48 mi) is underground and about 33.48 kilometres (20.80 mi) is elevated.[13] There are 40 stations in Phase 1, of which 7 stations are underground, 1 at grade and 32 are elevated.[48]
The first phase of the project was initially budgeted at ₹6,395 crore (US$875 million).[49] With route extensions and cost escalation, this was later revised to ₹11,609 crores (US$1.6 billion). There were many delays during construction and as a result, there were several postponements. The difficult geological conditions below ground with a mix of soft soil, high groundwater levels, hard granite and large boulders was a major impediment for tunnel boring. A major delay was due to a broken cutter head of TBM Godavari for which spares had to be ordered from Italy.[50][51] Phase 1, containing 2 lines aggregating 42.3 km was completed and services opened to public on 19-June-2017. The final costs for phase-1 were ₹14,405 crores.[52]
Phase 2[]
The State Government accorded approval for preparation of the detailed project report (DPR) for Phase 2 by DMRC on 4 January 2011.[53] The high power committee (HPC) gave in-principle clearance to proceed with Phase 2 in July 2011. Karnataka government gave in-principle approval to Phase 2 of the Namma Metro project on 3 January 2012.[54][55] However, there were delays in DPR preparation and hence approval from Central government.[32] Phase 2 was cleared by the expenditure finance committee (EFC) in August 2013. The Union Cabinet finally announced that it had approved plans for phase-2 on 30 January 2014.[56]
The estimated total cost for Phase 2 was around ₹26,405 crore (US$3.7 billion) at 2011-12 price levels.[57] The State Government would contribute ₹9,000 crore (US$1.3 billion).[58] The project cost of ₹26,405 at 2011–12 price levels is set to escalate about 5 per cent every year with increasing cost of inputs. The Union government will share that part of cost escalation due to increase in central levies, while the State and BMRCL will have to bear any other escalation. The total project cost for Phase 2 is estimated to reach at least ₹30,000 crore (US$4.2 billion) at start of construction itself. In October 2018, Deputy Chief Minister G Parameshwara stated that the cost of Phase 2 would be around ₹32,000 crore (US$4.5 billion).[59]
Phase 2 spans a length of 72.095 km (44.798 mi) – 13.79 km (8.57 mi) underground, 0.48 km (0.30 mi) at grade and 57.825 km (35.931 mi) elevated, and adds 62 stations to the network, of which 12 are underground.[60] Phase 2 includes extension of the two Phase 1 lines in both directions, as well as construction of two new lines.[61]
The south-end of the Green Line will be extended from Yelachenahalli to Silk Institute (previously named Anjanapura) along Kanakapura Road, north-end from Nagasandra to Madavara (previously named BIEC) on Tumkur Road (NH-4). The east-end of the Purple Line will be extended from Baiyappanahalli to Whitefield and the west-end from Mysore Road to Kengeri (later extended to Challaghatta). A new, 18.82 km (11.69 mi) long, fully elevated line from RV Road to Bommasandra will be constructed, passing through Electronic City. The second new line will be 21.25 km (13.20 mi) from Kalena Agrahara (previously Gottigere) to Nagawara. The line is mostly underground (13.79 km or 8.57 mi), but also has a 6.98 km (4.34 mi) elevated section and a 0.48 km (0.30 mi) at-grade section. There are 18 stations on the line, of which 12 are underground and 6 are elevated.[48] Unlike Phase 1, all stations being built in Phase 2 will have bus bays and/or parking facilities.[62]
Karnataka Industrial Areas Development Board (KIADB) is responsible for acquiring land for Phase 2. It was estimated that 102.02 hectares (252 acres) of land would be required for Phase 2 (including Phase 2A). By April 2017, BMRCL had already spent ₹5000 crore on land acquisition.[63]
Construction work began on the south extension of the Green Line from Yelachenahalli to Silk Institute (6.29 km or 3.91 mi) and the west extension of the Purple Line from Mysore Road to Kengeri (8.81 km or 5.47 mi) by October 2016. Construction work on the west extension of Purple Line was awarded in two packages for ₹660 crore,[64] while the Green Line south extension was awarded in a single package for ₹508.86 crore.[65]
Construction work for the north extension of the Green Line (from Nagasandra to Madavara) and the east extension of the Purple Line (from Baiyyappanahalli to Whitefield) began in July 2017. The 3.031 km (1.883 mi) north extension is estimated to cost ₹247.41 crore[66] while the east extension (15.5 km) was awarded for ₹1,300 crore (US$180 million).[67]
Construction of the yellow line, a new line from Rashtreeya Vidyalaya Road to Bommasandra in 3 packages began post awarding of tenders in November 2017. The first package (6.418 km / 3.988 mi) was a stretch from Bommasandra to Hosa Road station, including depot entry line to Hebbagodi depot and five Metro stations. The second package was for a 6.38 km (3.96 mi) stretch from Hosa Road to Bommanahalli (previously HSR Layout). Both packages were awarded for ₹1,750 crore (US$250 million) to Thailand-based ITD Cementation India.[67] The third package was for a stretch from RV Road to Bommanahalli (previously HSR Layout), 6.34 km long elevated section and 5 stations, for ₹797.29 crores (US$110 million) and includes the construction of a road-cum-rail flyover, road widening and allied works.[68]
Construction of the 7.5 km elevated section of a new pink line between Kalena Agrahara and Tavarekere (previously Swagat Road Cross) stations, estimated to cost ₹575.52 crore (US$81 million) began post tendering in February 2018. The tender includes the construction of the elevated viaduct, 5 stations and car depot line to Kothanur depot.[69]
Underground section[]
BMRC initially floated tenders for the construction of the 13.9 km underground section in four packages during June 2017. However, the tenders were cancelled as all the bids received were far too high (higher by nearly 70%)[70][71] at Rs.8553.45 core (US$1.28 billion) when compared to BMRC's estimated total of Rs 5047.56 core (about US$760 million).
The second round of tendering resulted in tenders being awarded to three firms during March–June period, 2019. One of the firms (L&T) won two bids.[72]
The total awarded tunneling tenders for the underground sections was ₹5,925.95 crores (appx US$812 million).[73][74][75]
Pre-tunneling construction work and piling for stations began in May 2019 by L&T.[76] Tunnel boring using TBMs began in July 2020 by L&T.[77] Tunnel boring work by the other two contractors (viz. Afcons & ITD-Cem) was commenced during 2021.
Phase 2A[]
In September 2016, then-Chief Minister of Karnataka Siddaramaiah announced that a new 18 km (11 mi) line connecting Silk Board with K.R.Puram would be included in Phase 2 as Phase-2A of the project. The line would be along the eastern half of Outer Ring Road and is proposed to have 13 stations – Silk Board, HSR Layout, Agara, Ibbalur, Bellandur, Kadubeesanahalli, Kodibisanahalli, Marathahalli, ISRO, Doddanekundi, DRDO Sports Complex, Sarasvathi Nagara (previously Mahadevapura) and K.R. Puram.[78] The cost was estimated to be ₹4202 crores. BMRCL prepared the detailed project report for the proposed line and submitted the DPR to the state government on 28 October 2016.[79] Phase 2A was approved by the State Cabinet on 1 March 2017.[80] The ORR Metro line (Blue line) will have interchange stations with the extended Purple Line at K.R.Puram and with the proposed R V Road – Bommasandra line (Yellow Line) at Silk Board.
Tenders for ORR Metro line (east) were called during February 2018 and IL&FS emerged the lowest bidder for all packages. However, the tenders were quashed due to cash flow problems and bankruptcy proceedings by the firm.[81] A second round of tendering was done during December 2019 and bids were received by multiple firms during March 2020.[82][83] There are two packages. The first package included 2.84 km of ramps for a flyover at Central Silk board junction in addition to 9.859 km of viaduct with six elevated stations. The second package was for 8.377 km viaduct with seven elevated stations, 1.097 km depot line and a 0.30 km pocket track.
