North–South Line (Jakarta MRT)

From Wikipedia, the free encyclopedia
North–South Line
M
MRTset12.jpg
Overview
StatusOperational (Phase 1)
Under Construction (Phase 2A)
OwnerMinistry of Transportation
LocaleJakarta, Indonesia
TerminiLebak Bulus
Bundaran HI
Stations13
Service
TypeRapid transit
SystemJakarta MRT
Services1
Operator(s)PT MRT Jakarta
Depot(s)Lebak Bulus
Ancol Barat (future)
Rolling stock16 six-car MRTJ 1000 series trainsets
History
Opened24 March 2019 (2019-03-24)
Technical
Line length15.7 km (9.8 mi)
CharacterElevated
Underground
Track gauge1,067 mm (3 ft 6 in)
Electrification1,500 V DC overhead catenary
Operating speedlimit of 100 km/h (62 mph)
Route map

Legend
↑ Phase 2 
 
Ancol Barat Depot
Jakarta KRL TP.svg
Jakarta Inner Ring Road
↑ Phase 2B
Kota
Koridor 1 Transjakarta Koridor 12 Transjakarta
Koridor 1 Transjakarta
Koridor 1 Transjakarta
Koridor 1 Transjakarta
Koridor 1 Transjakarta Koridor 2 Transjakarta Koridor 3 Transjakarta
↑ Phase 2A II: opening 2027
Thamrin
 M2  Koridor 1 Transjakarta
↑ Phase 2A I: opening 2025
BHI
Bundaran HI
Koridor 1 Transjakarta
DKA
Dukuh Atas BNI
(Jakarta LRT S.svg) Koridor 1 Transjakarta Koridor 4 Transjakarta Koridor 6 Transjakarta
Jakarta KRL A.svg BNI CityJakarta KRL L.svg Sudirman
West Flood Canal
Jakarta LRT CB.svg Jakarta LRT BK.svg
STB
Setiabudi Astra
Koridor 1 Transjakarta
BNH
Bendungan Hilir
Koridor 1 Transjakarta Koridor 9 Transjakarta
Jakarta Inner Ring Road
IST
Istora Mandiri
Koridor 1 Transjakarta
SNY
Senayan
Koridor 1 Transjakarta Koridor 4 Transjakarta
SSM
ASEAN
Koridor 1 Transjakarta
BLM
Blok M BCA
Koridor 1 Transjakarta Koridor 13 Transjakarta
BLA
Blok A
HJN
Haji Nawi
CPR
Cipete Raya
Jakarta Outer Ring Road
FTM
Fatmawati
LBB
Lebak Bulus Grab
Koridor 8 Transjakarta
Lebak Bulus Depot

The North–South line is a rapid transit line of the Jakarta MRT. Coloured red on the map, the line is currently 15.7 km long and serves 13 stations. It is the first line of the Jakarta MRT.

History[]

Jakarta MRT underground section between Dukuh Atas station and Bundaran HI, in March 2018

Phase 1[]

A total of eight contracts were awarded.

  • CP 101 (Construction of Lebak Bulus Depot, Lebak Bulus station and related elevated works) awarded to Tokyu Corporation - Wijaya Karya consortium.
  • CP 102 (Construction of Cipete Raya and Fatmawati stations and related elevated works) awarded to Tokyu Corporation - Wijaya Karya consortium.
  • CP 103 (Construction of Haji Nawi, Blok A, Block M and ASEAN stations and related elevated works) awarded to Obayashi Corporation - Shimizu Corporation - PT Jaya Konstruksi JV.
  • CP 104 (Construction of Senayan and Istora stations and related tunnelling works awarded to Shimizu Corporation - Obayashi Corporation - PT Wijaya Karya - PT Jaya Konstruksi JV.
  • CP 105 (Construction of Bendungan Hilir and Senayan stations and related tunnelling works awarded to Shimizu Corporation - Obayashi Corporation - PT Wijaya Karya - PT Jaya Konstruksi JV.
  • CP 106 (Construction of Dukuh Atas and Bundaran HI stations and related tunnelling works awarded to Sumitomo Mitsui Construction - PT Hutama Karya consortium.
  • CP 107 (Construction of railway systems and trackworks) awarded to Metro One consortium.
  • CP 108 (Construction of rolling stock) awarded to Sumitomo Corporation - Nippon Sharyo consortium.

