Line 22 (Guangzhou Metro)

From Wikipedia, the free encyclopedia
Line 22
 22 
Overview
Other name(s)South station express line (Chinese: 南站快线)
StatusUnder Construction
OwnerCity of Guangzhou
TerminiFangcun
Panyu Square
Stations8
Service
TypeRapid transit
SystemGuangzhou Metro
Services1
Operator(s)Guangdong Intercity
(Wholly-owned subsidiary of Guangzhou Metro Corporation)
History
OpenedEarly 2022 (Panyu Square—Chentougang section)
Technical
Line length18.2 km (11.3 mi) (Panyu Square—Chentougang section)[1]
30.8 km (19.1 mi)[2] (full Phase 1)
CharacterUnderground
Track gauge1,435 mm (4 ft 8+12 in)
Electrification25 kV 50 Hz AC overhead catenary
Operating speed160 km/h (99 mph)[3]
Route map

Legend
 11 
Left arrow clockwise
anti-clockwise Right arrow
Fangcun
 1   11 
Xilang
 1   10   Guangfo 
Chentougang Stabling Yard
Foshan Metro  2  Left arrow to
Guangzhou South Railway Station
 2   7  & Foshan Metro  2 
Panyu Square
 3   18 
 3  to Haibang Right arrow
Line 22 drawn to scale.

Line 22 of Guangzhou Metro (Chinese: 广州地铁22号线; pinyin: Guǎngzhōu Dìtiě Èrshí'èr Hào Xiàn) is a rapid transit express line under construction in Guangzhou.[4][5] It will run in a south-north direction, connecting Panyu Square and Guangzhou South Railway Station in Panyu District, Xilang and Fangcun in Liwan District.

Summary[]

Phase 1[]

The line runs approximately north-south, starting at Panyu Square in Panyu District and the end of the line at Fangcun; connecting Nansha and Fangcun, with a total length of 30.8 km (19.1 mi)[2] and 8 stations. The line is an express subway line using 8 car Type D trains with an operating speed of 160 km/h (99 mph).[6] Two distinct stopping patterns will be operated, a local all stop service and an express service. In early planning, Line 22 would interline with Line 18 south of Panyu Square to Wanqingsha.[7] This was later abandoned and Line 22 upon opening will terminate at Panyu Square but track connections between the two lines still exist.

North Extension[]

The North extension of Line 22 will be 41.1 km in length with 10 new stations, to Airport North (Terminal 2) in Huadu District of Guangzhou. It will be fully underground.[8] On December 31, 2021, the North Extension started construction.[9]

South Extension[]

In 2019, Dongguan municipal government proposed Line 22 to be extended east beyond Panyu Square to Nansha Subdistrict and cross the Shiziyang Channel into Dongguan and beyond to Shajing Town in northern Bao'an District, Shenzhen.[10][11] In 2020, Guangzhou Metro began soliciting bids to further investigate the extension of Line 22 into Dongguan and Shenzhen.[12] The first section of this extension a 58.5 kilometer segment from Panyu Square to Chang'an, Dongguan were officially included in Guangdong's 14th Five Year Plan in 2021 with provisions for future extension an connection with the Shenzhen Metro.[13][14]

When complete a number of different services and express and local stopping patterns will be operated, including Shenzhen/Dongguan to Baiyun Station, Nansha Passenger Ferry Terminal to Baiyun Airport North, Nansha Passenger Transport Port to Huacheng Street, etc.[15]

Opening time[]

Segment Commencement Length Station(s) Name
Chentougang — Panyu Square 2022 (Under testing) 18.2 km (11.3 mi)[1] 4 Phase 1
Fangcun — Chentougang TBA (Under construction) 12.6 km (7.8 mi) 4

Stations[]

Legend

  - Under testing, opening in early 2022
  - Under construction

Section Station
Station name[16][17] Connections Location
English Chinese
North ext. Airport North (Terminal 2) 机场北  3  Huadu
Airport South (Terminal 1) 机场南  3 
(Terminal 3) 机场东 Baiyun
Renhe 人和  3 
方石  18 
白云城市中心  18 
夏茅  24 
Baiyun Railway Station 白云站  8  (via Shitan)  12   24  Guangzhou Baiyun railway station TVQ
Guangzhou Railway Station 广州火车站  2   5   11   14  Guangzhou railway station GZQ Yuexiu
彩虹桥  8   11   13  Liwan
Phase 1 22 08 Fangcun 芳村  1   11 
22 07 Xilang 西塱  1   Guangfo 
22 06 南漖
22 05 南浦西 Panyu
22 04 陈头岗
22 03 Guangzhou South Railway Station 广州南站  2   7   Guangzhu  Guangzhou South railway station IZQ Mainline rail interchange  2 
22 02 市广路
22 01 Panyu Square 番禺广场  3   18 

References[]

  1. ^ a b "广州地铁18号线陇枕停车场首次迎接"活力橙"". 2021-02-20. 广州市2021年十件民生实事显示,2021年广州将力争开通试运营地铁18号线先通段(万顷沙-冼村,58.3公里)、22号线先通段(番禺广场-陈头岗,18.2公里)
  2. ^ a b "广州市轨道交通新线建设概况及进展". 2021-04-12.
  3. ^ "广州最高规格地铁——18号线、22号线计划2020年建成" (in Chinese). bendibao.com. 25 July 2017.
  4. ^ "壕气!投三千来亿,广州未来15年新建15条地铁线". . 2015-12-22. Archived from the original on 2015-12-23.
  5. ^ "广州新一轮地铁规划将杀到 15条线路详解". . 2015-12-22. Archived from the original on 2016-03-04.
  6. ^ "详细页". www.gzggzy.cn. Retrieved 2020-06-12.
  7. ^ "定了!地铁18号线、22号线首通段计划明年6月通车_广州日报大洋网". 2021-01-20. Archived from the original on 20 January 2021. Retrieved 2022-01-05.
  8. ^ "广州地铁18、22号线北延段有新进展". 2021-08-25. 广州地铁22号线北延段,线路起于芳村站(不含),止于机场北站,线路长约41.1公里,全地下敷设。新建10座车站
  9. ^ "芳村至白云机场城际项目正式动工!未来广州市中心与机场30分钟互达_广州日报大洋网". news.dayoo.com. Retrieved 2022-01-05.
  10. ^ "南沙未来已来!地铁22号线直通东莞,与深圳地铁18号线连接-广州搜狐焦点". gz.focus.cn. Retrieved 2022-01-05.
  11. ^ "这条"地铁",把穗佛莞连起来!_". 2020-08-08. Archived from the original on 8 August 2020. Retrieved 2022-01-05.
  12. ^ "粤港澳大湾区线网优化客流预测专题比选公告" (PDF). 广州公共资源交易中心. 2020-10-13.{{cite web}}: CS1 maint: url-status (link)
  13. ^ "广州市交通运输"十四五"规划" (PDF). 广州市交通运输局.{{cite web}}: CS1 maint: url-status (link)
  14. ^ ""十四五"时期广州拟建9条地铁_广州日报大洋网". news.dayoo.com. Retrieved 2022-01-05.
  15. ^ "白云机场45分钟到南沙!18号线北延段、22号线北延段最新曝光_广州日报大洋网". news.dayoo.com. Retrieved 2022-01-05.
  16. ^ "关于再次公开征求地铁二十二号线车站名称意见的公告". 2021-05-10.
  17. ^ "地铁二十二号线工程车站名称.doc". 2021-05-10. Archived from the original on 2021-05-10.
Retrieved from ""