Phase 2B (Airport Line)[]
There had been a proposal to build a 33 km (21 mi) high speed rail line from MG Road to Kempegowda International Airport (KIA), at a cost of ₹5,767 crore (US$810 million).[84] This was to be executed by an independent SPV, but later it was decided that BMRC would manage this project and a regular metro line with fewer halts would be built instead of a high speed rail, thus travel time between city to airport would be less. As early as in February 2012, the Central Government had also requested BMRC to start work on the airport link during Phase 2 itself.[85][86]
Following this, during September 2016, suggestions were invited from public to choose any one of nine possible extension routes from existing and proposed metro lines to the airport.[87] The proposed extension routes had an average length of 30 km (19 mi), and cost estimates ranged between ₹4,500 crore and ₹7,000 crore. A 25.9 km (16.1 mi) extension from Nagawara via Kannur and Bagaluru was the shortest, while the 35.4 km (22.0 mi) extension from Yeshwanthpur via Yelahanka, Kannur and Bagaluru was the longest of the proposed routes. BMRC received 1,300 responses from the public.[88] A 25.9 km (16.1 mi) extension of the Kalena Agrahara (previously Gottigere) – Nagawara line via Kannur and Bagaluru to the airport emerged as the most popular choice.[89]
Since Bangalore International Airport Limited (BIAL) forbade underground construction from the southern side of the airport (due to security as it would have to pass beneath the airport's second runway), the shortest route options (i.e. extending the Pink line from Nagawara directly north) were eliminated . An alternate route proceeding north till RK Hegde nagar and then turning west to Jakkur was then explored. However, even this had an obstacle as a high-pressure petroleum pipeline was passing through the originally proposed route.[90]
Bangalore Development Minister K. J. George announced on 12 May 2017 that the government had finalized the Nagawara-Ramakrishna Hegde Nagar-Jakkur-Yelahanka route to the airport.[91] On 10 January 2019, the State Cabinet approved a change in alignment for the proposed metro line to the airport. The new line would begin at Krishnarajapura (K.R. Puram) and be aligned along the northern part of ORR (Outer Ring Road), passing Nagawara, Hebbal, and Jakkur before heading towards the airport along Ballari road.[92] The line would be 39.8 km long, about 8 km longer than the route previously proposed. It is estimated to cost ₹10,584 crore (US$1.5 billion) almost twice as much as the previous route's estimate of ₹5,950 crore (US$830 million).[93]
The Union Cabinet cleared two much awaited lines of the Bengaluru Metro's Phase-2A and 2B on 20 April 2021. Phase-2A and Phase 2B lines total a distance of 58.19 km and were approved at a cost of Rs.14,788 crore. The projected ridership on both these lines in 2026 is estimated at 7.7 lakhs.[94] Construction of the airport line is expected to begin by October 2021.[95]
Phase 2, 2A, and 2B lines and sections[]
Phase 2 originally involved extending four reaches of the two lines in all directions and two new lines (Yellow Line and Pink Line).
The ORR-East Line was later included as Phase 2A followed by the Airport Line (as a continuation of the ORR-East Line) as Phase-2B. The line was later named as Blue Line.
Line | Terminals | Length | New stations | [96] Expected Work Completion date |
---|---|---|---|---|
Purple Line | Kengeri – Challaghatta | 1.30 km | 1 | March 2023[97] |
Purple Line | Baiyyappanahalli – Whitefield | 15.50 km | 13 | December 2022 |
Green Line | Nagasandra – Madavara (previously BIEC) | 3.77 km | 3 | September 2022 |
Yellow Line | Rashtreeya Vidyalaya Road – Bommasandra | 18.82 km | 16 | December 2022 |
Pink Line | Kalena Agrahara (previously Gottigere) – Nagawara | 21.25 km | 18 | March 2025 |
Blue Line | Central Silk Board - KR Puram | 18.30 km | 13 | September 2027 |
Blue Line | KR Puram - Kempegowda International Airport | 37.70 km | 17* | December 2027 |
Total (Phase-2, 2A, 2B) : | 132.63 km | 91 | *Includes two Airport Stations |
Construction of Phase 2 has been divided into six (elevated) reach extensions and four underground sections. Construction of Phase 2A has been divided into two (elevated section) packages. Construction of Phase 2B has been divided into three (elevated section) packages. Airport stations have not been included with tenders as they will likely be built by Kempegowda International Airport.
Progress on Construction
List of contracts for various sections under construction is as per table below:
Finances[]
Funding[]
Phase 1[]
Phase 1 missed nine deadlines, and its cost was revised four times. The initial cost estimate for Phase 1 when it had been approved in 2006 was ₹6,395 crore (US$850 million). The increase in length from 33 to 42.3 km (20.5 to 26.3 mi) increased the total cost to ₹8,158 crore (US$1.1 billion). Delays caused further escalations. The cost escalated to ₹11,609 crore (US$1.5 billion) in 2011 and ₹13,845 crore (US$1.8 billion) in 2015. The final cost to build Phase 1 was estimated at ₹14,405.01 crore (US$1.9 billion).[98] Land acquisition for Phase 1 accounted for ₹2,500 crore (US$330 million).[99]
The Central and State Government funded 58.91% of the cost. The remaining 41.09% was secured through loans from domestic and foreign financial institutions.[98] BMRCL secured ₹6,500 crore (US$860 million) through long-term loans and ₹300 crore (US$40 million) by selling bonds, while the remaining cost was funded by Central Government and the State Government. BMRCL secured loans from several agencies – ₹3,000 crore (US$400 million) from the Japan International Cooperation Agency (JICA), ₹600 crore (US$80 million) from the Housing and Urban Development Corporation Limited (HUDCO), ₹25 crore (US$3.3 million) from the Asian Development Bank (ADB), and the rest from the French Development Agency. Approximately 10% of the ₹6500 crore had to be paid as interest by the BMRCL each year. The Federation of Karnataka Chambers of Commerce and Industry (FKCCI) estimated that this amounted to an interest payment of ₹2 crore (US$270,000) per day. BMRCL stated that interest component wasn't that high but it was "definitely more than ₹1 crore (US$130,000) per day".[99]
BMRCL announced plans on 13 June 2013 to issue 10-year bonds.[100] The proposed bonds received a credit rating of "IND AA" from India Ratings & Research (Ind-Ra).[101] Namma Metro MD N. Sivasailam announced on 3 August 2013 that the issue of bonds would be postponed as the market was volatile. He stated that the metro would "be in the market soon when it is stable".[102]
Phase 2 /2A /2B[]
On 3 January 2012, the Karnataka government approved a budget of ₹27,000 crore (US$3.6 billion) for Phase 2 of Namma Metro project.[103] Phase 2 is estimated to cost ₹26,405 crore (US$3.5 billion). Land acquisition is expected to account for ₹5,000 crore (US$660 million).[99] The Central and State Governments will fund around ₹15,000 crore.[104] The State and Central Governments will bear 30% and 20% of the project cost respectively. The remaining will be obtained through senior term loans.[105] BMRCL is permitted to raise up to ₹9,000 crore through loans.[104]
On 27 March 2012, Asian Development Bank (ADB) signed an agreement to lend $250 million to BMRC to part-finance Phase 2. The loan marked the multilateral lending agency's foray into the urban transport sector in South Asia, the ADB said in a press release. The loan, approved by the ADB Board in March 2011, is the first ADB loan to the urban transport sector without recourse to sovereign guarantees.[106] In 2016, the Agence Francaise De Development (AFD) sanctioned a ₹1,600 crore loan for the project. The rate of interest on the loan is linked to Euro Interbank Offered Rate (Euribor) + 130 basis points. In early 2017, the European Investment Bank agreed to loan ₹3,700 crore to BMRCL, with a repayment period of 20 years at a rate of interest lower than the one on the AFD loan.[104][107]
In May 2017, BMRC received in-principle approval from the European Investment Bank (EIB) to fund construction of the Gottigere-Nagawara line through a ₹3700 crore loan.[108] The line will also be funded by the AIIB and the Central and State Governments.[109]
Indian firms Biocon and Infosys announced that they would provide funding for the construction of the Hebbagodi and Electronics City metro stations respectively on the RV Road-Bommasandra Metro line. BMRC expects that each firm will contribute ₹100 crore (US$13 million) towards the project. Biocon CMD Kiran Mazumdar Shaw stated that the company wanted to fund the project because it would help decongest the city. Both Biocon and Infosys have offices located near the stations.[110]
BMRCL secured a $318 million loan from JICA in March 2021, and a $500 million loan from the ADB in August 2021 to fund construction of the ORR-Airport metro. The State and Union governments will contribute ₹3,973 crore (US$530 million), and the Karnataka Government will pay an additional ₹2,762 crore (US$370 million) for land acquisition.[111]
Revenues[]
During the first month since the opening of Reach I of just 6.7 km, about 13,25,000 people travelled by metro.[112] On average, 41,390 people took the train every day, while the average daily revenue was ₹667,262. The BMRC earned a revenue of ₹2.1 crore (US$280,000) in its first month of operation.[113] However, during the first six months of operation, average ridership went down to 24,968. The BMRC earned a total of ₹6.6 crore (US$880,000) during the same period.[114] Namma Metro posted a profit of ₹41 lakh (equivalent to ₹66 lakh or US$87,000 in 2020) after about one year of operations of Reach I. BMRCL estimates that nearly 80 lakh passengers travelled on the system in its first year of operations.[115]
The following table shows annual ridership and farebox revenue of Namma Metro since inception.[116][117]
Year | Passengers | Fare Box Revenue(₹) |
---|---|---|
2011–12 | 4,166,000 | 6.17 crore |
2012–13 | 6,636,000 | 8.70 crore |
2013–14 | 7,255,000 | 9.86 crore |
2014–15 | 11,400,000 | 17.83 crore |
2015–16 | 16,800,000 | 28.29 crore |
2016–17 | 54,225,130 | 110.09 crore |
2017–18 | 109,206,905 | 281.00 crore |
2018–19 | 133,738,555 | 355.02 crore |
2019-20 | 174,219,000 | 376.88 crore |
Infrastructure[]
Rolling stock[]
BMRC procured 150 metro coaches for fifty 3-car train sets in DMC-TC-DMC formation for Phase l of Namma Metro from BEML - Hyundai Rotem at a cost of Rs 1,672.50 crore (Rs 16.72 billion). Coach specifications were as follows. Dimensions: Length-20.8m, Width-2.88m, and Height-3.8m. Each coach had a seating capacity of about 50 and standing capacity of 306 (basis 8 per sqm). Thus, each train had a capacity of about 1000. Traction is through four 180Kw motors in each motor coach. The trains have a maximum speed of 80 kmph and axle load of 15 tonnes. The trains operate on 750V DC with third rail bottom power collector system. Features include stainless steel body fully air-conditioned coaches, longitudinal bank of wide seats, wide vestibules between coaches, non-skid and non-slip floor surfaces, wi-fi enabled, four wide passenger access doors on each side, wide windows, automatic voice announcement system and electronic information and destination display system.