On 1 June 2013, the first three civil contracts for the 9.2 km (5.7 mi) underground section were signed. Three civil engineering contracts for the elevated section were signed in the third quarter of 2013. Construction work began in October 2013.[1]

Tunnelling was completed on 23 February 2017, meeting the target completion date.[2] By October 2017, the construction of both elevated and underground line sections were completed.[3]

Ahead of its official opening, a limited public trial run was conducted from 12 March 2019 to 23 March 2019. The official opening ceremony was held on 24 March 2019 by the Indonesian president, Joko Widodo.[4][5]

Phase 2[]

A total of nine contracts were put up.

  • CP 200 (Construction of underground electrical substation near Monas station) awarded to PT Trocon Indah Perkasa.
  • CP 201 (Construction of Thamrin and Monas stations and related tunnelling works) awarded to Shimizu Corporation - PT Adhi Karya JV.
  • CP 202 (Construction of Harmoni, Sawah Besar and Mangga Besar stations and related tunnelling works).
  • CP 203 (Construction of Glodok and Kota stations and related tunnelling works) awarded to Sumitomo Mitsui Construction Company - PT Hutama Karya JO.
  • CP 204 (Construction of depot at Ancol Barat).
  • CP 205A (Construction of railway systems and trackworks from Bundaran HI to Mangga Besar stations).
  • CP 205B (Construction of railway systems and trackworks from Mangga Besar to Kota stations) awarded to Sumitomo Mitsui Construction Company - PT Hutama Karya JO
  • CP 206 (Construction of 14 sets of rolling stock).
  • CP 207 (Installation of Automatic Fare Collection system).

Groundbreaking for Phase 2 was initially planned to begin on 19 December 2018. However, due to land acquisition issues, it was pushed back to January 2019. On 30 January 2019, President Director of PT MRT Jakarta, William Sabandar announced that the groundbreaking ceremony is delayed again as the State Secretariat has yet to issue a land-use permit for the area near Medan Merdeka.[6] The groundbreaking ceremony for Phase 2 was finally held on 24 March 2019 and advanced works began in June 2019 near the future Monas station.[7]

Site works for contract CP201 were originally planned to begin in March 2020. However, due to the COVID-19 pandemic, it was pushed back three months, to June 2020.[8] Site works for contract CP203 began in September 2021.[9]

Route[]

Jakarta MRT set 11 departing from Lebak Bulus station
Jakarta MRT train departing from Bundaran HI station and approaching Blok M station
Region Jakarta - MRT Jakarta North South Line Icon.svg Station Name Transfers/Notes
Phase 2B (planned)
North Jakarta Ancol Barat Future terminal station
Koridor 5 Transjakarta Koridor 5 Transjakarta Koridor 5 Transjakarta (5H) K5-1 Ancol (planned)
Mangga Dua Koridor 12 Transjakarta (5K) K12-8 Mangga Dua (planned)
Phase 2A (under construction, operational by 2027)
West Jakarta Kota Future Phase 2A terminus

Kereta Api Indonesia Jakarta KRL C.svg Jakarta KRL B.svg Jakarta KRL TP.svg Jakarta Kota (planned)

Koridor 1 Transjakarta (4M) (5K) Koridor 9 Transjakarta Koridor 12 Transjakarta K1-20 Kota (planned)