Thus, initial operations began with 3-coach trains. Each train had a capacity of 1000 passengers. As loads increased with increasing ridership, all trains were converted to six coaches.
The first train set made a trial run in December 2010.[118] In early 2017, BMRC floated tenders for an additional 150 coaches to convert all trains to 6 coach trains on the two Phase 1 routes.[119] On 27 March 2017, BEML announced that it had won an ₹1,421 crore contract to supply the coaches.[120] The first six car train was introduced on the Purple Line on 23 June 2018.[121] By January 2020, all trains had been converted to six coaches.[122]
Free Wi-Fi service was made available to commuters on 31 July 2013.[123] Passengers also have emergency voice communication with train staff through a speaker system. Passengers are provided with a call button to communicate with the driver or control center during an emergency.[124]
Power supply[]
In December 2009, the ABB Group was awarded the contract to provide power solutions for the first phase of the planned metro network. ABB designed, supplied, installed and commissioned four substations that receive and distribute electricity, each rated at 66/33 kV, as well as the auxiliary and traction substations. ABB also provided an integrated network management system, or SCADA (Supervisory Control And Data Acquisition), to monitor and control the installations.[125] BMRC currently pays BESCOM ₹5.7 per unit of electricity.[126]
In 2016, BMRCL signed an agreement with CleanMax Solar to set up solar installations at Baiyapanahalli and Peenya stations. After Phase 2 of the metro is complete, CleanMax Solar will set up similar installations at the metro depots in Challaghatta, Whitefield, Kothanur and Hebbagodi. Per the agreement, CleanMax Solar will bear the cost of installation and the BMRC will pay CleanMax a rate of ₹5.5 per unit of electricity for three years. Following the three-year period, all six installations will be transferred to the BMRC. According to the BMRC director of operations NM Dhoke, "The 1.4 MW installation can generate up to 10,000 units, which help power the depot facilities. However, it is not sufficient to power the trains, but it will help us save ₹51 crore over 25 years on energy".[126]
In February 2019, Alstom was awarded a GBP 62 million contract to provide electrification systems for Phase II of the Namma Metro. The company will construct 56 substations to supply power for Phase II of the system.[127]
Signaling[]
In September 2009, the consortium led by Alstom Project India Limited was awarded a contract worth ₹563.4 crore (US$74.8 million) to supply control and signalling system for the first phase of the project. The consortium is led by Alstom and composed of Alstom Transport SA, Thales Group Portugal S A, and Sumitomo Corporation. Alstom will provide the design, manufacture, supply, installing, testing, and commissioning of the train control and signalling system and Thales will provide the design, installing, testing, and commissioning of the telecommunication system for Phase 1 of the metro system. It includes the Urbalis 200 Automatic Train Control system which will ensure optimal safety, flexible operations and heightened passenger comfort.[128][129]
The integrated control center at Baiyyappanahalli has direct communication with trains and stations are CCTV fitted with visual and audio service information.[124] Passengers have emergency voice communication with train staff.
Stations[]
There are 40 stations on the Namma Metro network. Majestic station is the largest with a total floor area of 48,000 square metres (520,000 sq ft).[130]
Initially, there were no toilets at Namma Metro stations. BMRCL eventually heeded public demand, and the metro's first toilets were opened at Baiyappanahalli and Indiranagar stations on 21 June 2013.[131] As of February 2017, there were 33 ATMs at Namma Metro stations.[132]
The 12 underground stations built during Phase II will be smaller in size than the underground stations built in Phase I to minimise land acquisition costs.[133] All Phase I underground stations were 272 meters long and 24 meters wide, except for Chickpet and K.R. Market stations which had the same width but were 240 meters long. In contrast, Phase II's underground stations are shorter at 210 meters but retain the same width.[134]
On 17 February 2017, Uber announced that it would open booking counters at 12 metro stations by the end of March 2017. The counters enable commuters to book an Uber, and is aimed at commuters who do not have access to the internet or do not have the Uber mobile app installed on their phone. Ola Cabs announced a similar arrangement on 22 February 2017.[135][136]
Depots[]
Under phase-1, two depots were built at Baiyyappanahalli and Peenya. For the line extensions in phase-2, BMRC is building additional depots at Anjanapura on the Green Line and at Challaghatta and Kadugodi for the Purple Line. For the new lines in phase-2, depots are being built at Kothanur (Pink Line) and at Hebbagodi (Yellow Line).
For the Blue Line (airport line, phase-2A), the Baiyyappanahalli depot is planned to be used[137] as two depots are being built for Purple Line at its ends. In addition, a depot is planned at Doddajala, near the Trumpet inter-change. The depot at Baiyappanahalli has an operations control center for managing the metro network and also a training center.
Depot | Line | Built | Area (Acres) | Remarks |
Baiyyappanahalli[138][139] | Purple | Phase-1 | 50 | Depot-Cum-Workshop; Operation Control Center; Metro Training Center.
Transition planned from DTG to CBTC depot (for Blue line trains)[137] |
Peenya[140][141] | Green | Phase-1 | 100 | Depot-Cum-Workshop |
Anjanapura[142] | Green | Phase-2 | 8.9 | Depot, Stabling |
Challaghatta[142][143] | Purple | Phase-2 | 47.0 | Depot-Cum-Workshop |
Hebbagodi[142] | Yellow | Phase-2 | 39.3 | Depot-Cum-Workshop |
Kothanur[144] | Pink | Phase-2 | 31.5 | Depot-Cum-Workshop |
Kadugodi[145] | Purple | Phase-2 | 44.75* | Depot-Cum-Workshop
*Land includes two stations (Channasandra & Kadugodi) |
Shettigere, Doddajala[146][147] | Blue | Phase-2B | 23.0 | In planning stage |
Vertical gardens[]
The BMRC granted permission to Hydrobloom, a start-up company, to grow hydroponic plants on the pillars of the Namma Metro. Pillars covered with plants are referred to as vertical gardens. Hydrobloom had previously developed a vertical garden on a metro pillar near Rangoli Art Centre next to the MG Road Metro station. The gardens are intended for beautification and to reduce air pollution.[148]
Safety[]
As of February 2014, BMRCL has two road-cum-rail rescue vehicles that can be used to perform evacuations or re-load derailed trains back onto the track.[149]
The trains are equipped with derailment prevention equipment, and the tracks are equipped with concrete barriers to prevent trains from leaving the viaduct. The support pillars are earthquake-proof and are designed to have a lifespan of at least 100 years. Trains are equipped with sensors to detect impending collisions, and have automatic braking systems to prevent speed limits from being exceeded.[150] In case of train stoppages midway between stations during emergencies, pavements beside tracks are provided on elevated viaducts as well as in underground sections.
Accessibility[]
Yellow tactile tiles are used at all stations to guide the visually impaired. The tiles start at the ramp and lead to the staircases and lifts.[151] Disabled and elderly passengers can avail a wheelchair at all metro stations. The wheelchair can be used by the passenger to board a train and then dropped off at the destination station.[126] In February 2017, BBMP and BMRC began a project to upgrade all footpaths along metro routes. The project is estimated to cost ₹40 crore and was scheduled to be completed in 18 months.[152][153]
Rainwater harvesting[]
BMRCL, in a public-private partnership, harvests rainwater from the viaducts on the rail system. The private partner, Karnataka Rural Infrastructure Development (KRIDL), collects the water at multiple points, treats it, and sells it in bulk as potable water.[154] Pipes inside each metro viaduct pillar carry the rainwater from the viaduct down to underground tanks located beneath the median. When these tanks overflow, the water is diverted to 5 metres deep rainwater harvesting pits. Two rainwater harvesting pits are installed between each pillar. The average distance between the two pillars is 28 meters. As of March 2017, a 33.48 km (20.80 mi) of the elevated metro is covered by the rainwater harvesting system. With the completion of Phase 2 of the metro, the BMRCL will cover a total of 58 km (36 mi) with rainwater harvesting systems.[155] Around 8 crore litres of water are expected to be collected annually.[156]
BMRCL also harvests rainwater from the 140 acres depot facility at Peenya. Water will be collected from the 190,000 sq foot roof and stored in two tanks with a capacity of 50,000 litres each. Rainwater harvesting is also planned in existing and under-construction stations. The water harvested will be supplied to places where needed, and any excess will be used for groundwater recharge.[156]
BMRC has installed a water harvesting system along Reach 1 and will be doing the same for Reaches 3 & 4. Installation of flower beds was delayed due to garbage being dumped on the median by garbage collectors, BMRC will also set up flower beds on Reach 1 with assistance from the horticulture department. However, the work related to this has slowed down due to garbage contractors dumping garbage along the median, due to the lack of a waste management plan in the city.[157] BMRC also planned to rejuvenate Kengeri and Veerasandra lakes using water collected from a nearby corridor.[158][159]
Operations[]
Fare collection[]
MIFARE DESFire platform, developed by NXP Semiconductors, was selected to manage the Automated Fare Collection (AFC) for Namma Metro.[160] The system uses contactless smart tokens and contactless smart card.[161] Tokens are available only for a single journey.[48] Smart cards can be used for multiple journeys.[48] There is currently one type of smart card available on the metro – Varshik.[162]
- Varshik is priced at ₹50, with ₹50 as a user deposit. It is valid for a year, and provides a 5% discount on fares.[163] The card can be recharged.
- Saral was available for ₹70. It permitted one day's travel on BMTC non-air-conditioned buses and on the metro. Saral is no longer available.
- Saraag was available for ₹110. It permitted one day's travel on BMTC air-conditioned buses and on the metro.[164] Saraag is no longer available.
- Sanchar was available in denominations of ₹10, ₹40, ₹50 and ₹100. Sanchar was withdrawn from 1 March 2017.[165][166]
BMRCL began selling tokens through automatic ticket vending machines (ATVMs) on 4 December 2012 at MG Road, Indiranagar and Baiyyappanahalli stations. The service will eventually be expanded to all metro stations. The touchscreen-enabled ATVMs are available in 3 languages – English, Kannada, and Hindi. Commuters can purchase a single journey token by selecting the destination station or the amount in the ATVM. They can also add value or add trips to the contactless smart card. Commuters can purchase up to 8 tickets at a time and can get the receipt printer for card recharge. ATVMs accept coins of ₹5 and ₹10 denominations and ₹10, 20, 50, 100, 500 denominations of currency notes. However, the ATVM cannot differentiate between ₹1 and ₹2 coins.[167][168]
In November 2016, BMRC began accepting online payments to recharge smart cards. Tickets cannot be purchased online.[169]
Approximately 68% of passengers on the metro use smart tokens and 32% use smart cards.[115]
Frequency[]
The metro service runs between 05:00 and 23:00 hours. The service starts at 07:00 hours on Sundays. There are trains every 8 minutes between 08:00 and 20:00, and every 10 minutes at other times.[170] On weekdays, trains operate at 4-minute intervals between 09:00 and 10:00.[171] The headway is slated to decrease to once every three minutes after completion of Phase I.[126] The end-to-end travel time on the Purple Line is 35 minutes, and on the Green Line 45 minutes.[172]
Metro services have occasionally operated beyond 2300 hours. Services are usually extended on festival days or when an international cricket match is held in the city.[173][174]
Ridership[]
The Purple Line's Reach-1 of 6.7 km was the first to open during October 2011. On the first 3 days of operations of Reach-1, 169,019 people rode the metro.[47] At the end of the 4th day, about 200,000 passengers had already commuted on Namma Metro. During the first month since opening of Reach-1, about 1,325,000 people had travelled by metro. Thus, on average, 41,390 people took the train each day during the first month. However, the average ridership during the first six months of operation dipped down to 24,968.[117]
The northern section of Green Line (Reach 3,3A - 9.9 km) opened during March 2014. About 25,000 passengers travelled on the northern section on the opening day.[20] In the first month of operations of the Green Line stretch, 762,000 people used the line, at a daily average of 24,605.
Reach-1, Reach-3/3A and Reach-2 (opened during November 2015) operated independently until the east–west underground section of Purple Line (connecting Reaches 1 and 2) was opened during April 2016. Once the east and west reaches were inter-connected with the intermediate underground section of Purple line, ridership surged hugely to nearly 100,000 a day on the line in the first few days.[175] After the north–south underground section was opened (simultaneously with the elevated reaches 4,4A in the south), the network provided connectivity in all four directions with interchange between the lines and this increased ridership further, reaching between 350,000 and 360,000 on average by December 2017.[176]
As ridership kept growing, overcrowding became a serious concern. Hence, 3-coach trains were converted to 6 coaches. The first six car train was introduced on the Purple Line on 23 June 2018. By January 2020, all trains had been converted to six coaches.[126]
During 2019–20, the annual ridership was 174.22 million (average during the year was thus 477,315). The maximum daily ridership of 601,164 was on 25 October 2019 while the highest daily revenue of Rs.1.67 crore was on 2 March 2020. During January 2020, ridership averaged 518,074.[6]
Due to Covid pandemic, services were halted from 25 March 2020 onwards. Operations resumed on 7 September 2020.[177] During the second wave, operations were again halted from 27 April 2021 to 20 June 2021.[178] Services remained limited throughout the pandemic period and ridership was low due to enforcement of constrained capacity and social distancing norms, as stipulated by the state government.
Speed[]
The system is designed for a maximum train speed of 80 km/h (50 mph). However, the Research Design and Standards Organization (RDSO) fixed the speed at which trains are allowed to operate commercially as 67.50 km/h (41.94 mph) on straight sections, 35 km/h (22 mph) on curves, and 45 km/h (28 mph) in stations.[179]
Security[]
The Karnataka State Industrial Security Force (KISF) is responsible for security on the Namma Metro.[180] Bangalore Police conducted detailed mock drills at metro stations for the first time on 25 March 2017. Police officials stated that the drill was to assess readiness to deal with situations such as hoax bomb calls, terrorist infiltration, or attacks. Sniffer dogs, bomb detection and disposal squad, anti-sabotage squad, and Quick Reaction Teams (QRTs) were involved in the drill. Police had previously conducted basic mock drills, but this was the first one aimed toward dealing with specific threats. The chosen day was a Saturday, when crowds are usually larger, in order to make the drill more challenging for officers. The BMRCL has not informed of the drill in advance.[181]
Laws[]
The Bangalore Metro Rail (Carriage and Ticket) Rules 2011 limit the weight of personal baggage to 15 kg. Rule 3 says: "No person shall, while traveling in metro railway, carry with him any goods other than small baggage containing personal belongings not exceeding 60cm x 45cm x 25cm in size and 15kg in weight, except with the prior approval of the metro railway administration." The rules also prohibit carrying explosive, inflammable, and poisonous substances.[182]
The Metro Railway (Operation and Maintenance) Act, 2002, imposes fines and in some cases jail sentences for offences committed on the metro.[citation needed] Anyone indulging in sabotaging the train or maliciously hurting or attempting to hurt other passengers while travelling in the metro can face imprisonment for up to 10 years. Pasting posters or drawing graffiti on the walls of stations or trains is punishable by a fine of ₹1,000 or imprisonment for up to 6 months. Traveling in an inebriated state or creating nuisance in the train is punishable by a ₹500 fine.[183] Passengers are monitored at security checkpoints and those that are causing trouble, heavily drunk, or carrying forbidden items are not permitted to board.[184] Spitting on the metro premises is punishable by a fine of ₹100.[185]
Mobile app[]
The BMRCL launched a Namma Metro app for Android devices in 2013. However, it had limited features.[186] The app was officially re-launched on 4 November 2016 with additional features.[187] The app was developed by the Centre for Development of Advanced Computing (CDAC). The app allows users to purchase and recharge smart cards, locate nearby metro stations and also provides information related to parking, train frequency, route map, and fare details.[126][188]
Expansion[]
Phase 3[]
A 127 km (79 mi) Phase 3 was proposed in May 2016.[189] Phase-3 was to include two semicircular halves covering the eastern and western semi-circles of Outer Ring Road (ORR). A 33 km (21 mi) line was proposed to cover the eastern portion of ORR from Silk Board to Hebbal, while a 31.37 km (19.49 mi) line was to cover the western portion of ORR. A 21.31 km (13.24 mi) line linking Hosakerehalli to ORR at Marathahalli, passing through Old Airport Road was proposed to serve the areas of Domlur, Konena Agrahara and HAL. Another 33 km line was from Carmelaram (Sarjapur Road) to Yelahanka, passing through Central College, Palace Guttahalli, Mehkri Circle and Hebbal. Another shorter line of 8.89 km (5.52 mi) line was proposed from Nice Road to Toll Gate (Magadi Road). Extension of the Red line (later renamed Pink line) to airport was also part of the third phase. Some lines and sections that were proposed above for Phase 3 were included in Phase 2 as Phase 2A and Phase 2B.