Koridor 1 Transjakarta (4M) Koridor 9 Transjakarta K1-19 Glodok (planned)
Mangga Besar Koridor 1 Transjakarta (4M) Koridor 9 Transjakarta K1-17 Mangga Besar (planned)
Central Jakarta Sawah Besar Koridor 1 Transjakarta Koridor 9 Transjakarta (10H) K1-16 Sawah Besar (planned)
Harmoni Koridor 1 Transjakarta Koridor 2 Transjakarta Koridor 3 Transjakarta Koridor 5 Transjakarta (5H) (7F) Koridor 8 Transjakarta Koridor 8 Transjakarta Koridor 9 Transjakarta (10H) (12M) K1-15 Harmoni (planned)
Phase 2A (under construction, operational by 2025)
Central Jakarta Koridor 1 Transjakarta Koridor 2 Transjakarta Koridor 2 Transjakarta Koridor 2 Transjakarta Koridor 6 Transjakarta Koridor 6 Transjakarta (7F) Koridor 9 Transjakarta K1-14 Monas (planned)
Thamrin  M2  Planned interchange station to  M2 

Koridor 1 Transjakarta Koridor 6 Transjakarta Koridor 6 Transjakarta Koridor 9 Transjakarta Transjakarta K1-13 Bank Indonesia (planned)

Phase 1
Central Jakarta Bundaran HI Phase 1 terminus

Koridor 1 Transjakarta Koridor 6 Transjakarta Koridor 6 Transjakarta Koridor 9 Transjakarta K1-11 Bundaran HI

Dukuh Atas BNI Jakarta KRL L.svg Sudirman

Jakarta KRL A.svg BNI City

Jakarta LRT CB.svg Jakarta LRT BK.svg Dukuh Atas (U/C)

Koridor 1 Transjakarta (4C) Koridor 6 Transjakarta Koridor 9 Transjakarta (13C) K1-9 Dukuh Atas 1

Koridor 4 Transjakarta (L4) Koridor 6 Transjakarta K4-17 Dukuh Atas 2

Setiabudi Astra
Bendungan Hilir
Istora Mandiri Koridor 1 Transjakarta (4C) (13C) K1-5 Polda Metro Jaya
Senayan Koridor 1 Transjakarta (4C) Koridor 9 Transjakarta (10H) (13C) K1-3 Bundaran Senayan
South Jakarta ASEAN[10] Initially named 'Sisingamangaraja'

Koridor 1 Transjakarta (10H) (13C) K1-2 Masjid Agung

Koridor 1 Transjakarta (10H) K1-* CSW 3 (U/C)

Koridor 1 Transjakarta (10H) K1-* CSW 4 (U/C)

Koridor 13 Transjakarta (13A) (13B) (13C) (13D) (13E) (13F) K13-4 CSW 1 (U/C)

Blok M BCA Koridor 1 Transjakarta (4K) (10H) (13A) K1-1 Blok M

Bus Terminal Blok M Bus Terminal (via short walk)

Blok A
Haji Nawi
Cipete Raya
Fatmawati
Lebak Bulus Grab Terminal station

Koridor 8 Transjakarta K8-1 Lebak Bulus

Bus Terminal Lebak Bulus Bus Terminal (via short walk)

References[]

  1. ^ "Jakarta metro contracts signed". Railway Gazette International. 13 June 2013.
  2. ^ "Pengeboran Jalur "Underground" di MRT Fase I Sudah Selesai". 14 March 2017.
  3. ^ "MRT Jakarta focuses on constructing stations, depot". The Jakarta Post. Retrieved 1 December 2017.
  4. ^ "The News We've All Been Waiting For: Jakarta MRT Open for Public in March". Jakarta Globe. 22 February 2019.
  5. ^ "Operasional MRT Diresmikan Jokowi 24 Maret". CNN Indonesia. 18 March 2019.
  6. ^ "Groundbreaking MRT Fase II Molor (Lagi)". 30 January 2019.
  7. ^ "MRT Jakarta decides on Ancol as site of depot in Phase II construction". The Jakarta Post. Retrieved 20 June 2019.
  8. ^ "Imbas Corona, Proyek MRT Jakarta Fase 2 Diundur ke Juni 2020". Kompas. 29 April 2020.
  9. ^ "Akhir 2021, Konstruksi MRT Mangga Besar-Kota Dimulai". Investor ID. Retrieved 14 September 2021.
  10. ^ "Menjajal Ratangga, MRT Jakarta yang Diuji Coba Hari Ini". 12 March 2019.
Retrieved from ""