In April 2019, plans for Phase 3 were revised and two key trunk lines cutting through the city were dropped. The revised plan had five lines totaling 83.02 km.[190] Two lines were proposed in north Bengaluru connecting KIADB Aerospace Park to Nagawara (25 km) and between Kogilu Cross and Rajankunte (10 km). Other proposed lines were from Hebbal to Jaya Prakash Nagara (31.37 km) and a 13-km line between Ibluru and Carmelaram. The revised plan was heavily criticized by the general public because all lines were planned on the outskirts of the city, while the lines originally proposed had included lines that would pass through important areas within the city.[191][192]
In December 2019, BMRCL unveiled a Comprehensive Mobility Plan (CMP) with further changes that included metro-lite lines, as detailed on table below. This was again criticized by the public as the CMP included elevated roads and again omitted the two key trunk routes cutting through the city.[193][194]
Comprehensive Mobility Plan (2019) | Length |
---|---|
ORR West Line (Orange Line) | 30 km |
Magadi Road Toll gate-Kadabgere (Metrolite-Elevated) | 13 km |
Whitefield–Domlur Line (Metrolite-Elevated /MRT) | 16 km |
Katamanallur Gate–Sarjapura Road–Hebbal (Metrolite-Elevated /MRT) | 52 km |
Inner Ring Metro (UG) | 34 km |
Total | 145 km |
BMRCL stated that they would name the ORR-west line as Orange line.[195] In March 2020, chief minister BS Yediyurappa declared in his budget speech that the Outer Ring Road-West Metro and Magadi Road-Metrolite line would be developed on public-private partnership mode (PPP).[196] Later in October 2021, BMRCL completed the road report planning and announced that two new corridors were set to emerge in west Bengaluru. The first corridor is set to follow the ring road from JP Nagar Phase 4 to Kempapura in Hebbal, thus connecting with the Blue Line. The second corridor will emerge from Hosahalli Toll and end in Kadabagere. The projected completion date of these new lines which have been color coded as Orange Lines are said to be around 2027-28.[197] After the new plans were announced, it appeared that Hoskerehalli-Marathahalli and Sarjapura Road-Yelahanka lines, which were part of the initial report were dropped.[198]
Livery | Line | Terminals | Length | New stations | Projected completion |
---|---|---|---|---|---|
Orange Line | JP Nagar Phase 4 – Kempapura | 31 km | 22 | 2028 [197] | |
Hosahalli – Kadabagere | 11 km | 11 | 2028 [197] |
In popular culture[]
Several films and commercials have been shot on the Namma Metro premises. The BMRCL charges ₹50,000 (US$660) for shooting inside a metro station, and ₹40,000 (US$530) for shoots inside a metro train during peak hours between 6 am to 10 pm. During non-peak hours, from 10 pm to 4 am, the agency charges ₹50,000 (US$660) for shoots inside metro stations and ₹20,000 (US$270) inside a train. The film producers must also make a security deposit of ₹5 lakh (US$6,600), as insurance for the metro property. Film shoots are permitted during three slots – 6 to 8 am, 12 pm to 2 pm, and 9 to 11 pm. Kannada films can avail lower rates.[199]
The first film to shoot on Namma Metro was the Kannada Blockbuster Ugramm in 2013. Later many other Kannada movies including 2015 film Rana Vikrama starring Puneeth Rajkumar and Adah Sharma, were shot using Namma Metro's facilities.[200]
The 2012 Malayalam film 22 Female Kottayam also has a song sequence shot in the Namma Metro coach.
In December 2016, Tamil film Imaikkaa Nodigal became the first film to shoot scenes inside the tunnel stretch of the Purple Line. According to BMRC officials, prior to this film, one Kannada film, one Telugu film and several commercials had been shot on the Namma Metro premises.[199]
In February 2017 a mobile game based on Namma Metro was released. It is called the Bangalore Metro Simulator 2017, which includes users to drive both Purple Line and Green Line.
Controversies[]
In August 2021, the Karnataka government requested large corporations with offices on the Outer Ring Road (ORR) to consider extending work from home (WFH) to their employees till the end of December 2022 to keep the road traffic in check during the soon-to-be initiated Metro rail construction on the stretch from Silk Board to KR Puram.[201] Due to questions raised by IT companies and employees awaiting return to their offices, having been forced to work from home for past 18 months due to COVID-19, the government issued a clarification that it was not mandatory.[202]
Network Map[]
See also[]
- Namma Metro Lines
- Purple Line
- Green Line
- Yellow Line
- Pink Line
- Blue Line
- Orange Line
- List of Namma Metro stations
- Rapid transit in India
- Rangoli Metro Art Center
- List of metro systems in India
- List of metro systems
- Urban rail transit in India
References[]
- ^ "Metro Phase I Will be Ready by May, to Miss Deadline". The New Indian Express. 22 October 2015.
- ^ a b "BMRCL Annual Report 2019-20" (PDF).
- ^ "At 4.58 lakh passengers, Namma Metro records highest ridership on Friday - newindianexpress". The New Indian Express. Retrieved 1 September 2019.
- ^ "Passengers welcome higher Namma Metro frequency - KARNATAKA". The Hindu. 28 February 2017. Retrieved 14 January 2018.
- ^ a b "South India's first underground Metro launch on April 29". The Times of India. Retrieved 26 April 2016.
- ^ a b c "Namma Metro". english.bmrc.co.in. Retrieved 2 September 2020.
- ^ Correspondent, Special. "Namma Metro fares hiked, timings extended". The Hindu. Retrieved 20 June 2017.
- ^ "All 42 trains now have 6 coaches commuters want better frequency".
- ^ a b c d "WB Report on Transport" (PDF).
- ^ "Namma metro to chug on October 20". IBN Live. 1 October 2011. Archived from the original on 3 October 2011. Retrieved 21 October 2011.
- ^ "Namma Metro inaugurated in Bangalore". Railway Gazette International. 24 October 2011. Retrieved 5 June 2015.
- ^ a b "Underground metro will be ready to take commuters in 15 days: K J George". The Times of India. 19 April 2016. Retrieved 19 April 2016.
- ^ a b "Project Highlights". Official webpage of B.M.R.C. Archived from the original on 25 October 2011. Retrieved 3 May 2010.
- ^ a b "Schematic Route Map". Bengaluru Metro Rail Corporation Limited. Archived from the original on 14 August 2015. Retrieved 5 June 2015.
- ^ "Sampige Road-Peenya Metro Line Inaugurated". The New Indian Express. 1 March 2014. Retrieved 5 June 2015.
- ^ a b c d "25,000 ride Green line Metro on 1st working day". Deccan Herald. 3 March 2014. Retrieved 5 June 2015.
- ^ "Rajajinagar, Peenya residents can smile". The Times of India. 28 November 2011. Archived from the original on 15 July 2012.
- ^ a b "Metro Reach 3B to be opened on May 1". Deccan Herald. 24 April 2015. Retrieved 5 June 2015.
- ^ a b "Reach 3B of Metro rail flagged off". The Hindu. 1 May 2015. Retrieved 5 June 2015.
- ^ a b "A closer look at Namma Metro that can transform Bengaluru's mobility landscape". The Economic Times. 9 June 2017. Retrieved 9 June 2017.
- ^ "Bengaluru Metro Rarely Met Deadlines Expect no Surprise in April 2017". The Economic Times. 23 March 2017. Retrieved 12 April 2017.
- ^ 17 Jun, TIMESOFINDIA COM /; 2017; Ist, 18:27. "Namma Metro: President Pranab Mukherjee inaugurates Bengaluru Namma Metro | India News - Times of India". The Times of India. Retrieved 3 September 2020.CS1 maint: numeric names: authors list (link)
- ^ Menezes, Naveen. "President Pranab Mukherjee inaugurates Rs 13,854 crore Namma Metro project". The Economic Times. Retrieved 3 September 2020.
- ^ Lalitha, S (14 January 2021). "First line of Bangalore Metro's Phase-2 flagged off". The New Indian Express. Retrieved 14 January 2021.
- ^ a b "Namma Metro: Metro Network". Bangalore Metro Rail Corporation Limited. Archived from the original on 14 August 2015. Retrieved 5 June 2015.
- ^ NewsKarnataka (19 November 2015). "Namma Metro takes its first ride on Mysuru Road". NewsKarnataka. Retrieved 12 September 2020.
- ^ a b c "All of Bangalore Metro Phase-1 will be up and running from June 18". The New Indian Express. Retrieved 15 June 2017.
- ^ Agarwal, Anshu (16 January 2021). "Namma Metro extends its service on Green Line". The Hindu. Retrieved 16 January 2021.
- ^ "PM lays foundation stone for Bangalore Metro Rail Project". Zee News. 24 June 2006. Retrieved 2 September 2020.
- ^ "NEC loses 25% of Namma Metro contract". The New Indian Express. Retrieved 2 September 2020.
- ^ "Bangalore Metro seeks Rs 1,763 cr for extension work". The Financial Express. 17 July 2008. Retrieved 2 September 2020.
- ^ a b Shah, Narendra (20 August 2015). "Bangalore Metro|BMRC Ex-Chiefs unite against Sreedharan's view". Metro Rail News. Retrieved 2 September 2020.
- ^ "A majestic prospect – tunnelling the Bangalore metro". Railway Technology. 17 August 2011. Retrieved 2 September 2020.
- ^ "Bangalore Metro TBMs inaugurated". tunneltalk.com. Retrieved 8 September 2020.
- ^ "Helen, Margarita to resume Metro tunneling work soon". Deccan Herald. 1 May 2012. Retrieved 2 September 2020.
- ^ N, Shree D. (11 March 2016). "When is Namma Metro Phase-I expected to complete realistically?". Citizen Matters, Bengaluru. Retrieved 2 September 2020.
- ^ "Tunnelling for Bengaluru Metro tougher than anywhere in the world, says official". Deccan Herald. 5 May 2016. Retrieved 2 September 2020.
- ^ 21 Apr, Aparajita Ray / TNN /; 2015; Ist, 04:00. "Metro's tunnel borer to get its teeth again | Bengaluru News - Times of India". The Times of India. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "What you need to know about Bengaluru's new metro line". thenewsminute.com. 14 June 2017. Retrieved 2 September 2020.
- ^ "Bangalore Metro misses deadline for 4th time, minister sets Sept 26 as next date : South, News". India Today. 16 September 2011. Retrieved 8 September 2014.
- ^ "Bangalore Metro | Namma Metro". Karnataka.com. 20 October 2011. Retrieved 2 September 2020.
- ^ "Metro comes to Bangalore finally". The Times of India. 20 October 2011. Archived from the original on 20 October 2011.
- ^ "Revenue Services Report" (PDF). Archived from the original (PDF) on 24 June 2013.
- ^ Madhumathi D.S. "Business Line : Industry & Economy / Logistics : Namma Metro rides on 'gawk' power". Business Line. Retrieved 3 January 2012.
- ^ Special Correspondent (28 February 2014). "CM in a hurry, delays Namma Metro launch". The Hindu. Retrieved 27 March 2014.
- ^ "Byappanahallimg road metro stretch more popular". The Hindu.
- ^ a b "At 4.58 lakh passengers, Namma Metro records highest ridership on Friday". The New Indian Express. Retrieved 2 September 2020.
- ^ a b c d "Bangalore Metro Rail Project Phase 2" (PDF). bmrc.co.in. BMRC. Archived from the original (PDF) on 12 April 2015. Retrieved 5 June 2015.
- ^ 21 Mar, Kushala SKushala S. / Updated; 2015; Ist, 04:00. "Metro Phase-I cost is now Rs 13,845 crore". Bangalore Mirror. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ 20 Apr, Bangalore Mirror Bureau / Updated; 2016; Ist, 02:00. "Godavari sees light". Bangalore Mirror. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "Getting Bangalore Metro north-south line back on track". tunneltalk.com. Retrieved 2 September 2020.
- ^ Menezes, Naveen. "Cost and & time overrun marks Bengaluru metro phase-I". The Economic Times. Retrieved 2 September 2020.
- ^ "State Cabinet approves phase-II of metro". Business Standard. 4 January 2012. Retrieved 6 March 2012.
- ^ "Metro project: Cabinet approves two new lines for Phase 2". The Times of India. 4 January 2012. Archived from the original on 28 September 2013.
- ^ "Cabinet clears Namma Metro Phase 2 – Bangalore – DNA". Daily News and Analysis. 4 January 2012. Retrieved 6 March 2012.
- ^ IRJ (30 January 2014). "Go-ahead for Bangalore metro phase 2".
- ^ "Cities / Bangalore : Frame policy for differential fare pricing, BMRCL told". The Hindu. Chennai, India. 22 February 2012. Retrieved 6 March 2012.
- ^ "Underground Bengaluru Metro Station service flagged off, Siddaramaiah seeks Centre's help for Namma Metro phase III | Latest News & Updates at Daily News & Analysis". dna. 29 April 2016. Retrieved 29 April 2016.
- ^ "Namma Metro Phase 2 will now cost Rs 32,000 crore: Deputy Chief Minister G Parameshwara". The New Indian Express. Retrieved 24 January 2019.
- ^ "Metro gets poll push for Phase II". Deccan Chronicle. 4 June 2013. Retrieved 28 September 2013.
- ^ "All new Namma Metro stations in Phase II may get bus bays | Bengaluru News - Times of India". The Times of India.
- ^ "Metro Phase 2 will be bigger, better, says BMRCL chief". Deccan Herald. 23 December 2016. Retrieved 13 January 2017.
- ^ Menezes, Naveen. "Bengaluru Metro phase 2 land acquisition on track – The Economic Times". The Economic Times. Retrieved 13 April 2017.
- ^ "IL&FS Engg bags Bangalore Metro contract worth Rs 327 cr". Business Standard India. 24 April 2015. Retrieved 2 September 2020.
- ^ "NCC ltd emerges lowest bidder for bangalore metros 6.9km extension to Anjanapura". Retrieved 2 September 2020 – via Twitter.[non-primary source needed]
- ^ "BMRCL invites bids for 3-km extension from Nagasandra". Deccan Herald. 13 October 2016. Retrieved 2 September 2020.
- ^ a b "ITD-Cemindia JV emerges L1 bidder for four packages of Bangalore Metro". projectstoday.com. Retrieved 2 September 2020.
- ^ "HCC-URCC JV bags Bangalore Metro contract worth Rs 789 crore". indiainfoline.com. Retrieved 2 September 2020.
- ^ Menezes, Naveen. "Simplex Infrastructures quotes lowest to build metro stretch on Bannerghatta Road". The Economic Times. Retrieved 2 September 2020.
- ^ "Bangalore Metro bids for Phase II". tunneltalk.com. Retrieved 2 September 2020.
- ^ Menezes, Naveen. "High cost forces BMRCL to cancel underground tenders". The Economic Times. Retrieved 2 September 2020.
- ^ Menezes, Naveen. "Vellara Junction-Pottery Town metro underground work to start in 6 months". The Economic Times. Retrieved 2 September 2020.
- ^ "Bangalore Metro Phase II moves ahead". tunneltalk.com. Retrieved 2 September 2020.
- ^ Shah, Narendra (26 September 2019). "ITD Cementation bags Rs. 1549 cr contract from BMRCL". Metro Rail News. Retrieved 2 September 2020.
- ^ Sarim. "BMRCL awarding 14-km metro contracts to ITD & Afcons". nbmcw.com. Retrieved 2 September 2020.
- ^ Sarim. "L&T launches tunneling works for Bangalore metro". nbmcw.com. Retrieved 2 September 2020.
- ^ "Bengaluru: Metro underground tunnel work on Cantonment, Tannery Road stations begins". daijiworld.com. Retrieved 2 September 2020.
- ^ "Metro line from Silk Board to KR Puram to be fast-tracked". The Times of India. Retrieved 18 September 2016.
- ^ "Metro link to Outer Ring Road: BMRC unveils DPR, invites suggestions". The Times of India. Retrieved 17 February 2017.
- ^ Correspondent, Special. "Karnataka Cabinet approves ORR metro line". The Hindu. Retrieved 2 March 2017.
- ^ 17 Dec, Christin Mathew Philip / TNN / Updated; 2018; Ist, 08:55. "Bangalore: Setback for techies as BMRCL cancels ORR project tender | Bengaluru News - Times of India". The Times of India. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "Namma Metro ORR line tender receives 14 bids". The New Indian Express. Retrieved 2 September 2020.
- ^ Singh, Neha (20 March 2020). "Namma Metro Outer Ring Road line tender receives 14 bids". Metro Rail News. Retrieved 2 September 2020.
- ^ Ramesh, B. S. (6 October 2010). "SPV for high-speed rail link". The Hindu. ISSN 0971-751X. Retrieved 2 September 2020.
- ^ "DPR for Metro link to BIA in five months". Deccan Herald. 3 November 2012. Retrieved 8 October 2020.
- ^ "Bangalore Metro Rail yet to decide on route for Airport Line".
- ^ "Now, suggest a Namma Metro route to the airport". Deccan Herald. 15 September 2016. Retrieved 2 September 2020.
- ^ "Central funding brightens prospects of metro line to Bengaluru airport". The Hindu. Special Correspondent. 14 January 2017. ISSN 0971-751X. Retrieved 2 September 2020.CS1 maint: others (link)
- ^ 7 Dec, Suchith KidiyoorSuchith Kidiyoor / Updated; 2016; Ist, 12:28. "Bengaluru wants KIA Metro line via Nagawara". Bangalore Mirror. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "Bengaluru Metro airport line to now run through Hebbal". The New Indian Express. Retrieved 2 September 2020.
- ^ "Govt finalises KIA metro link route". Deccan Herald. 13 May 2017. Retrieved 2 September 2020.
- ^ "Airport Metro line gets one station but loses another". Deccan Herald. 25 July 2019. Retrieved 2 September 2020.
- ^ 11 Jan, TNN /; 2019; Ist, 07:58. "Karnataka government clears suburban rail project, Metro to airport | Bengaluru News - Times of India". The Times of India. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "Huge relief in sight for techies, flyers as Centre clears ORR-Airport Line for Bengaluru". The New Indian Express. Retrieved 21 April 2021.
- ^ Sep 22, Christin Mathew Philip / TNN / Updated; 2021; Ist, 19:47. "Complete Bengaluru Metro Phase 2 by 2024: Karnataka CM Basavaraj Bommai | Bengaluru News - Times of India". The Times of India. Retrieved 24 September 2021.CS1 maint: numeric names: authors list (link)
- ^ "How COVID-19 will impact already delayed metro projects in Bengaluru". thenewsminute.com. Retrieved 2 September 2020.
- ^ Aug 22, TNN / Updated; 2021; Ist, 06:31. "Bengaluru: All Purple Line trains to run up to Kengeri only during peak hours | Bengaluru News - Times of India". The Times of India. Retrieved 22 August 2021.CS1 maint: numeric names: authors list (link)
- ^ a b "Cost and & time overrun marks Bengaluru metro phase-I – The Economic Times". The Economic Times. Retrieved 9 March 2017.
- ^ a b c "Metro June Deadline Stands, But With Rider". The New Indian Express. Retrieved 27 April 2016.
- ^ "B'lore Metro to raise Rs 300 cr via bond issue". Business Standard. 11 June 2013. Retrieved 28 September 2013.
- ^ "BMRC proves merit in investment ratings". The Times of India. Archived from the original on 30 September 2013.
- ^ "BMRCL defers issue of bonds citing market volatility". The Hindu. Chennai, India. 4 August 2013.
- ^ "Admin approval for Namma Metro Phase 2 – South India – Karnataka – ibnlive". Ibnlive.in.com. Archived from the original on 10 July 2012. Retrieved 6 March 2012.
- ^ a b c Lalitha, S. (6 February 2017). "European Bank's Rs 3.7k crore fillip for Metro Phase-II". The New Indian Express. Retrieved 10 February 2017.
- ^ Bangalore, DHNS (17 October 2012). "Centre's nod awaited to extend Metro to Bengaluru Intl Airport". Deccan Herald. Retrieved 4 March 2013.
- ^ "Bangalore Metro gets $250 mn ADB loan". Business Standard. 28 March 2012. Retrieved 25 July 2012.
- ^ "Funding for Phase II". The Hindu. Retrieved 13 January 2017.
- ^ "Rs 3,700-cr loan likely for Nagawara-Gottigere line". Deccan Herald. Retrieved 11 May 2017.
- ^ Briginshaw, David. "India seeks EIB loan for Bangalore metro Line 4". International Rail Journal. Retrieved 2 March 2017.
- ^ "Biocon, Infy to Adopt Two Metro Stations – ETtech". ETtech.com. Retrieved 18 May 2017.
- ^ "Namma Metro: BMRCL Inks $500 Million Funding Deal With ADB For Under Construction ORR Metro, Achieves Financial Closure For Rs.14,844 Cr Project". in.news.yahoo.com. Retrieved 20 August 2021.
- ^ "13.25 lakh rode the Metro". The Times of India. 25 November 2011. Archived from the original on 15 July 2012.
- ^ "Namma Metro gains momentum – southindia – Bangalore – ibnlive". Ibnlive.in.com. Archived from the original on 23 November 2011. Retrieved 3 January 2012.
- ^ "Joyrides in Bangalore Metro are over – Bangalore – DNA". Daily News and Analysis. Retrieved 25 July 2012.
- ^ a b "Bangalore Metro posts Rs 41 lakh profit in first year – Bangalore – DNA". Daily News and Analysis. 18 October 2012. Retrieved 18 October 2012.
- ^ Staff Reporter (20 October 2016). "Metro to complete 5 years of operations". The Hindu. Retrieved 2 November 2016.
- ^ a b "Bangalore Metro Route Map 2020: Station List, Fare, Timings". indiametrorail.com. Retrieved 30 May 2020.
- ^ "Railway Gazette: Bangalore metro trial". Retrieved 13 February 2011.
- ^ Bengaluru, DHNS (4 February 2017). "Metro Phase 1 set to meet April deadline". Deccan Herald. Retrieved 11 February 2017.
- ^ "BEML wins Rs 1,421-cr contract from Bangalore Metro". Business Line. 27 March 2017. Retrieved 28 March 2017.
- ^ "Second six-coach Namma Metro train flagged off - Times of India". The Times of India. Retrieved 24 January 2019.
- ^ 29 Jan, Christin Mathew Philip / TNN / Updated; 2020; Ist, 23:19. "All 42 metro trains now have 6 coaches, says BMRCL; passengers want better frequency | Bengaluru News - Times of India". The Times of India. Retrieved 6 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "Bangalore Metro goes wi-fi". Deccan Chronicle. 1 August 2013. Retrieved 28 September 2013.
- ^ a b "NAMMA-METRO-IS-A-GEEK-TRAIN". The Times of India. 16 October 2011. Retrieved 21 October 2011.
- ^ "ABB wins $115 million order to power Bangalore metro". The ABB Group. Retrieved 1 January 2010.
- ^ a b c d e f "BMRC hoping to finish work on Sampige Road-Puttenahalli line ahead of April 2017 deadline". The Times of India. Retrieved 5 November 2016.
- ^ Songer, Dave. "Alstom signs £62-million deal with Bangalore Metro for electrification of Phase II". smartrailworld.com. Retrieved 26 April 2019.
- ^ "Alstom will provide train control and signalling system for the new Bangalore metro network in India". Alstom. Retrieved 2 October 2011.[dead link]
- ^ "Alstom-led consortium in pact with Bangalore Metro". Business Standard. 18 September 2009. Retrieved 3 May 2010.
- ^ "2,240 workers worked day in, day out to build India's largest metro station". Bangalore Mirror. Retrieved 27 April 2016.
- ^ "At Metro, wanna pee? Pay Rs 3 – Bangalore – DNA". Daily News and Analysis. Retrieved 28 September 2013.
- ^ Staff Reporter (21 February 2017). "Metro stations to get more ATMs". The Hindu. Retrieved 21 February 2017.
- ^ "Why Namma Metro stations under Phase 2 will be smaller than Bengaluru Metro Phase 1". The Financial Express. 16 April 2019. Retrieved 4 May 2019.
- ^ "Bengaluru Metro Phase-II: Underground stations will be smaller". The New Indian Express. Retrieved 4 May 2019.
- ^ "Bengaluru: Cab aggregator booking kiosks at Metro stations soon". Deccan Chronicle. 23 February 2017. Retrieved 23 February 2017.
- ^ KJ, Shashidhar (23 February 2017). "Ola will set up kiosks for cab booking at Bangalore metro stations". MediaNama. Retrieved 23 February 2017.
- ^ a b "DPR Silkboard-KRPuram-Airport Line" (PDF).
- ^ Sastry, Anil Kumar (2 May 2012). "Behind the scenes of Namma Metro". The Hindu. ISSN 0971-751X. Retrieved 7 September 2020.
- ^ "Bangalore Metro Rail Training Institute goes global; companies based in US & UK nominate staff for training – RailNews Media India Ltd". Retrieved 7 September 2020.
- ^ Menezes, Naveen. "Namma Metro looks to bolster revenue, may exploit space in phase II depots for commercial use". The Economic Times. Retrieved 7 September 2020.
- ^ 22 Oct, Senthalir S. / TNN /; 2010; Ist, 05:21. "BMRC spent '533 crore only to acquire land | Bengaluru News - Times of India". The Times of India. Retrieved 7 September 2020.CS1 maint: numeric names: authors list (link)
- ^ a b c 18 Mar, Christin Mathew Philip / TNN / Updated; 2019; Ist, 10:18. "Namma Metro News: Decks cleared for Namma Metro's Phase 2 depots | Bengaluru News - Times of India". The Times of India. Retrieved 7 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "Ground-level elevated metro depot at Bengaluru's Challaghatta to save Rs 400 crore". The New Indian Express. Retrieved 16 December 2021.
- ^ 23 May, ByNaveen MenezesNaveen Menezes / Updated; 2020; Ist, 06:00. "Noida-based firm is lowest bidder for Kothanur depot". Bangalore Mirror. Retrieved 7 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "BMRCL likely to get Kadugodi forest land in a month". Deccan Herald. 2 August 2019. Retrieved 7 September 2020.
- ^ "Tenders called for three packages for Metro's Airport Line". The New Indian Express. Retrieved 7 September 2020.
- ^ "Bengaluru's Airport Metro dream on track, Shettigere to house depot". www.timesnownews.com. Retrieved 20 August 2021.
- ^ "Metro pillars a vertical garden – Bangalore Mirror -". Bangalore Mirror. Retrieved 10 March 2017.
- ^ Special Correspondent (24 February 2014). "BMRCL launches road-cum-rail vehicle for rescue operations". The Hindu. Retrieved 29 August 2015.
- ^ "'We've taken steps to ensure public safety'". The Times of India. 28 October 2011.
- ^ G. Ananthakrishnan (14 January 2013). "Linking modes of commute". The Hindu. Chennai, India. Retrieved 4 March 2013.
- ^ "Sidewalks under Metro corridors to get a facelift". The Times of India. Retrieved 10 February 2017.
- ^ "Footpaths along 40-km Metro corridors to get facelift". Deccan Herald. 9 February 2017. Retrieved 10 February 2017.
- ^ "'Liquid' cash from viaduct". The Hindu. Chennai, India. 15 December 2011.
- ^ "Metro will extend rainwater harvesting project to Phase 2". Deccan Herald. 22 March 2017. Retrieved 24 March 2017.
- ^ a b Francis, Merlin (2 April 2012). "Namma Metro gets waterwise". DNA India. Bangalore, India. Retrieved 24 June 2012.
- ^ "Metro medians turn garbage dumps". The Times of India. 6 August 2012. Archived from the original on 26 January 2013.
- ^ "Lakes to come alive along Metro path". The Times of India. 4 November 2012. Archived from the original on 3 January 2013. Retrieved 4 March 2013.
- ^ "BMRCL plans to rejuvenate lakes, starting with Kengeri – Bangalore – DNA". Daily News and Analysis. 4 November 2012. Retrieved 4 March 2013.
- ^ "Bengaluru Metro System Adopts NXP's MIFARE Technology". MarketWatch. 23 January 2012. Archived from the original on 25 January 2012. Retrieved 13 January 2017.
- ^ "Bangalore Metro: Recharge and ride on". The Times of India. 1 January 1970. Retrieved 21 October 2011.
- ^ "Cities / Bangalore : 20,000 smart cards sold for metro ride". The Hindu. Chennai, India. 17 October 2011. Retrieved 21 October 2011.
- ^ "Namma Metro". english.bmrc.co.in. Retrieved 17 December 2018.
- ^ "20,000 smart cards sold for metro ride". The Hindu. 17 October 2011. Retrieved 8 September 2014.
- ^ ReporterBengaluru, Staff (28 February 2017). "Namma Metro withdraws Sanchar tickets". The Hindu. Retrieved 2 March 2017.
- ^ "BMRC withdraws cheaper trip tickets, commuters fume". The Times of India. Retrieved 2 March 2017.
- ^ Bangalore, DHNS (3 December 2012). "Automatic ticket vending at Metro stations". Deccan Herald. Retrieved 4 March 2013.
- ^ "Yeshwantpur Metro link work picks up pace". The Times of India. 5 December 2012. Archived from the original on 26 January 2013. Retrieved 4 March 2013.
- ^ "BMRCL launches online system to top up Metro cards". Deccan Herald. 17 November 2016. Retrieved 18 November 2016.
- ^ "Namma metro may up frequency". The New Indian Express. Retrieved 6 June 2016.
- ^ "Metro Phase 1 set to meet April deadline". Deccan Herald. 4 February 2017. Retrieved 10 February 2017.
- ^ "Metro speed upped on Purple line". Deccan Herald. 24 December 2016. Retrieved 13 January 2017.
- ^ Bangalore, DHNS (22 December 2012). "Bar timings relaxed for revellers". Deccan Herald. Retrieved 6 June 2013.
- ^ "Metro to run till midnight today, tomorrow". The Times of India. 24 December 2012. Archived from the original on 26 January 2013. Retrieved 6 June 2013.
- ^ Service, Indo-Asian News (2 May 2016). "Record one lakh commuters travel in Bengaluru metro on Sunday". India News, Breaking News | India.com. Retrieved 23 August 2021.
- ^ "17 crore passengers have boarded Bengaluru Metro since 2011". The New Indian Express. Retrieved 23 August 2021.
- ^ "Bengaluru Metro to restart tomorrow. Here's all you need to know". Hindustan Times. 6 September 2020. Retrieved 23 August 2021.
- ^ Jun 25, TNN /; 2021; Ist, 09:45. "Bengaluru: Covid-hit Metro operator plans to raise Rs 500 crore | Bengaluru News - Times of India". The Times of India. Retrieved 23 August 2021.CS1 maint: numeric names: authors list (link)
- ^ Chethan Kumar, Bangalore, DHNS (22 May 2013). "RDSO in no hurry to allow Metro to up speed". Deccan Herald. Retrieved 6 June 2013.CS1 maint: multiple names: authors list (link)
- ^ "Namma Metro security cover to soon get a boost". The New Indian Express. Retrieved 18 March 2017.
- ^ "Mock drill at Metro stations takes passengers aback". Deccan Herald. 26 March 2017. Retrieved 26 March 2017.
- ^ "Metro gets luggage scanners". Deccan Herald. 2 December 2011.
- ^ Rohith B R, Bangalore, DHNS (18 October 2012). "Commuters' brush with etiquette on Namma Metro". Deccan Herald. Retrieved 6 June 2013.CS1 maint: multiple names: authors list (link)
- ^ "No entry for drunk commuters in Metro". Deccan Chronicle. 25 December 2012. Retrieved 6 June 2013.
- ^ "Not fine to spit in Metro". The Times of India. 11 October 2012. Archived from the original on 3 January 2013. Retrieved 6 June 2013.
- ^ "New app for Namma Metro once Phase 1 gets fully operational". Deccan Herald. 4 June 2015. Retrieved 29 August 2015.
- ^ Bengaluru: DHNS (5 November 2016). "Metro trial run between National College, Puttenahalli in 3 weeks". Deccan Herald. Retrieved 11 February 2017.
- ^ "'Unofficial' apps of govt transport corpns flood digital platform". Deccan Herald. Retrieved 2 November 2016.
- ^ "Namma Metro, a third phase in the making". Deccan Herald. 22 May 2016. Retrieved 2 September 2020.
- ^ Menezes, Naveen. "Bangalore Metro: Namma Metro phase III may make way for elevated corridor". The Economic Times. Retrieved 2 September 2020.
- ^ "Bengaluru Comprehensive Mobility Plan a 'backdoor' to elevated corridor?". thenewsminute.com. 18 January 2020. Retrieved 2 September 2020.
- ^ 20 Jan, Naveen MenezesNaveen Menezes / Updated; 2020; Ist, 06:00. "Citizens want Metro to stay off CMP, mind its own business". Bangalore Mirror. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ "Bengaluru's Draft Mobility Plan in a nutshell: Elevated corridors get Rs 18,480 crore". Citizen Matters, Bengaluru. 18 December 2019. Retrieved 2 September 2020.
- ^ 6 Jan, Bangalore Mirror Bureau / Updated; 2020; Ist, 06:00. "One-man show? BMRCL prepares 'comprehensive' mobility plan alone". Bangalore Mirror. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ 20 Nov, Christin Mathew Philip / TNN /; 2019; Ist, 09:30. "Bengaluru: Gottigere-Nagawara Metro line to go Pink | Bengaluru News - Times of India". The Times of India. Retrieved 2 September 2020.CS1 maint: numeric names: authors list (link)
- ^ Singh, Neha (7 March 2020). "BMRCL to Construct two Metrolite corridors via PPP mode". Metro Rail News. Retrieved 2 September 2020.
- ^ a b c "42 KMs Bangalore Metro Phase-3 Project will start its operation by 2027-28". Metro Rail News. 27 October 2021.
- ^ "BMRCL resumes traffic analysis to finalise Phase 3 lines". Deccan Herald. 24 November 2021.
- ^ a b "Shooting in the metro tunnel". Bangalore Mirror. Retrieved 11 December 2016.
- ^ "Puneeth Rajkumar, Adah Sharma shoot at MG Road Metro Station, Bangalore - Times of India". The Times of India.
- ^ Poovanna, Sharan (24 August 2021). "Allow WFH till Dec 2022 to help Bengaluru Metro work: K'taka govt to IT firms". www.hindustantimes.com. Hindustan Times. Retrieved 5 September 2021.
Allow WFH till Dec 2022 to help Bengaluru Metro work: K’taka govt to IT firms
- ^ "Karnataka govt retracts WFH advisory for IT companies along Bengaluru Outer Ring Road after backlash". www.firstpost.com. FP Trending. 2 September 2021. Retrieved 5 September 2021.
The government clarified its stand later. Reddy issued a new notification saying that the advisory was not mandatory and should not be treated as such.
External links[]
Wikimedia Commons has media related to Namma Metro. |
Wikivoyage has a travel guide for Bangalore. |
- Namma Metro
- Standard gauge railways in India
- 750 V DC railway electrification
- 2011 establishments in Karnataka